[Cite as Wells v. Right Choice Contracting, L.L.C., 2026-Ohio-117.]
COURT OF APPEALS OF OHIO
EIGHTH APPELLATE DISTRICT COUNTY OF CUYAHOGA
MARIO WELLS, :
Plaintiff-Appellant, : No. 114802 v. :
RIGHT CHOICE CONTRACTING, LLC, : ET AL., : Defendants-Appellees.
JOURNAL ENTRY AND OPINION
JUDGMENT: AFFIRMED IN PART, REVERSED IN PART, AND REMANDED RELEASED AND JOURNALIZED: January 15, 2026
Civil Appeal from the Cuyahoga County Common Pleas Court Case No. CV-23-976984
Appearances:
Myers Law, LLC, and Daniel J. Myers, for appellant.
McMillan & Sobel, LLC, and Jonathan F. Sobel, for appellee.
MICHELLE J. SHEEHAN, A.J.:
{¶ 1} In 2020, plaintiff-appellant Mario Wells (“Wells”) purchased a home
utilizing a Federal Housing Administration (“FHA”) sponsored 203(k)
rehabilitation loan that provides financing for both the purchase and rehabilitation of a borrower’s primary residence. As part of this federal program, Wells was
required to hire a draw inspector to verify progress and quality of construction to
demonstrate to the lender that it was appropriate to pay contractors working on the
project. Defendant-appellee Keith Bowman (“Bowman”) was the draw inspector
hired by Wells. Multiple disputes involving several parties took place throughout
the construction process culminating in this lawsuit. This appeal only addresses the
issues between Wells and Bowman.
{¶ 2} After a bench trial, the trial court found Bowman not liable on all
remaining claims asserted against him. Wells appeals raising three assignments of
error:
(1) The trial court committed reversable [sic] error when it concluded that the Consumer Sales Practices Act (CSPA) and Summit County Consumer Protection Ordinance (SCCPO) did not apply to the transaction between consumer Mario Wells and his paid consultant Keith Bowman.
(2) The trial court committed reversable [sic] error when it failed and refused to consider or admit the HUD handbook to establish for reasons other than impeachment.
(3) The trial court committed reversable [sic] error when it determined that Keith Bowman did not breach his contract with Mario Wells.
{¶ 3} Based on our review of the record and relevant legal authority, we
conclude that the trial court erred in finding the Ohio Consumer Sales Practices Act
(“OCSPA”) and the Summit County Consumer Protection Ordinance (“SCCPO”)
inapplicable to this matter on the sole basis that Bowman was not a “supplier” or
“person” as defined by the respective statutes. We also find that the trial court did not abuse its discretion in refusing to admit the FHA/HUD handbook (the
“Handbook”) for purposes other than impeachment because the Handbook does not
provide a basis for a breach-of-contract claim between private individuals.
Regarding assignment of error No. 3, we reverse the trial court’s decision because
its conclusion that Bowman was not liable on Wells’s breach-of-contract claim is not
based on the contractual agreements existing between Wells and Bowman.
{¶ 4} Accordingly, this matter is affirmed in part, reversed in part, and
remanded to the trial court for proceedings consistent with this opinion.
I. Procedural History and Relevant Facts1
A. Factual Background
{¶ 5} In 2020, Wells purchased a home for his family in Cleveland Heights,
Ohio through an FHA program known as a “203(k) loan” that provides financing to
a borrower for both the purchase and rehabilitation of their primary residence.2 As
part of this process, the FHA requires borrowers such as Wells to hire what is
generally referred to as a “HUD consultant.” Bowman was the HUD consultant
hired by Wells.
1 The underlying lawsuit involves multiple parties and causes of action that have
no impact on our resolution of this appeal. Thus, we will limit our discussion to the procedural and substantive facts related to the dispute between Wells and Bowman.
2 Specifically, the term 203(k) loan refers to HUD-administered loans pursuant to
Section 203(k) of the National Housing Act, 12 U.S.C. 1709(k), and the regulations promulgated thereunder. See generally 24 C.F.R. 203.440 et seq. {¶ 6} Bowman had two roles in Wells’s 203(k) funded home purchase and
rehabilitation (hereinafter referred to as the “project”). Initially, Wells hired him as
a “consultant” to perform the initial property inspection and prepare written
specifications identifying the type and cost of the repairs and remodeling planned
on the project. This information was required by the FHA and the lender to
demonstrate the property’s suitability for the 203(k) loan program or, in other
words, so that Wells could be approved for the 203(k) loan. Bowman’s role as a
consultant ended once the 203(k) loan was accepted by the FHA and the lender.
