West Virginia Pulp & Paper Co. v. Peck

189 A.D. 286, 178 N.Y.S. 663, 1919 N.Y. App. Div. LEXIS 4647
CourtAppellate Division of the Supreme Court of the State of New York
DecidedNovember 12, 1919
StatusPublished
Cited by11 cases

This text of 189 A.D. 286 (West Virginia Pulp & Paper Co. v. Peck) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
West Virginia Pulp & Paper Co. v. Peck, 189 A.D. 286, 178 N.Y.S. 663, 1919 N.Y. App. Div. LEXIS 4647 (N.Y. Ct. App. 1919).

Opinion

Cochrane, J.:

Plaintiff is the owner of a dam seven hundred and ninety-six feet long across the Hudson river at Mechanieville. It also owns the land on both sides of the river at the termini of the dam. As originally constructed in the year 1882 the dam was sixteen feet high. In the year 1903 the Barge Canal Act was passed being chapter 147 of the Laws of that year which canalized (§3) the river from Waterford to Fort Edward. Notwithstanding that legislation the plaintiff in 1904 increased the height of its dam three feet. Subsequently the State in the construction of the Barge canal built lock No. 3 through the easterly end of the dam and dredged the bed of the river above and below the dam for the purposes of the canal. In doing so the State officers adopted the height of the dam at that time as the basis of construction and built the canal and lock to conform to the dam as it then existed. At about the time the canal and lock were completed, and in 1913, the plaintiff put flashboards on the dam raising it to a still greater height of two and one-half feet. These flashboards were removed by the defendants acting for and representing the State for the protection of the canal. The plaintiff thereupon instituted this action to restrain the defendants from interfering with its dam. It is found by the trial justice that by reason of the flashboards the Barge canal could not be safely navigated nor could the locks or canal structures withstand the water pressure and that they were jeopardized and their usefulness impaired. This finding is not criticised. From a judgment dismissing the complaint the plaintiff appeals.

The dam was built pursuant to chapter 406 of the Laws of 1882 which purported to authorize its construction. Chapter 683 of the Laws of 1900 was passed to legalize the erection [289]*289of the dam and purports to give the plaintiff’s predecessor certain rights in respect thereto. It has been found by the trial justice that neither of these acts operated to confer title to the plaintiff or its predecessor in respect to the river or its bed. It is unnecessary to consider the effect of either of those legislative enactments because the plaintiff expressly disclaims any rights thereunder except as they may have constituted a license or permission for the construction of the dam. The position of the plaintiff is stated in its brief as follows: “The act of 1900 did not, any more than the act of 1882, confer upon the plaintiff’s predecessor the right to maintain a dam. The plaintiff’s predecessor in title had the right to erect and maintain the dam irrespective of any legislative permission by virtue of its ownership of the uplands and the bed of a non-tidal, non-navigable stream. * * * The plaintiff does not and has not at any time claimed the ownership of the bed of the river by virtue of either of these acts.”

