Saulsbury Industries, Inc. v. The Babcock & Wilcox Company

CourtDistrict Court, N.D. New York
DecidedMay 28, 2020
Docket1:19-cv-00771
StatusUnknown

This text of Saulsbury Industries, Inc. v. The Babcock & Wilcox Company (Saulsbury Industries, Inc. v. The Babcock & Wilcox Company) is published on Counsel Stack Legal Research, covering District Court, N.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Saulsbury Industries, Inc. v. The Babcock & Wilcox Company, (N.D.N.Y. 2020).

Opinion

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF NEW YORK

SAULSBURY INDUSTRIES, INC., Plaintiff, v. 1:19-CV-0771 (GTS/TWD) THE BABCOCK & WILCOX COMPANY, Defendant.

APPEARANCES: OF COUNSEL: DINSMORE & SHOHL LLP GLEN R. McMURRY, ESQ. Counsel for Plaintiff SUNNI R. HARRIS, ESQ. Fifth Third Center 1S. Main St., Suite 1300 Dayton, OH 45402 BOND SCHOENECK & KING, PLLC BRIAN J. BUTLER, ESQ. Counsel for Defendant One Lincoln Center Syracuse, NY 13202 ROETZEL & ANDRESS, LPA JESSICA A. LOPEZ, ESQ. Co-Counsel for Defendant RONALD S. KOPP, ESQ. 222 S. Main St., Suite 400 Akron, OH 44308 GLENN T. SUDDABY, Chief United States District Judge DECISION and ORDER Currently pending before the Court, in this breach-of-contract action filed by Saulsbury Industries (“Plaintiff”) against the Babcock & Wilcox Company (“Defendant”), are Plaintiff's motion to strike Defendant’s first affirmative defense (demanding a set-off) pursuant to Fed. R. Civ. P. 12(f), and Plaintiff's motion to dismiss Defendant’s first-amended counterclaim (containing counts for a set-off and breach of contract) pursuant to Fed. R. Civ. P. 12(b)(6).

(Dkt. No. 33-1; Dkt. No. 43.) For the reasons set forth below, Plaintiff's motion to strike Defendant’s affirmative defense of set-off is granted, Plaintiffs motion to dismiss Defendant’s counterclaim is denied with regard to both the count of set-off and the count of breach of contract. 1. RELEVANT BACKGROUND A. Summary of Plaintiff’s Complaint Generally, liberally construed, Plaintiff's Complaint alleges as follows. (See generally Dkt. No. 1 [PIf.’s Compl.].) On September 1, 2015, Defendant entered into a Consortium Framework Agreement (“Consortium Agreement”) with various entities, including Plaintiff, to work cooperatively to obtain business from potential construction customers. (/d.) The Consortium Agreement prohibited, among other things, a consortium member from withholding or setting off any payment that was due to another consortium member unless the dispute was resolved by agreement of the parties or finally disposed of by a court. (/d.) On November 2, 2015, Plaintiff and Defendant (and other consortium members) entered into an Engineering, Procurement and Construction Contract (“EPC Contract”) with Continental Carbon Company (“CCC”). (/d.) Pursuant to the EPC Contract, CCC retained ten percent (10%) of each “Milestone Payment” as “Retainage,” agreeing to pay that Retainage as part of the final Milestone Payment. (/d.) In January of 2019, CCC paid Defendant (as the “Consortium Leader”) the Retainage, after deciding to postpone the parties’ work on its facility in Phenix City, Alabama (“Phenix project”). (/d.) Of that amount, Plaintiff was entitled to $3,233,543.63. Ud.) However, Defendant paid Plaintiff only $785,000.00, wrongfully demanding (and finding to be inadequate) invoices to substantiate the remaining amount. (/d.)