This dispute does not involve Bowman’s actions as a consultant.
{¶ 7} After the closing of the 203(k) loan, Bowman’s role on the project
transitioned to “draw inspector.” In general, as a draw inspector, Bowman
periodically inspected the project to verify the progress and quality of the work
completed in order to certify to the lender that it was appropriate to pay contractors
from the loan proceeds.3 Bowman prepared and certified three draw requests on
this project totaling $41,613. Upon completion of the third draw request, Bowman
did no further work on the project.
3 “A ‘draw inspection’ is an inspection completed and submitted to a bank in order
to release funds for disbursement during a home rehabilitation or construction. The draw inspection verifies that certain phases of a home renovation/construction project have been completed and that materials required for renovation/construction are purchased on a specific schedule to keep the project moving. A draw inspection confirms that the construction benchmarks have been completed or, in the alternative, reports what has not been completed in a given time.” Billups v. B.C. Ent. Group, Inc., 104 So.3d 577, 578, fn. 2 (4th Cir. La. 2012). {¶ 8} Bowman’s actions (or inaction) as the project’s draw inspector
provide the basis for the dispute between Wells and Bowman. Specifically, Wells
contends that Bowman failed to inspect the project, improperly certified work that
was not yet completed on the project, or certified work completed but not done in a
workmanlike manner. Wells also argues that Bowman failed to ensure that the
project had all required permits.
B. Procedural History
{¶ 9} In March 2023, Wells filed a lawsuit against multiple parties involved
in the project including Bowman. Specifically, Wells asserted claims for breach of
contract, negligence, violation of the OCSPA, and violation of the SCCPO against
Bowman. Bowman filed a counterclaim against Wells for his attorney fees and costs.
The underlying matter proceeded with motion practice and discovery.
{¶ 10} In November 2024, a bench trial was conducted on the claims
asserted by Wells against Bowman as well as his fraud claim against defendant
Timothy Kingsbury (“Kingsbury”) who worked for one of the mortgage companies
involved in this matter. At the conclusion of the bench trial, the parties stipulated
to the dismissal of Wells’s negligence claim against Bowman. Wells’s fraud claim
against Kingsbury was dismissed with prejudice. Additionally, Bowman’s
counterclaim for attorney fees and costs was dismissed pursuant Wells’s motion for
directed verdict on the grounds that no evidence was offered regarding the claim.
Wells’s remaining claims against Bowman for breach of contract and violation of the
OCSPA and SCCPO were taken under consideration by the trial court. In January 2025, the trial court issued its decision in a six-page opinion finding Bowman not
liable on Wells’s claims against him. Wells appeals this decision.
II. Law and Analysis
{¶ 11} Our appellate review of a bench trial is as follows:
“In a civil appeal from a bench trial, we apply a manifest weight standard of review, guided by a presumption that the trial court’s findings are correct. Seasons Coal v. Cleveland, 10 Ohio St.3d 77, 79- 80, 461 N.E.2d 1273 (1984). A judgment supported by some competent, credible evidence going to all the material elements of the case will not be reversed as being against the manifest weight of the evidence. C.E. Morris Co. v. Foley Constr. Co., 54 Ohio St.2d 279, 376 N.E.2d 578 (1978), syllabus. Where, however, the trial court’s decision is based upon a question of law, we review the trial court’s determination of that issue de novo. See, e.g., Taylor Bldg. Corp. of Am. v. Benfield, 117 Ohio St.3d 352, 2008-Ohio-938, 884 N.E.2d 12, ¶ 34 (‘Courts review questions of law de novo.’). ‘A finding of an error of law is a legitimate ground for reversal, but a difference of opinion on credibility of witnesses and evidence is not.’ Seasons Coal at 81.”
TLOA Acquisitions, L.L.C. v. Unknown Heirs, 2021-Ohi0-3678, ¶ 11 (8th Dist.),
quoting 3637 Green Rd. Co. v. Specialized Component Sales Co., 2016-Ohio-5324,
¶ 19 (8th Dist.).
{¶ 12} For ease of discussion, we will first address assignment of error No. 3.
