Panhandle Eastern Pipe Line Company v. Federal Energy Regulatory Commission, Michigan Gas Utilities, Intervenors

95 F.3d 62, 320 U.S. App. D.C. 374
CourtCourt of Appeals for the D.C. Circuit
DecidedSeptember 10, 1996
Docket94-1728, 95-1131 to 95-1133, 95-1159, 95-1160, 95-1224 to 95-1226, 95-1130 and 95-1332
StatusPublished
Cited by10 cases

This text of 95 F.3d 62 (Panhandle Eastern Pipe Line Company v. Federal Energy Regulatory Commission, Michigan Gas Utilities, Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Panhandle Eastern Pipe Line Company v. Federal Energy Regulatory Commission, Michigan Gas Utilities, Intervenors, 95 F.3d 62, 320 U.S. App. D.C. 374 (D.C. Cir. 1996).

Opinion

GINSBURG, Circuit Judge:

In these consolidated petitions, five interstate natural gas pipelines and three of their customers request review of a series of orders issued by the Federal Energy Regulatory Commission concerning the appropriate allocation of production-related costs that the Pipeline Petitioners incurred from 1980 to 1983. We deny all but one of the petitions.

I. Background

In Title I of the Natural Gas Policy Act of 1978 the Congress capped the price of natural gas at the wellhead by setting the “maximum lawful price” for a “first sale” of natural gas. NGPA §§ 102-110, codified at 15 U.S.C. §§ 3312-3320 (1988), and repealed effective Jan. 1, 1993, by Pub.L. 101-60 § 2(b), 103 Stat. 158 (1989). Apparently concerned that this maximum lawful price scheme would discourage production of natural gas that might be especially expensive to produce, the Congress provided, in § 110(a) of the Act, that

... a price for the first sale of natural gas shall not be considered to exceed the maximum lawful price applicable to the first sale of such natural gas under this part if such first sale price exceeds the maximum lawful price to the extent necessary to recover—
(2) any costs of compressing, gathering, processing, treating, liquefying, or transporting such natural gas, or other similar costs, borne by the seller and allowed for, by rule or order, by the Commission.

The Congress also provided that an interstate pipeline that incurs such costs may recover them by means of a “[guaranteed passthrough” to its customers. NGPA § 601, as amended by Pub.L. 101-60 § 3(a)(7)(B) (1989), and codified at 15 U.S.C. § 3431(c).

In August 1980 the Commission did indeed rule, in Order No. 94, that natural gas producers could charge in excess of the otherwise maximum lawful price in order to recover such production-related costs, but it postponed the producers’ collection of these sums pending completion of a rulemaking proceeding in which the agency would determine how much to allow the producers to charge. Order Amending Interim Regulations Under the [NGPA] ..., 45 Fed.Reg. 53099 (1980) (Order No. 94). Two and a half years later (February 1983), the Commission issued an interim rule. Delivery Allowances Under Section 110 of the [NGPA] ..., 48 Fed.Reg. 5180 (Interim Rule). On the same day, in Order No. 94r-A, the Commission authorized natural gas producers to collect in equal installments from March 1983 through December 1984 the Order No. 94 costs they had incurred with respect to first sales between July 1980 and March 1983. Regulations Implementing Section 110 of the [NGPA] and Establishing Policy Under the Natural Gas Act, 48 Fed.Reg. 5152 (1983) (Final Rule and Order on Rehearing).

In November 1984, Natural Gas Pipeline of America petitioned the Commission for authority “to institute a special, one-time, lump-sum billing procedure to recover from its customers certain retroactive Order No. 94 ... payments ... made by Natural as of December 31,1984 ... in place of recovering these payments through the ... mechanism of Natural’s regular Purchased Gas Adjustment [PGA].” Natural Gas Pipeline of America, 30 FERC ¶ 61,138 (Letter Order). The Commission granted Natural’s petition in January 1985. Id. In September 1985 *65 the Pipeline Petitioners followed Natural’s lead, applying for and receiving Commission authorization to recover Order No. 94 costs incurred between August 1980 and February 1985 through a direct billing procedure whereby the Pipelines would pass these costs through to their customers in lump-sum bills based upon what the customers had purchased during that period. Transcontinental Gas Pipe Line Corp., 32 FERC ¶ 61,230, reh’g denied 33 FERC ¶ 61,213 (1985); Texas Eastern Transmission Corp., 32 FERC ¶ 61,493, reh’g denied 33 FERC ¶ 61,257 (1985); Texas Gas Transmission Co., 33 FERC ¶ 61,032 (1985), reh’g denied 33 FERC ¶ 61,359 (1986); Trunkline Gas Co., 33 FERC ¶ 61,217 (1985), reh’g denied 34 FERC ¶ 61,021 (1986); Panhandle Eastern Pipe Line Co., 33 FERC ¶ 61,218 (1985), reh’g denied 34 FERC ¶ 61,231 (1986); see also Panhandle, 62 FERC ¶ 61,130 at 61,832 (1993).

Under existing PGA tariff provisions, the Pipeline Petitioners could have recovered these costs prospectively by raising the rates charged to all customers in subsequent transactions. The costs incurred prior to February 1985 would then have been passed through to the pipelines’ customers based not upon their past purchases but upon their purchases from 1985 forward. See Panhandle, 62 FERC ¶ 61,130 at 61,832; see also Consolidated Edison Co. of New York v. FERC, 958 F.2d 429, 432-33 (D.C.Cir.1992); 18 C.F.R. §§ 154.301-310.

The Pipelines Petitioners no doubt preferred lump-sum direct billing because recovering Order No. 94 costs prospectively by raising commodity rates to all customers would have placed them at a competitive disadvantage relative to pipelines that had incurred lower (or no) Order No. 94 costs between 1980 and 1985 — i.e., pipelines that had not purchased as much gas from producers authorized to recover such expenses for first sales during that period. In Order No.94r-A the Commission had clearly expressed its understanding that some of the first purchasers of natural gas that would incur Order No. 94 costs would be interstate pipelines “that may receive compensation for paying these allowances through [their PGA] clauses.” 48 Fed.Reg. at 5152. The Commission nonetheless approved direct billing because, we are now told, it had subsequently become concerned that “permitting recovery of the past costs under the PGA would distort the newly competitive gas market that [the Commission] was attempting to foster.”

Columbia Gas Transmission Corp. and the Municipal Defense Group challenged the lump-sum direct-bill method of cost recovery, and in 1987 we held the method unlawful because it violated the filed rate doctrine. Columbia Gas Transmission Corp. v. FERC, 831 F.2d 1135 (“Columbia F). On remand the Commission concluded that it had the authority to waive the filed rate doctrine in the circumstances of this ease, and upon that basis reinstated its Orders approving the direct-bill method.

In 1988, the Commission ruled also that Panhandle Eastern Pipe Line could use the same method to pass along additional production-related costs that natural gas producers had been permitted to recover pursuant to Order No. 473. Panhandle, 44 FERC ¶ 61,173, reh’g denied 44 FERC ¶ 61,418 (1988); see also Compression Allowances and Protest Procedures Under NGPA Section 110, 52 Fed.Reg. 21660 (1987) (Final Rule). (Because the Commission and the Petitioners treat Order No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
95 F.3d 62, 320 U.S. App. D.C. 374, Counsel Stack Legal Research, https://law.counselstack.com/opinion/panhandle-eastern-pipe-line-company-v-federal-energy-regulatory-cadc-1996.