Weitman Excavation, LLC v. CPM Development Corp.

368 P.3d 66, 276 Or. App. 583
CourtCourt of Appeals of Oregon
DecidedFebruary 24, 2016
Docket110506898; 120100334; A153619
StatusPublished
Cited by2 cases

This text of 368 P.3d 66 (Weitman Excavation, LLC v. CPM Development Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Weitman Excavation, LLC v. CPM Development Corp., 368 P.3d 66, 276 Or. App. 583 (Or. Ct. App. 2016).

Opinion

SHORR, J.

This is an appeal of a trial court judgment awarding plaintiff, Weitman Excavation, LLC, its attorney fees under ORS 36.715 and an enhanced prevailing party fee under ORS 20.190. Defendant, CPM Development Corporation, challenges both of those awards on appeal. Defendant argues, among other things, that the trial court erred in awarding plaintiff its attorney fees incurred in arbitration because, under ORS 36.715(3), a party may only recover fees incurred “in a judicial proceeding” following an arbitration award as part of an effort to vacate, modify, or correct the arbitration award. Defendant also argues that the trial court erred in awarding plaintiff an enhanced prevailing party fee based on a legally erroneous recklessness determination.

Because we conclude that a party cannot obtain attorney fees under ORS 36.715(3) for work undertaken in an arbitration proceeding, the trial court erred in awarding attorney fees on that basis. We further conclude that the trial court erred in awarding plaintiff the enhanced prevailing party fee. That fee award was based, in part, on a determination that defendant was reckless in proceeding with the arbitration. However, the trial court also concluded that defendant’s legal position in seeking arbitration was “objectively reasonable” and made in the context of a “good faith” disagreement on the law. As explained below, those conclusions are incompatible in this context and result in legal error.

Separately, plaintiff cross appeals, arguing that the trial court erred in denying its request for attorney fees under another statute, ORS 20.105. Plaintiff also argues in its cross-appeal that the trial court abused its discretion in awarding plaintiff less than the full amount of attorney fees that plaintiff requested under ORS 36.715(3). We reject both of those contentions without discussion and affirm the trial court’s rulings on those issues.

Accordingly, on appeal, we reverse the portion of the attorney fee award that was based on fees that were incurred in the arbitration, and we vacate and remand the [586]*586award of an enhanced prevailing party fee for reconsideration in light of our opinion.1 On plaintiffs cross-appeal, we affirm.

We begin with an overview of the parties’ contractual dispute and relevant aspects of the dueling arbitration and judicial proceedings that followed. These facts are undisputed.

Defendant is a general contractor specializing in infrastructure and transportation construction. Plaintiff is an excavation subcontractor. Both parties placed bids on a major airport utility project in February 2011. Plaintiff submitted its bid to defendant based on general specifications provided by the Port of Portland and a brief telephone conversation with defendant. Defendant then incorporated plaintiffs bid into its own bid for the project.

Defendant was awarded the contract and subsequently notified plaintiff that its bid had been approved. Shortly thereafter, defendant notified plaintiff, for the first time, of multiple terms that had not been included in the bid solicitation, including bonding, insurance, and withholding requirements. On February 24, 2011, defendant provided plaintiff with a subcontract containing those new terms and an arbitration clause.

Based on previous experience on public works projects, plaintiff had not anticipated a bond requirement and, as such, had not factored the cost of securing one into its original bid. Plaintiff doubted that it would be able to obtain the bond and was concerned that, even if it could, the cost of doing so would be prohibitive. Plaintiff immediately communicated those concerns to defendant. After discussions and unsuccessful efforts by plaintiff to comply with defendant’s proposed terms, the parties were unable to reach an agreement. Plaintiff — which never signed the subcontract— notified defendant that it was withdrawing from the project.

[?]*?In May 2011, defendant initiated arbitration proceedings before the American Arbitration Association. Defendant claimed that plaintiff breached their contractual agreement. Plaintiff contested arbitration jurisdiction before the arbitrator, claiming that the parties never entered into a contract compelling arbitration. In addition, plaintiff brought a declaratory judgment action in court. Plaintiff sought a declaration that defendant had no contractual rights that were enforceable through arbitration. As part of the declaratory judgment action, defendant filed a petition to compel arbitration and stay the court proceedings. See ORS 36.625(1) (requiring a court “summarily to decide” a contested motion to compel). After the parties briefed and argued those issues at an August 2011 hearing, the trial court took the matter under advisement.

While the trial court’s ruling was under advisement, the October 2011 arbitration went forward as scheduled.2 Defendant prevailed in the arbitration and the arbitrator awarded $71,955.65 in damages, plus $101,682.24 in attorney fees and costs. When the trial court learned that the arbitration had taken place, it asked the parties if the motion to compel was moot. Defendant, the moving party, advised the trial court that the motion was moot; plaintiff advised the trial court that it was not. The trial court interpreted defendant’s representations to mean that “the motion to compel arbitration had been withdrawn” and that the issue of whether the dispute was subject to arbitration had been preclusively decided by the arbitrator.

After the arbitration award issued, plaintiff filed a motion for summary judgment in the original declaratory judgment action, incorporating essentially the same jurisdictional arguments it had previously advanced before both the arbitrator and the trial court. Defendant, in addition to opposing summary judgment, petitioned the trial court for an order to confirm the arbitration award. Defendant’s petition instituted a second case, which was consolidated [588]*588with plaintiffs declaratory judgment action. Plaintiffs answer to defendant’s petition to confirm the arbitration award included a competing petition to vacate the arbitrator’s award on the ground that the arbitrator lacked subject matter jurisdiction due to the absence of a binding contract that included an agreement to arbitrate. See ORS 36.700; ORS 36.705; ORS 36.710; ORS 36.715

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Paatalo v. McCarthy
325 Or. App. 755 (Court of Appeals of Oregon, 2023)
Al-Ani v. Wafeek
455 P.3d 1006 (Court of Appeals of Oregon, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
368 P.3d 66, 276 Or. App. 583, Counsel Stack Legal Research, https://law.counselstack.com/opinion/weitman-excavation-llc-v-cpm-development-corp-orctapp-2016.