A. Assignment of Error No. 3 – Breach of Contract
{¶ 13} In assignment of error No. 3, Wells argues that the trial court erred
in finding Bowman not liable on his breach-of-contract claim. In making this
decision, the trial court determined that Wells had not substantially performed his
own obligations under the parties’ contract. As a result of this finding, the trial court
made no further findings of fact or conclusions of law regarding the remaining elements of the breach-of-contract claim. For the following reasons, we sustain this
assignment of error, reverse the decision below, and remand this matter to the trial
court for further proceedings consistent with our forthcoming construction and
interpretation of the parties’ contract.
1. General Contract Principles
{¶ 14} “In general terms, a contract is ‘an agreement upon sufficient
consideration between two or more persons to do or not to do a particular thing.’”
Sheaffer v. Rowland, 1992 Ohio App. LEXIS 6590, *2 (3d Dist. Dec. 29, 1992),
quoting 17 Ohio Jur.3d, Contracts, § 2 (1979). In legal terms, “‘“[a] contract is
generally defined as a promise, or a set of promises, actionable upon breach.”’”
Rayess v. Educational Comm. for Foreign Med. Graduates, 2012-Ohio-5676, ¶ 19,
quoting Kostelnik v. Helper, 2002-Ohio-2985, quoting Permuter Printing Co. v.
Strome, Inc., 436 F.Supp. 409, 414 (N.D. Ohio 1976). A contract is only binding
upon the parties to the contract. Am. Rock Mechanics, Inc. v. Thermex Energy
Corp., 80 Ohio App.3d 53, 58 (8th Dist. 1992). Further, “only a party to a contract
or an intended third-party beneficiary may bring an action on a contract in Ohio.”
Grant Thornton v. Windsor House, 57 Ohio St.3d 158, 161 (1991); accord Stride
Studios, Inc. v. Alsfelder, 2023-Ohio-1502, ¶ 20 (1st Dist.). “In order for a third
person to enforce a promise made for his benefit, it must appear that the contract
was made or entered into directly or primarily for the benefit of such third person.”
Koster v. Chowdhury, 2016-Ohio-5704, ¶ 8 (8th Dist.). {¶ 15} To establish a breach-of-contract claim, a party is required to
demonstrate that (1) a contract existed; (2) they fulfilled their obligations under the
contract; (3) the other party breached their obligations under the contract; and
(4) damages resulted from this breach. See, e.g., Re/Max Crossroads Props. v.
Roberts, 2013-Ohio-5575, ¶ 11 (8th Dist.) (identifying the essential elements of a
breach-of-contract claim). The failure to establish any one of these essential
elements is fatal to the cause of action. See, e.g., Brock v. Servpro, 2022-Ohio-158,
¶ 31 (12th Dist.) (Breach of contract failed because the essential element of damages
was not established.). A breach-of-contract claim is generally reviewed under a
manifest-weight-of-the-evidence standard. See, e.g., Schaste Metals v. Tech
Heating & Air Conditioning, 1997 Ohio App. LEXIS 3543, *3-4 (8th Dist. Aug. 7,
1997). However, the construction of a contract and the interpretation of its terms
and conditions are questions of law for the court. Bd. of Cty. Commrs. v. Hardlines
Design Co., 2021-Ohio-1832, ¶ 8 (2d Dist.), citing Alexander v. Buckeye Pipeline
Co., 53 Ohio St.2d 241 (1978), paragraph one of the syllabus.
{¶ 16} “A written contract must be construed and interpreted from its four
corners without consideration of parol evidence.” Morris Novak Realty Co. v.
Gibbons, 1993 Ohio App. LEXIS 2684, *8 (8th Dist. May 27, 1993). “If the language
of a contract is plain and unambiguous, we must enforce the terms as written, and
we may not turn to evidence outside the four corners of the contact to alter its
meaning.” Beverage Holding, L.L.C. v. 5701 Lombardo, L.L.C., 2019-Ohio-4716,
¶ 13. “If a contract is clear and unambiguous, then its interpretation is a matter of law and there is no issue of fact to be determined.” Nationwide Mut. Fire Ins. Co.
v. Guman Bros. Farm, 73 Ohio St.3d 107, 108 (1995), quoting Inland Refuse
Transfer Co. v. Browning-Ferris Industries of Ohio, Inc., 15 Ohio St.3d 321, 322
(1984).
