Webster County v. Nelson

135 N.W. 390, 154 Iowa 660
CourtSupreme Court of Iowa
DecidedApril 2, 1912
StatusPublished
Cited by2 cases

This text of 135 N.W. 390 (Webster County v. Nelson) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Webster County v. Nelson, 135 N.W. 390, 154 Iowa 660 (iowa 1912).

Opinion

Weaver, J.

On March 17, 1908, in proceedings pending before the board of supervisors of Webster county .for the improvement of a certain drainage district, the appellant John Nelson became the successful bidder for the construction of a ditch according' to designated plans and specifications' prepared by the county’s engineer. Soon thereafter Nelson entered upon the work, but the written contract therefor was not executed until a later date as hereinafter shown, during which period the only written evidence of -the agreement was in the bid of Nelson, its acceptance by the board of supervisors and possibly the advertised terms of the letting of the contract. It seems to bo conceded, however, that the bid was made and accept[662]*662ed with the understanding that the work "should be completed by January 1, 1909. For some reason Nelson made slow progress with the work and failed to finish it within the specified period, and a further agreement was entered into extending the time for the performance of the contract for one year*. Still no written agreement was executed until July 7, 1909, when the board awoke to the fact that it not only had no formal written contract, but no bond securing its due performance as provided by law. On the date mentioned a contract was executed, by the terms of which for the amount of his bid, $14,691.36, Nelson undertook to do the work according to the specifications, and have the ditch completed on or before January 1, 1910, and stipulated that upon his failure to have the work done within the time thus limited that he would pay “as actual and liquidated damages ten dollars per day.” On July 22, 1909, the defendant fidelity company as surety for Nelson made and delivered its bond to the board of supervisor’s, as follows:

Know all men by these presents: That we, John Nelson, of Ft. Dodge, Iowa, as ^principal and the United States Fidelity & Guaranty Company of Baltimore, Maryland, as sureties, are held and firmly bound unto the board of supervisors of the county of Webster and state of Iowa, for drain district No. 43 in the penal sum of $3,741.00 lawful money of the United States, well and truly to be paid to the said board of supervisors as sureties in trust for drain district No. 43. The condition of the above obligation is such that, whereas, the above named John Nelson, agrees to construct county drain No. 43 according to a contract this day signed and bearing even date herewith: Now, therefore, if the said John Nelson shall well and faithfully perform and keep all the conditions of said contract on their part to be kept and performed, and shall .well and truly protect the interests of said drain district in performance of their contract, then this bond is to be void, otherwise to remain in full force and effect. Witness our hands this 22d day of July, 1909. John Nelson. The United States Fidelity & Guaranty Company.

[663]*663By the terms of Nelson’s contract he was to be paid in monthly installments as the work progressed on the basis of eighty percent of the engineer’s estimates of the amount earned; the remaining twenty percent being retained in the nature of a guaranty fund for the due fulfillment of the contract. On January 7, 1910, the work being still uncompleted, the board of supervisors ordered written notice served on Nelson and his surety that on January 12, 1910, it would take up the matter of reletting the contract to complete the ditch, and of enforcing a claim for damages by action upon the bond. The notice thus provided for was served. The hearing pursuant to said notice was continued from time to time until March 9, 1910, when a resolution was adopted by the board to the effect that Nelson, having failed to complete the ditch within the limit of time agreed upon, his contract should be declared terminated and forfeited, and that the work should be readvertised and contract relet at a public bidding. It was further ordered that the attorneys for the county bring action on the bond against Nelson and his surety to recover damages sustained by the failure to perform the work according to agreement. Acting upon the authority thus conferred, the contract was relet, and this action was then begun.

The petition sets out the substance of the facts hereinbefore recited. It is further averred that at-the time the contract was forfeited the work of constructing the ditch was somewhat less than half done, that the amount actually earned by Nelson was $6,678.19, of which sum $1,607.96 is still in the hands of the county treasurer, and is applicable to the payment of the damages occasioned by Nelson’s breach of his contract. But it is averred that said damages far exceed said guaranty fund for that upon the reletting of the work the best bid offered was $13,400, and the contract was let upon that basis, and that, after making due allowance for credits and deductions to which defendants may be entitled, there remains due the plaintiff from Nel[664]*664son tlie sum of $6,398.29.' For the recovery of this sum judgment is asked, against both defendants upon their bond for $3,741, and against Nelson individually for the further sum of $2,657.29. To this claim the defendants, pleading separately, filed answer in denial of the allegations of the petition. At a later day the surety amended its answer, pleading that, by the terms of the bond, its liability can in no case be in excess of the agreed penalty of $10 per day for the period from January 1, 1910, when the time limit agreed upon expired to March 9, 1910, when the contract was declared at an end. It further alleges that under said contract the sum of $1,607.96 earned by Nelson has been withheld from him, and said surety company asks that it be subrogated to the right to demand and receive said fund, and that the same be applied to the payment of the penalty’ provided for by the terms of the contract to secure which the bond was given. The cause having been tried to the court, it was found and decided that the clause of the contract providing for liquidated damages of $10 per day for failure to complete the work within the time specified was void and of no effect; that the actual damages so arising from Nelson’s failure to perform his contract were $4,716.03 upon which should be credited the amount withheld from him on estimates for work already performed, $1,607.96, leaving the net sum due plaintiff $3,108.07, for which the court awarded judgment on the bond against both Nelson and the surety company. From this judgment the appeal herein has been prosecuted.

1. Drainage: forfeiture of contract: notice. I. The appellants each insist that no cause of action has been shown. It is not denied that the contractor failed to perform the work within the specified time limit, but counsel say that the board of supervisors could not rightfully stop said work, and proceed to a new letting without notice to the contractor, Again, it is said the hoard of supervisors refused to pay the contractor his and that no such notice was given [665]*665eighty percent of the engineer’s estimate for work done in January, 1910, and, having thus itself violated the contract, it cannot now have the same enforced in its favor. Conceding that plaintiff’s purpose to forfeit the contract should be indicated to the contractor and his surety by some adequate notice, and that such notice should be given within reasonable time after the default complained of, we think the record discloses nothing of which appellants can rightfully complain in this respect.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fellows v. Errington
186 Iowa 322 (Supreme Court of Iowa, 1919)
Humboldt County v. Ward Bros.
145 N.W. 49 (Supreme Court of Iowa, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
135 N.W. 390, 154 Iowa 660, Counsel Stack Legal Research, https://law.counselstack.com/opinion/webster-county-v-nelson-iowa-1912.