Western Resources, Inc. v. Federal Energy Regulatory Commission, Pacific Gas and Electric Company, Intervenors

72 F.3d 147, 315 U.S. App. D.C. 229, 1995 U.S. App. LEXIS 36323
CourtCourt of Appeals for the D.C. Circuit
DecidedDecember 22, 1995
Docket93-1642, 94-1316
StatusPublished
Cited by11 cases

This text of 72 F.3d 147 (Western Resources, Inc. v. Federal Energy Regulatory Commission, Pacific Gas and Electric Company, Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Resources, Inc. v. Federal Energy Regulatory Commission, Pacific Gas and Electric Company, Intervenors, 72 F.3d 147, 315 U.S. App. D.C. 229, 1995 U.S. App. LEXIS 36323 (D.C. Cir. 1995).

Opinion

STEPHEN F. WILLIAMS, Circuit Judge:

In 1985 the Federal Energy Regulatory Commission embarked on a policy of “unbun- *149 dling” the sale and transportation of natural gas. See Order No. 436, Regulation of Natural Gas Pipelines After Partial Wellhead Decontrol, 50 Fed.Reg. 42,408 (1985). Its goal was to give gas consumers direct access to the competitive gas prices available at the wellhead. Because of the market power of interstate pipelines controlling transportation of the gas, and the inadequacy of their incentives to get the best wellhead prices, their customers had not previously—even though the Commission held the pipelines to prices based on cost—enjoyed the benefit of competitive prices. Indeed, as of 1985 the pipelines were subject to billions of dollars of “take-or-pay” obligations—duties under their gas purchase contracts either to take (and pay for) specified quantities of gas or to pay for them without taking them, at prices on average well above then-current market levels. See, e.g., Associated Gas Distributors v. FERC, 824 F.2d 981, 995 (D.C.Cir.1987) (“AGD I”).

While the unbundling policy gave customers direct access to the wellhead market for the future, a side effect was largely to disable the pipelines from recovering their existing supra-competitive contract costs. Customers could avoid these costs by buying directly in the gas market and using the pipelines only for transportation. Id. at 1025-26. In AGD I, we concluded that Order No. 436 had “abruptly and retroactively subjected [the pipelines to] risk.” Id. at 1027. We therefore remanded the order to the Commission to consider possible actions to mitigate the burden of take-or-pay liabilities on the pipelines.

The Commission responded to our remand in AGD I with Order No. 500, Regulation of Natural Gas Pipelines After Partial Wellhead Decontrol, 52 Fed.Reg. 30,334 (1987), which provided for recovery of take-or-pay costs through what the Commission called an “equitable sharing mechanism.” Under such a mechanism, a pipeline could, in exchange for agreeing to absorb a specific amount of its take-or-pay costs, recover an equal amount by means of a “direct bill” to its customers, i.e., a flat one-time charge as opposed to an increase in its commodity or demand charge. In Order No. 500 the Commission said that this surcharge would be allocated among a pipeline’s customers on the basis of “purchased gas deficiencies” during past periods, i.e.j the difference between their purchases in a “deficiency period” and their purchases in a prior “base period.” See Associated Gas Distributors v. FERC, 893 F.2d 349, 353 (D.C.Cir.1989) (“AGD II”).

Seeking to follow the Commission’s guidance in Order No. 500, Transwestern filed a tariff October 17, 1988, which culminated in a December 16, 1988 Commission order allowing Transwestern to impose a direct bill based on purchased gas deficiencies. Transwestern Pipeline Co., 45 FERC ¶ 61,427 (1988) (the “1988 Order”). In AGD II, however, we held that use of the purchased gas deficiency method violated the filed rate doctrine, which “forbids a regulated entity to charge rates for its services other than those properly filed with the appropriate federal regulatory authority.” 893 F.2d at 354-57; Ark. La. Gas Co. v. Hall, 453 U.S. 571, 577, 101 S.Ct. 2925, 2930, 69 L.Ed.2d 856 (1981). The Commission then issued Order No. 528, Mechanisms for Passthrough of Pipeline Take-or-Pay Buyout and Buydown Costs, 53 FERC ¶ 61,163 (1990), authorizing pipelines to allocate the take-or-pay burden in accordance with buyers’ “current contract demand.” Id. at 61,597. Transwestern accordingly refiled its tariff, seeking in effect to have the now-invalid 1988 Order replaced with one permitting a direct bill based on its customers’ 1988 contract demand. The Commission approved the filing. Transwestern Pipeline Co., 54 FERC ¶ 61,356 (1991) (the “1991 Order”), reh’g granted in part and denied in part, 64 FERC ¶ 61,145 (1993), reh’g denied, 66 FERC ¶ 61,287 (1994).

Petitioner Western Resources, Inc. is a customer of Williams Natural Gas Company, which in turn was a customer of Tran-swestern at the time of the 1988 Order, and remained a customer until February 1, 1989. Because of Commission rulings not here in dispute, Western will be subject to a direct bill from Williams for its share of the take- or-pay costs allocated to Williams under the 1991 Order. Western objects to the 1991 Order on the grounds of the filed rate doctrine. As a central purpose of the doctrine is to enable purchasers to “know in advance the consequences of the purchasing decisions they make,” Transwestern Pipeline Co. v. FERC, 897 F.2d 570, 577 (D.C.Cir.1990) *150 (“Transwestem I ”); see also Towns of Concord, Norwood, & Wellesley v. FERC, 955 F.2d 67, 75 (D.C.Cir.1992) (same), it requires that customers receive adequate notice of a rate in advance of the service to which it relates, see, e.g., Columbia Gas Transmission Corp. v. FERC, 831 F.2d 1135, 1140 (D.C.Cir.1987), order on reh’g, 844 F.2d 879 (1988).

Western argues first that the 1991 Order cannot be given effect because the 1988 Order it replaces failed to give timely notice. The 1988 Order, Western says, was conditional on Transwestern’s withdrawal of its judicial appeal of an earlier Commission ruling, and in fact Transwestern withdrew the appeal only on March 2,1989 — after Williams had ceased to be a customer of Transwest-ern. Thus, according to Western, Williams (and Western itself) did not receive adequate notice of the direct bill in the 1988 Order until after Williams had stopped buying gas from Transwestern altogether. Second, Western argues, as the direct bill in the 1991 Order uses 1988 contract demand, not the purchased gas deficiency method, the bill approved in 1991 so differs from that approved in 1988 that, again, there was no notice of the direct bill until after Williams had left the Transwestern system. Finally, as Williams at best had notice only on December 16,1988 of any direct bill for take-or-pay liabilities, it (and Western) should be liable only for liabilities accruing after that date and before its departure from the system. We reject these contentions and affirm the Commission’s decision.

Fulfillment of Condition in 1988 Order.

The 1988 Order approved Transwestern’s filing subject to the condition that Transwestern “inform the Commission within five business days ... of its election to pursue this filing or to pursue its pending judicial appeal.... ” 45 FERC ¶ 61,427 at 62,348 (emphasis added).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
72 F.3d 147, 315 U.S. App. D.C. 229, 1995 U.S. App. LEXIS 36323, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-resources-inc-v-federal-energy-regulatory-commission-pacific-cadc-1995.