{¶ 17} “However, if ambiguities exist, issues of fact arise which may require
the court to look outside the four corners of the document.” Std. Elec. Co. v. Bd. of
Cty. Commrs., 1988 Ohio App. LEXIS 1907, *4 (8th Dist. May 19, 1988). “Terms in
a contract are ambiguous when they are susceptible to more than one reasonable
interpretation.” Tera, L.L.C. v. Rice Drilling D, L.L.C., 2024-Ohio-1945, ¶ 12. “It is
generally the role of the fact-finder to resolve any ambiguity in a contract.” Id. In
other words, “whether a contract is ambiguous is a question of law, but the
resolution of an ambiguous term in a contract is a question of fact.” Id.
{¶ 18} With these well-settled guiding principles in mind, we turn to the
facts of this case.
2. The Existence of a Contract and Its Terms
{¶ 19} The parties do not dispute the existence of a contract between them.
Rather, they dispute what document (or documents) constitute the contract
between them. They also dispute what contractual obligations they may owe to one
another under that agreement. Consequently, we must first determine what
document and/or documents govern the parties’ contractual relationship as well as
the contractual obligations set forth thereunder. {¶ 20} Throughout this case, the parties as well as the trial court have
referred to several documents contained in the 203(k) loan package as purporting
to create the contractual obligations between Wells and Bowman. Both the trial
court and Bowman primarily rely on the “Rehabilitation Loan Agreement” to impose
upon Wells the obligation to ensure that all necessary permits were obtained on the
project and to cause all improvements to be made in a workmanlike manner.
Indeed, the trial court’s conclusion that Wells failed to substantially perform his
contract with Bowman is based on his alleged failure to satisfy these terms.
{¶ 21} But our review of the plain and unambiguous language of the
Rehabilitation Loan Agreement reveals that it is a contract only between Wells and
the lender. Bowman is not a party to the contract. Accordingly, pursuant to well-
established law, Bowman is not entitled to enforce any obligations Wells may have
had thereunder.4
{¶ 22} The same analysis applies to Bowman’s reliance on the document
titled “203(k) Borrower’s Acknowledgement” to support Wells’s obligation to ensure
proper permits were obtained and to make sure the work done on the project was
completed in a workmanlike manner. The plain and unambiguous language of this
document also demonstrates that it is not a contract between Bowman and Wells,
but rather it is an agreement between Wells and the lender. Again, Bowman is not
a party to this contract and, therefore, he has no enforceable rights thereunder.
4 Bowman has not raised the issue of third-party beneficiaries either below or
before this court, and we will not address it here now. {¶ 23} Bowman also refers to the 203(k) loan program document titled
“Draw Requests” to demonstrate Wells’s contractual obligations to him. Yet, the
unambiguous terms of this document reveal that it is not a contract. Specifically, it
is not an agreement between Bowman and Wells to do or not to do something. No
promises are exchanged between them. Rather, the document is akin to an affidavit
where, in this case, Bowman and Wells are independently certifying to the lender
the truth of the facts stated in the document — that work on the project is completed,
it is completed in a workmanlike manner, and therefore it is appropriate to pay the
contractors for their work. Simply put, it is not a contract.
{¶ 24} Our review of the record locates two documents signed by both
Bowman and Wells in this matter: “A Consultant’s & Client’s Limitation of Liability
of Agreement” and “Consultant’s Allowable Fee Agreement.” See Appendix. In the
“Consultant’s & Client’s Limitation of Liability Agreement,” Bowman agrees to
“become[] an inspector for the draws” after the closing of the loan and agrees to
“assist the client [Wells] in the preparation of . . . the HUD required form for the
draw request.” In turn, Wells agrees to pay Bowman for his services. The
“Consultant’s Allowable Fee Agreement” confirms the work that Bowman will
perform on the project and Wells’s promise to pay him for his services.
{¶ 25} The unambiguous language of these two agreements demonstrates
that they are both contracts and that Wells and Bowman are the parties to these
contracts. Notably, neither of these documents expressly incorporates by reference
any of the other loan documents either discussed above or elsewhere in the record. Further, the record demonstrates that there are no other agreements signed by both
Wells and Bowman in this case. Accordingly, we find that it is these two documents
that constitute the parties’ contract.
