American Rock Mechanics, Inc. v. Thermex Energy Corp.

608 N.E.2d 830, 80 Ohio App. 3d 53, 1992 Ohio App. LEXIS 2366
CourtOhio Court of Appeals
DecidedMay 18, 1992
DocketNo. 60080.
StatusPublished
Cited by25 cases

This text of 608 N.E.2d 830 (American Rock Mechanics, Inc. v. Thermex Energy Corp.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Rock Mechanics, Inc. v. Thermex Energy Corp., 608 N.E.2d 830, 80 Ohio App. 3d 53, 1992 Ohio App. LEXIS 2366 (Ohio Ct. App. 1992).

Opinion

Weaver, Judge.

Appellant, Independent Explosives Company (“Independent”), timely appeals the outcome of a jury trial which resulted in a verdict in favor of appellee, American Rock Mechanics, Inc. (“American Rock”). We affirm the decision and remand the case to the lower court for a new journal entry clarifying the fact that a judgment exists against American Rock in the amount of $75,000.

The evidence presented to the jury consisted of the following:

*56 In October 1987, appellee successfully bid on a subcontract to drill and blast subsurface rock in Elyria, Ohio for the purpose of installing a sanitary sewer system. This construction project required the use of explosives to break up the subsurface rock to facilitate excavation.

The record reflects that there was a substantial amount of consultation between the parties regarding the appropriate explosives to be used, given the characteristics of the project. Appellee explained the project to Dick Kent, an agent and representative of appellant. Appellant recommended an explosive manufactured by Thermex Energy Corporation (“Thermex”). The product was designated T-600.

T-600 was an explosive that was manufactured by Thermex and sold by Independent. Prior to Dick Kent’s recommendation of T-600, Ed Walter, of American Rock, described the important characteristics of the area that he would need to blast. While Kent did discuss some of the technical characteristics of the T-600, he did not explain that T-600 required warm-up-time allowances. Despite the fact that at the time the T-600 explosives were being purchased there was conversation with other Independent representatives in Kentucky and Cleveland, there were still no limitations placed on the use of the T-600 by Independent.

Having purchased and utilized the T-600 on the project in Elyria, Ohio, American Rock began to experience difficulties in early December 1987. American Rock contacted Independent about the problem. The agent with whom these problems were discussed was again Dick Kent. American Rock described the difficulties as both poor and good breakage, holes in which the explosives were shot and left empty, and live explosives remaining in the trench.

American Rock discussed certain changes with Kent and he did not voice any objections to those changes. American Rock remained under the impression that it was using the T-600 within the proper specifications. Independent never raised the issue of explosive product temperature during the discussions about the problems that American Rock was having on the job site.

The blasting on the project was terminated in February 1988. In March 1988, Kent sent some T-600 samples to the explosives laboratory of Independent for testing. The testing was conducted by Rehman Habib. A lab report of April 1988 indicated that there was nothing wrong with the T-600 product. Independent tested only product from stock and frozen samples and not from the actual job site. However, there was still some reference to temperature as a problem.

Independent’s testimony was that Thermex never supplied Independent with any technical data about T-600, despite testimony from Thermex representa *57 tives that the technical data sheet and warm-up chart are automatically shipped to all Thermex customers and distributors handling their products. According to Kent and Independent, the only technical information that Independent had was an old brochure from Gulf as to NCN-600. Gulf was bought by Thermex in the mid ’80’s and the product was renamed T-600. This old brochure did not contain any warm-up information for the product. Also, according to Kent and Independent, the brochure was never shown to Walter because his order was placed on the phone.

Also, according to Independent, Ed Walter never made the characteristics of the project known to Kent. Walter never gave Kent a copy of the bid specifications or drawings for the site or any other technical data regarding the project. In February 1988, Kent went to the job site and discussed the blasting problems with Ed Walter, who he viewed as an experienced blaster.