Based on these factual allegations, Plaintiff asserts four claims against Defendant: (1) a claim for breach of contract; (2) a claim for promissory estoppel; (3) a claim for unjust enrichment; and (4) a claim for fraud. (/d.) Familiarity with the factual allegations supporting these claims in Plaintiff's Complaint is assumed in this Decision and Order, which is intended primarily for review by the parties. (/d.) B. Summary of Defendant’s Original Answer Generally, Defendant’s Answer denies a variety of Plaintiff's allegations and asserts two affirmative defenses: (1) that, should Defendant be determined to be liable to Plaintiff for any amount of money, that amount must be set-off by Plaintiff's obligation to repay Defendant (given that CCC’s termination triggered various provisions of the parties’ contracts, which prohibited Plaintiff from retaining payments for work it never performed and for materials it never purchased); and (2) that Plaintiff is estopped from pursuing its claims against Defendant. (See generally Dkt. No. 22.) Defendant also asserts a counterclaim against Plaintiff, requesting that the Court enter a Declaratory Judgement against Plaintiff in accordance with 28 U.S.C. § 2001, determining that, as between the parties, no additional monies are owed by Defendant to Plaintiff. (d.) C. Plaintiff’s First Motion Generally, in support of its first motion,' Plaintiff argues as follows: (1) the Court should strike Defendant’s first affirmative defense of set-off pursuant to Fed. R. Civ. P. 12(f), because it is insufficient in that it directly conflicts with Articles 9.5 and 9.6 of the Consortium Agreement, which specifically prohibit set-offs without agreement of the parties or court disposition; and (2) the Court should dismiss Defendant’s counterclaim for declaratory judgment from its original Plaintiff is respectfully reminded that, pursuant to the Court’s Local Rules of Practice, memoranda of law must contain a table of contents. N.D.N.Y L.R. 7.1(a)(1).

Answer pursuant to Fed. R. Civ. P. 12(b)(6), because a declaratory judgment is a remedy, not an independent cause of action. (Dkt. No. 33-1 [PIf.’s First Memo. of Law].) D. Summary of Defendant’s Amended Answer Twenty-one days after service of Plaintiff's motion, Defendant filed an Amended Answer as a matter of right under Fed. R. Civ. P. 15(a)(1)(A). (Dkt. No. 38.) Generally, Defendant’s Amended Answer restates its denial of various of Plaintiff's allegations and its assertion of the affirmative defenses of set-off and estoppel. (See generally id.) In addition, Defendant’s Amended Answer abandons its counterclaim for declaratory judgment and replaces it with two counterclaims: (1) a counterclaim for set-off arising from Plaintiffs breach of its contractual obligation to not retain payment in the amount of $2,154,216.38 for work that it never performed and materials that it never purchased, and (2) a counterclaim for breach of contract arising from Plaintiff's commitments under Article 5.9 of the Consortium Agreement (which provides, in pertinent part, that, should the EPC Contract be terminated prior to completion of performance, any payment by the customer would “be divided between the [Consortium] Members pro-rata to the costs, expenses, and obligations actually and reasonably incurred by each of them in the performance of its SCOPE OF WORK and recognized in arriving at the settlement with the CUSTOMER’) and Section 16.2 of the EPC Contract (which provides, in pertinent part, that, should CCC terminate the contract without cause, the Consortium Members are entitled to compensation “only for the work performed up to and including the date of termination”). (/d.)

E. Summary of the Remainder of the Parties’ Briefing on Plaintiff’s First Motion Generally, in response to Plaintiff's first motion, Defendant argues as follows: (1) Plaintiff's motion to strike Defendant’s first affirmative defense should be denied because Ohio law clearly recognizes set-off as an affirmative defense and Defendant’s affirmative defense of set-off is expressly contemplated by Articles 9.5 and 9.6.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conley v. Gibson
355 U.S. 41 (Supreme Court, 1957)
Branch v. Smith
538 U.S. 254 (Supreme Court, 2003)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
DiFolco v. MSNBC Cable L.L.C.
622 F.3d 104 (Second Circuit, 2010)
Rusyniak v. Gensini
629 F. Supp. 2d 203 (N.D. New York, 2009)
Jackson v. Onondaga County
549 F. Supp. 2d 204 (N.D. New York, 2008)
L-7 Designs, Inc. v. Old Navy, LLC
647 F.3d 419 (Second Circuit, 2011)
Optigen, LLC v. International Genetics, Inc.
777 F. Supp. 2d 390 (N.D. New York, 2011)
Ohio Savings Bank v. H. L. Vokes Co.
560 N.E.2d 1328 (Ohio Court of Appeals, 1989)
American Rock Mechanics, Inc. v. Thermex Energy Corp.
608 N.E.2d 830 (Ohio Court of Appeals, 1992)
Kocsorak v. Cleveland Trust Co.
85 N.E.2d 96 (Ohio Supreme Court, 1949)
Bluemile, Inc. v. Atlas Indus. Contractors, Ltd.
2017 Ohio 9196 (Ohio Court of Appeals, 2017)
Lucarell v. Nationwide Mut. Ins. Co. (Slip Opinion)
2018 Ohio 15 (Ohio Supreme Court, 2018)
Walter v. National City Bank
330 N.E.2d 425 (Ohio Supreme Court, 1975)
Alexander v. Buckeye Pipe Line Co.
374 N.E.2d 146 (Ohio Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
Saulsbury Industries, Inc. v. The Babcock & Wilcox Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/saulsbury-industries-inc-v-the-babcock-wilcox-company-nynd-2020.