{¶ 26} Turning to the parties’ contractual obligations under these two
agreements, we find that the agreements are, in part, ambiguous. Specifically, we
conclude that the term “assist” as used in the “Consultant’s & Client’s Limitation of
Liability Agreement” is ambiguous. In other words, the contract is ambiguous as to
what “assist” means in reference to Bowman’s promise to assist Wells in the
preparation the HUD-required form for the draw request. It is unclear from the
plain and unambiguous language of the agreement what exactly Bowman agreed to
do as part of his assistance. Additionally, it is unclear from the plain and
unambiguous language of the agreement what, if any, reciprocal obligations were
placed on Wells as part of Bowman’s duty to assist him.
{¶ 27} Because the resolution of contract ambiguity is for the factfinder, we
remand this matter to the trial court to answer these questions as well as consider
the remaining elements of a breach-of-contract claim under these governing
documents. In other words, the trial court must first determine what Bowman
promised to Wells and, in turn, what Wells promised to Bowman under the
Consultant’s & Client’s Limitation of Liability Agreement and the Consultant’s
Allowable Fee Agreement. Then, the trial court should determine whether either or
both of them performed their respective obligations as well as consider the issue of
damages, if any. {¶ 28} Based on the above, we sustain assignment of error No. 3. The trial
court’s decision finding Bowman not liable on Wells’s breach-of-contract claim is
reversed, and this matter is remanded to the trial court for further proceedings
consistent with this decision. In particular and in light of the contractual framework
set forth above, the trial court should decide what the term “assist” means with
regard to the parties’ contractual obligations to one another, whether Wells
substantially performed his obligations, and whether Bowman breached his
obligations as well as consider the issue of damages if necessary.
B. Assignment of Error No. 1 – Violation of OCSPA and SCCPO
{¶ 29} In his first assignment of error, Wells argues that the trial court erred
in its determination that Bowman was not a “supplier” as defined by R.C. 1345.01(C)
of the OCSPA or a “person” as defined by 759.02(g) of the SCCPO. The trial court’s
decision is based on its conclusion that the transaction between Wells and Bowman
was not for purposes that are primarily personal, family, or household because
Bowman’s services were for the benefit of the lender and government and not Wells,
individually. Therefore, it was not a consumer transaction as defined under these
statutes. Because it determined that Bowman was not a supplier or person, the trial
court concluded that both laws were inapplicable to the case at bar. Accordingly, the
trial court found Bowman not liable and made no further findings of fact or
conclusions of law regarding these two claims. We find Wells’s first assignment of
error well-taken. {¶ 30} Our review of this decision requires us to interpret provisions of both
the OCSPA and SCCPO. It is well settled law that the interpretation and
construction of statutes involves questions of law that we review de novo. Clay v.
Galita, 2024-Ohio-833, ¶ 12 (8th Dist.). Absent ambiguity, we must give effect to
the plain meaning of the statute and the words used in either must be accorded their
usual, normal, and customary meaning. Id., citing State ex rel. Pennington v.
Gundler, 75 Ohio St.3d 171, 173 (1996); R.C. 1.42. Additionally, the “‘Ohio
Consumer Sales Practices Act is a remedial law designed to provide various civil
remedies to aggrieved consumers and must be liberally construed pursuant to
R.C. 1.11.’” (Emphasis deleted.) Hanna v. Groom, 2008-Ohio-765, ¶ 34 (10th
Dist.), quoting State ex rel. Celebrezze v. Hughes, 58 Ohio St.3d 273, 275 (1991).
{¶ 31} The OCSPA provides that no “supplier” shall commit an unfair,
deceptive, or unconscionable act or practice in connection with a consumer
transaction. R.C. 1345.02(A) and 1345.03. Likewise, SCCPO 759.05 prohibits
unfair or deceptive trade practices by “persons.” These are defined terms under
both laws. Because these statutes are nearly identical, we will focus our discussion
on the OCSPA.
{¶ 32} R.C. 1345.01 defines a “supplier” as follows:
(C) “Supplier” means a seller, lessor, assignor, franchisor, or other person engaged in the business of effecting or soliciting consumer transactions, whether or not he deals directly with the consumer.
In turn, R.C. 1345.01 defines a “consumer transaction” as follows: (A) “Consumer transaction” means a sale, lease, assignment, award by chance, or other transfer of an item of goods, a service, a franchise, or an intangible, to an individual for purposes that are primarily personal, family, or household, or solicitation to supply any of these things.
These two definitions are intertwined, and both must be satisfied when
determining whether Bowman is a supplier under the OCSPA. Specifically, based
on the unambiguous language of these two definitions, our determination of
whether Bowman was a supplier is dependent upon (1) whether he was a “seller”
or “other person” engaged in the business of effecting or soliciting “consumer
transactions” (R.C. 1345.01(C)) and (2) whether there was a “sale” of “service” to
an individual for “primarily personal, household, or family purposes.”