The plaintiff does contend, however, that even assuming the ownership of the State in the bed of the river the State could not interfere with the dam without legislative authority because it had granted its consent to the location of the dam in the river by the acts of 1882 and 1900 and that such consent has not been revoked. The Barge Canal Act (Laws of 1903, chap. 147) in section 3 specifically states: “The route of the Champlain canal as improved shall be as follows: Beginning in the Hudson river at Waterford, thence up the Hudson river canalized to near Fort Edward,” etc. Here is a distinct declaration of legislative authority to use the river for canal purposes and constitutes a revocation of any license or consent theretofore granted. The act of 1903 provides in what manner property may be appropriated for the construction of the canal and the plaintiff claims that because the State did not make its survey and map and file the same and otherwise comply with the methods and procedure specified by the statute that, therefore, there has been no appropriation and the State is a trespasser. Compliance with those statutory requirements was necessary only when the State appropriated the property of others. It was unnecessary for the State [290]*290to make an appropriation of land or water which it already owned. If it owned the bed of the river and had the right to navigate the waters of the river no appropriation of the same was necessary and the declaration by the Legislature of its intention to canalize the river was a sufficient revocation of any previous consent to the location of the dam in the river. Furthermore, I think the plaintiff entirely misses the point. The defendants have not interfered with the dam as it existed when the canal was constructed but only with changes made to the dam since the construction of the canal. In the construction of the canal and the lock through the dam and in conforming such construction to the dam as it then existed the State seems to have had the consent and acquiescence of the plaintiff. There is certainly no evidence of any protest or objection. We must here assume that the method of construction and the utilization of' the dam for the purposes of the canal and the adaptability of the latter to the former were mutually agreeable to the plaintiff and the State. The canal, therefore, was properly built with reference to the plaintiff’s dam and assuming the canal to be on the property of the State any change in the dam detrimental to the canal was unauthorized. The question is not as to the right of the State to interfere with the dam as it existed when the canal was built but the question is as to the right of the plaintiff to so change its dam after the canal was built as to destroy it or impair its usefulness. Any question as to the liability of the State for utilizing the dam is not presented on this appeal and we refrain from expressing any opinion in reference thereto. On the record here presented we are required to assume that the plaintiff acquiesced in the use of its dam by the State and liability of the State for so doing is not now an issue. But assuming that the bed of the river was owned by the State and assuming as we must from this record that there was an acquiescence by the plaintiff in the utilization of its dam by the State for the purposes of the canal no trespass was committed by the defendants in removing the flashboards placed on the dam after the construction of the canal.

The plaintiff further contends that the State never had title to the bed of the river at the site of the dam because [291]*291of the effect of two colonial patents before New York became a State. Before considering those patents it is appropriate to consider the question of the navigability of the Hudson river at the locus in quo because on this question depends largely the effect of those patents as to whether or not they carried the title of the adjoining uplands to the thread of the stream in the absence of language indicating such a purpose. (Fulton Light, Heat & Power Co. v. State of New York, 200 N. Y. 400, 413; Danes v. State of New York, 219 id. 67; People v. Page, 39 App. Div. 110.) The plaintiff strenuously urges that the river at Mechanicville is not navigable. There is much judicial literature on the navigability of the Hudson above tidal influence and the Mohawk and the question I think is settled and justifies little discussion from an original standpoint. I shall, therefore, merely refer to a few cases which seem to bear with special pertinency on the situation at Mechanicville. Stillwater is less than three miles above the plaintiff’s dam. Between the two places are Fonda’s Rapids mentioned in the evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Federal Energy Regulatory Commission
954 F.2d 56 (Second Circuit, 1992)
City of New York v. Brooklyn Borough Gas Co.
201 Misc. 672 (New York Supreme Court, 1951)
New York Power & Light Corp. v. State
230 A.D. 338 (Appellate Division of the Supreme Court of New York, 1930)
People v. New York & Ontario Power Co.
219 A.D. 114 (Appellate Division of the Supreme Court of New York, 1927)
Little Falls Fibre Co. v. Henry Ford & Son, Inc.
126 Misc. 126 (New York Supreme Court, 1925)
Waterford Electric Light, Heat & Power Co. v. State
208 A.D. 273 (Appellate Division of the Supreme Court of New York, 1924)
Waterford Electric Light, Heat & Power Co. v. State
117 Misc. 480 (New York State Court of Claims, 1921)
Thompson v. Fort Miller Pulp & Paper Co.
14 Misc. 477 (New York Supreme Court, 1920)
West Virginia Pulp & Paper Co. v. Peck
190 A.D. 891 (Appellate Division of the Supreme Court of New York, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
189 A.D. 286, 178 N.Y.S. 663, 1919 N.Y. App. Div. LEXIS 4647, Counsel Stack Legal Research, https://law.counselstack.com/opinion/west-virginia-pulp-paper-co-v-peck-nyappdiv-1919.