During the trial of this matter, there were a number of possibilities stated as to what caused the problems with the explosives. Thermex opined that the problems came from “dead pressing” and inadequate bore hole size. American Rock opined that the age of the explosives and temperature cycling problems were more likely the cause of the problems on the job site than the way the shots were designed by the blaster.

After these two opposing opinions were placed before the jury, a verdict was returned in favor of American Rock on the theory of breach of an implied contractual duty to provide certain product information. A verdict was also returned in favor of Independent against Ed Walter, personally, for the unpaid purchase price of the explosives. Ed Walter did not appeal that verdict.

Appellant’s first and second assignments of error are interrelated and therefore will be discussed together. Respectively, they state:

“The trial court committed reversible error in not granting judgment notwithstanding the verdict in favor of Independent on American Rock’s implied contractual duty claim based on the jury’s determination that no contract existed between American Rock and Independent.
“The trial court committed reversible error in not granting a directed verdict and judgment notwithstanding the verdict in favor of Independent on American Rock’s implied contractual duty claim because American Rock failed to establish a prima .facie case of breach of such duty and of causation.”

Appellant argues in assignment of error one that appellee had no claim for breach of contract upon which judgment could be entered because no buyer-seller relationship existed between appellee and appellant. Appellant asserts this by alleging that a factual determination was made by the jury that *58 appellee did not buy the explosives from appellant; Ed Walter purchased the explosives according to appellant based on the finding by the jury regarding the counterclaim against Ed Walter that he personally owed the purchase price for the explosives. Appellant asserts that this factual determination establishes that there was no buyer-seller relationship between appellee and appellant and therefore, no contractual privity. Without privity of contract, there can be no recovery on a breach of implied contract claim.

The legal test that must be applied by the trial court in ruling on a motion for directed verdict or a motion for judgment notwithstanding the verdict is adequately explained in Posin v. A.B.C. Motor Court Hotel (1976), 45 Ohio St.2d 271, 74 O.O.2d 427, 344 N.E.2d 334., The Ohio Supreme Court states at 275, 74 O.O.2d at 428, 344 N.E.2d at 338:

“The test to be applied by a trial court in ruling on a motion for judgment notwithstanding the verdict is the same test to be applied on a motion for a directed verdict.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wells v. Right Choice Contracting, L.L.C.
2026 Ohio 117 (Ohio Court of Appeals, 2026)
In re Estate of Goode
2023 Ohio 4253 (Ohio Court of Appeals, 2023)
Stride Studios, Inc. v. Alsfelder
2023 Ohio 1502 (Ohio Court of Appeals, 2023)
Marquette Orri Holdings, L.L.C. v. Ascent Resources-Utica, L.L.C.
2022 Ohio 3786 (Ohio Court of Appeals, 2022)
Koliner v. Moorer
S.D. Ohio, 2020
Koster v. Chowdhury
2016 Ohio 5704 (Ohio Court of Appeals, 2016)
Risner v. Regal Marine Industries, Inc.
8 F. Supp. 3d 959 (S.D. Ohio, 2014)
Miles v. Raymond Corp.
612 F. Supp. 2d 913 (N.D. Ohio, 2009)
Hahn v. Jennings, Unpublished Decision (9-9-2004)
2004 Ohio 4789 (Ohio Court of Appeals, 2004)
Samadder v. DMF of Ohio, Inc.
798 N.E.2d 1141 (Ohio Court of Appeals, 2003)
Norcold, Inc. v. Gateway Supply Co.
798 N.E.2d 618 (Ohio Court of Appeals, 2003)
American Legacy Foundation v. Lorillard Tobacco Co.
831 A.2d 335 (Court of Chancery of Delaware, 2003)
Bobb Forest Products, Inc. v. Morbark Industries, Inc.
783 N.E.2d 560 (Ohio Court of Appeals, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
608 N.E.2d 830, 80 Ohio App. 3d 53, 1992 Ohio App. LEXIS 2366, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-rock-mechanics-inc-v-thermex-energy-corp-ohioctapp-1992.