(R.C. 1345.01(A)).
1. Bowman’s Answer
{¶ 33} Wells argues that Bowman admitted his status as a supplier under the
OCSPA in his answer. Indeed, “we know it to be elementary in the law of pleading
that an admission in a pleading dispenses with proof and is equivalent to proof of
the fact.” Duffy v. Cleveland Coin Machine Exchange, Inc., 1956 Ohio App. LEXIS
774, *6 (8th Dist. Dec. 6, 1956), citing 3 Jones Commentaries on Evidence, § 922
(2d Ed. 1912). “Because ‘an admission to a factual allegation in a pleading is
equivalent to proof of the fact admitted, the plaintiff does not have to prove that
allegation with evidence.’” State v. Jimenez, 2023-Ohio-4317, ¶ 18 (8th Dist.),
quoting Lopez v. Quezada, 2014-Ohio-367, ¶ 12 (10th Dist.). However, “allegations
concerning legal conclusions arising from certain facts are not admitted.” PNC Bank v. Kereszturi, 2015-Ohio-957, ¶ 17 (8th Dist.). In other words, to be binding, “‘the
admission must be a material and competent fact, not merely a legal conclusion or
statutory definition.’” Ohio Valley Assn. Builders & Constr. v. Rapier Elec., Inc.,
2014-Ohio-1477, ¶ 36, quoting Internatl. Bhd. of Elec. Workers, Local Union No. 8
v. Kingfish Elec., L.L.C., 2012-Ohio-2363, ¶ 20 (6th Dist.).
{¶ 34} With this authority in mind, we will review the complaint and answer
to determine whether Bowman admitted any material and competent facts that may
impact whether we conclude the definitional terms of R.C. 1345.01 are satisfied.
Paragraphs 5 and 10 of Wells’s complaint state:
(5) Defendant Bowman was the 203k consultant hired by Mario Wells and paid by Mario Wells to provide consulting services and inspection during the project at his home with both Capgro Defendants and Right Choice Defendants . . . .
...
(10) Mario Wells is an individual, and a consumer as that term is defined in R.C. 1345.01, who purchased and owned his residence outlined in the caption of the Complaint in Cleveland Heights, Ohio (“Property” or “Project”). Mario is married to Ciearra Wells, and Mario purchased services from various Defendants, except Kingsbury, and he purchased those services primarily for personal, family, or household use.
(16) Defendant Bowman is a resident of the State of Ohio, and upon information and belief is a 203k consultant. He is in the business of providing services to consumers who are purchasing remodeling services financed by a 203k loan, like Mario Wells. He sold these services to Mario Wells. In paragraphs 3, 7, and 9 of his answer, Bowman admits these allegations.
Additionally, paragraph 17 of Wells’s complaint states:
(17) At all times relevant, all Defendants interacted directly with Mario Wells by communicating with him in writing or otherwise, performing services, charging for services, and otherwise committing the acts or omissions outlined herein.
In paragraph 10 of his answer, Bowman stated, “Defendant Bowman admits that
on occasion he interacted directly with Plaintiff Mario Wells and admits
performing and charging for services rendered but otherwise denies the allegations
contained in said paragraph for want of knowledge.”
{¶ 35} Based on these answers, we conclude that Bowman has admitted the
following material facts: (1) he was a seller; (2) in the business of; (3) selling services;
(4) to individuals; and (5) he sold these services to Wells. See, e.g., Vannes v.
Bigelow, 1989 Ohio App. LEXIS 2831, *4-5 (6th Dist. July 21, 1989) (defendant
admitted to the sale of goods and services in his answer). These admissions of fact
partially satisfy the definitional requirement of a “supplier” under the OCSPA.
Bowman could not admit that the transaction was “for purposes that are primarily
personal, family or household” because that is a legal conclusion that belongs to the
court. See id. (Court determined whether the sale was for primarily for personal,
family, or household purposes.).
2. Purposes That Are Primarily Personal, Family, or Household
{¶ 36} The remaining question for us is whether Bowman’s sale of his
services as an inspector for draws to Wells was “for purposes that are primarily personal, family, or household.” The trial court determined that Bowman “did not
have a primary purpose of providing real or personal services to a primary
individual; rather the 203(k) consultant is providing services to corporate entities
insuring a risky investment.” However, when answering this question, courts look
to the “purpose” manifested by the purchaser and not the alleged supplier’s purpose
in providing the service or good. See Griffin v. Crestview Cadillac, 2009-Ohio-
6569, ¶ 22 (10th Dist.) (Courts examine the objective manifestations of the
purchaser regarding how they intended to use the purchased item.); Ford Motor
Credit Co. v. Ryan, 2010-Ohio-4601, ¶ 77 (10th Dist.); Tomas v. George P. Ballas
Leasing, 1986 Ohio App. LEXIS 8463, *9 (6th Dist. Sept. 30, 1986). In other words,
it is the motivation of the purchaser for obtaining the good or service that is
determinative of its purpose under the statute and not the motivation of the supplier
in selling the good or service. Simply put, the question is whether Wells as the
purchaser of the good or service intended to use the good or service for business or
personal purposes. See generally Ford Motor Credit Co. at ¶ 77; Griffin at ¶ 21.
{¶ 37} The record below establishes that Wells purchased the subject
property with the intent to use it as his family’s home. In fact, a 203(k) loan can only
be used for the purchase and rehabilitation of a borrower’s primary residence. Wells
engaged and paid Bowman for his services as part of this process. Specifically,
Bowman sold Wells his services as a draw inspector to assist Wells with completing
the renovation of his family home in compliance with the requirements of the 203(k) loan program. It logically follows that Wells’s intent in obtaining Bowman’s services
was primarily for purposes that were personal, family, or household.
{¶ 38} Further, regarding the trial court’s conclusion that Bowman was not
a supplier because his services were for the benefit of third parties, we do not
interpret the OCSPA so narrowly. The plain language of the statute does not contain
any requirement that the services rendered by a supplier be for the sole benefit of
the consumer. Neither does the trial court nor Bowman offer any Ohio legal
authority interpreting the statute in this fashion. The record below demonstrates
that Bowman’s services benefited Wells in the purchase and rehabilitation of his
home. Under the unambiguous language of the statute, it is irrelevant that his
services may have also benefitted third parties.
{¶ 39} Bowman and the trial court, in part, rely on two cases as support for
their conclusion that he is not a supplier. This court is unpersuaded by either of
these cases. Both Brown v. Countrywide Home Loans, Inc., 319 B.R. 278, 280 (D.C.
2004), and Diehl-Guerrero v. Hardy Boys Constr., LLC, 2017 Del.Super. LEXIS
105, *1 (Del. Super. Feb. 28, 2017), involved negligence actions between a
homeowner and a HUD consultant in a 203(k) loan program, among other parties.
Specifically, the courts answered whether the HUD consultant owed any duty to the
homeowner. Brown at 280; Diehl-Guerrero at *1, 5. Both courts concluded that no
duty existed, in part, because the HUD consultant’s role was to protect or for the
benefit of the government and lender. Brown at 287; Diehl-Guerrero at *7-8. Thus,
the negligence actions were dismissed. Brown at 287; Diehl-Guerrero at *8. {¶ 40} Both cases were limited to negligent actions. Moreover, neither case
involved nor addressed in any fashion similar unfair and deceptive state causes of
action. A violation of the OCSPA is a separate and distinct statutory cause of action.
Accordingly, we do not find these cases persuasive in determining whether Bowman
was a supplier under the OCSPA.
{¶ 41} “A violation of the CSPA is premised on the existence of a supplier, a
consumer, and a consumer transaction.” Williams v. Edwards, 129 Ohio App.3d
116, 121 (1st Dist. 1998), citing R.C. 1345.02 and 1345.03. Based on the above, we
find that Bowman was a supplier, Wells is a consumer, and the transaction between
them constituted a consumer transaction. Accordingly, both the OCSPA and SCCPO
were applicable to this matter. The trial court committed reversible error
determining otherwise. We sustain Wells’s first assignment of error and reverse and
remand this matter to the trial court to determine whether the OCSPA and SCCPO
were violated.
C. Assignment of Error No. 2 — Exclusion of the HUD Handbook
{¶ 42} In assignment of error No. 2, Wells argues that the trial court abused
its discretion in failing to admit the Handbook as additional evidence establishing
Bowman’s breach of the parties’ contract. The trial court addressed this issue in
response to a motion in limine filed by Bowman prior to trial. Specifically, Bowman
sought to prevent Wells from introducing the Handbook as evidence of any
additional contractual duties he may owe to Wells on the grounds that relevant authority holds that the Handbook does not create a private right of action or
provide a basis for a breach-of-contract claim between private individuals. The trial
court granted Bowman’s motion in limine stating:
2) On the issue of the introduction into evidence of the FHA/HUD Handbook, which governs the 203(K) program: The Handbook at issue will be allowed into evidence for the limited purpose of impeachment, not to establish a private cause or action to enforce any requirements of the Handbook.
Based on our review of this issue, we conclude that the trial court did not abuse its
discretion and we overrule Wells’s second assignment of error.
{¶ 43} “A motion in limine is essentially a request to limit or exclude
evidence or testimony at trial.” Sokolovic v. Hamilton, 2011-Ohio-4638, ¶ 13 (8th
Dist.), citing State v. Winston, 71 Ohio App.3d 154, 158 (2d Dist. 1991). “Therefore,
the standard of review on appeal of the grant of a motion in limine is whether the
trial court abused its discretion.” Id. An abuse of discretion “implies that the trial
court’s attitude, in reaching its decision, was arbitrary, unreasonable, or
unconscionable.” Johnson v. Abdullah, 2021-Ohio-3304, ¶ 34. “Accordingly,
absent such evidence, this court must affirm the decision of the trial court.”
Sokolovic at ¶ 13.
{¶ 44} Our review of the relevant legal authority confirms that the Handbook
does not provide a private cause of action or a basis for a breach-of-contract claim
between private individuals. Tanner v. Wells Fargo Bank, N.A., 2020 U.S. Dist.
LEXIS 232717, *9-13 (N.D. Ohio Dec. 10, 2020); see, e.g., M.B. Guran Co. v. Akron,
546 F.2d 201, 204 (6th Cir. 1976) (concluding the HUD regulations create neither an express nor implied private right of action); HSBC Bank USA, Natl. Trust Co. v.
Teagarden, 2013-Ohio-5816, ¶ 41-42 (11th Dist.) (Breach-of-contract claim may
exist only if the regulations are expressly incorporated by reference.). Additionally,
in instances where the party has argued that the Handbook (or HUD regulations)
have been incorporated by reference into the parties’ contract, the courts have
consistently held that the incorporation must be expressly and clearly made “so as
to leave no ambiguity about the identity of the material being referenced, nor any
reasonable doubt about the fact that the referenced material is being incorporated
into the contract.” Tanner at *12, citing Volovetz v. Tremco Barrier Sols., Inc.,
2016-Ohio-7707, ¶ 27 (10th Dist.). Further, “incorporation by reference, however,
is a term or art, and not every reference is the equivalent to substantive
incorporation.” Tanner at *13, quoting United States ex rel. Ken’s Carpets
Unlimited v. Interstate Landscaping Co., 1994 U.S. App. LEXIS 24419, *9 (6th Cir.
Sept. 6, 1994).5
{¶ 45} The above is persuasive authority supporting the trial court’s decision
to exclude the Handbook. Further, the record demonstrates that the relevant
documents governing the parties’ contractual relationship do not expressly and
5 In contrast, the authority introduced by Wells in support of admission of the
Handbook only address instances where the Handbook may be used as evidence to establish an industry standard of care or practice supporting the existence of a duty in a negligence action. See, e.g., Soberay v. Greyhound Lines, Inc., 2019-Ohio-1371, ¶ 102- 105 (8th Dist.); Chambers v. St. Mary’s School, 82 Ohio St.3d 563, 568 (1998). They do not address introduction of the Handbook within the context of a contract action. unequivocally incorporate the terms of the Handbook. The Handbook was properly
excluded from evidence. Wells’s assignment of error No. 2 is overruled.
{¶ 46} This matter is affirmed in part, reversed in part, and remanded to the
trial court for proceedings consistent with this opinion.
It is ordered that appellant and appellee share the costs herein taxed.
The court finds there were reasonable grounds for this appeal.
It is ordered that a special mandate issue out of this court directing the
common pleas court to carry this judgment into execution.
A certified copy of this entry shall constitute the mandate pursuant to Rule 27
of the Rules of Appellate Procedure.
_____________________ MICHELLE J. SHEEHAN, ADMINISTRATIVE JUDGE
MICHAEL JOHN RYAN, J., and ANITA LASTER MAYS, J., CONCUR APPENDIX