Wolf v. Des Moines & Ft. Dodge R'y Co.

20 N.W. 481, 64 Iowa 380
CourtSupreme Court of Iowa
DecidedSeptember 19, 1884
StatusPublished
Cited by10 cases

This text of 20 N.W. 481 (Wolf v. Des Moines & Ft. Dodge R'y Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wolf v. Des Moines & Ft. Dodge R'y Co., 20 N.W. 481, 64 Iowa 380 (iowa 1884).

Opinion

Reed, J.

The petition sets out the contract between the parties, which is in writing, and alleges that in pursuance of the contract plaintiff performed work and labor to the amount of $30,103.45, and that there remains due therefor the sum of $4,500, for which amount, with interest, they ask judgment. They also ask for the establishment and enforcement of a mechanic’s lien on the section of road on which said work was done.

The defendant’s answer admits the making of the contract, and that plaintiffs performed work and labor thereunder to the amount charged in the petition.

■ And it is alleged therein that defendant has paid plaintiffs on account of said work the sum of $26,467.87. It is also alleged that plaintiffs, having failed to prosecute the work with an adequate force, as required by the contract, and [382]*382to complete tlie same within, the time therein provided, it terminated the contract, as it had a right to do under the provisions of the contract, and that thereupon it became entitled to retain ten per cent of the amount coming to plaintiffs, under the contract, for liquidated damages. It is also alleged, by way of counter-claim, that plaintiffs failed and neglected to prosecute the work under said contract with an adequate force, and failed to complete the same within the time provided in the contract, for which reasons it took charge of and completed said work, as it had the right to do under the contract, by reason of which failure by plaintiffs it has been damaged in the sum of $50,000, the items of which amount arc the loss of the use of its road bed, the additional cost of doing said work over and above what its cost would have been if plaintiffs had performed the work under the contract; and the loss of certain subsidies which - had been voted by two townships in Pocahontas county in aid of the construction of said railroad, but which were voted on the condition that the same should be completed within a specified time, and which were forfeited by its failure to complete the road within said time; which loss was occasioned, as it alleges, by the failure of plaintiffs to complete the work covered by the contract within the time therein specified.

The plaintiffs, in their reply, admit that they did not complete the work within the time specified in the contract, but allege that their failure in this respect was occasioned by the fault and neglect of the defendant; that it neglected to furnish timber and materials for the bridges on said road, and also neglected for a long time to procure the right of way for its railroad, and that, by reason of this neglect on its part, the work was greatly delayed and hindered. They also allege that defendant, without their consent, changed the line and grades of its road, after the contract was entered into, whereby the amount of work' necessary to its completion was greatly increased. They also charge that defendant, by its employes, published and reported among the laborers employed by them [383]*383upon said work that they were not pecuniarily responsible, and would not be able to pay for such labor as they might employ in doing the work, and that their report had the effect to cause many of their employes to quit work thereon, and to greatly hinder and embarrass them in the prosecution of said work.

They also allege that there was an accounting and settlement between the parties, in which it was mutually agreed between them that they should suspend work upon the contract, and leave the same in the hands of defendant, and that all differences between the parties regarding the non-complc■tion of the work within the time specified should be settled, and no claim made by either party for any alleged failure to comply with the terms of the contract, and that the work then done should be computed and paid for; and that said work was then measured and computed, and the amount charged in the petition was found to be due them therefor. ’

I. The contract was entered into on the eleven th day of April, 1881. The work which plaintiff undertook to perform was the construction of all the earth work or grading required by defendant’s engineer on the extension of its railroad north of Tara. The contract provides that the work should be finished according to the direction of the engineer and his assistants, and in conformity with the specifications which were embodied in the contract. It also provided that the work should be commenced by plaintiffs within ten days from the date of its execution, and should be completed on or before August 1, 1881, but that the first ten miles thereof should be finished on or before July 20. It also contains the following provisions: .“Payments shall be made in the following manner, viz.: Once a month an estimate shall be made of the relative value of the work done, to be computed by the engineer, and within twenty days of said estimate the party of the first part (defendant) shall pay to the parties of the second part ninety per cent of said estimate. When all the work is completed according to the specifications, and in ac[384]*384cordance with the directions and acceptance of the engineer, there shall be a final estimate made of said work, and a settlement and payment made within thirty days after receiving the proper certificate of said engineer.” * * * * * * * “And in case the said parties of the second part should at any time fail to employ force to complete the work within the agreed time, or to prosecute the work according to the directions of-the party of the first part, or their engineer, the party of the first part may put on a force of men, and charge the expense of the same to said parties of the second part as so much paid on account of the contract. And for a failure to begin work at the time herein agreed upon, or on failure to prosecute the work with an adequate force, or for non-compliance with the directions of the engineer in regard to the manner of constructing it, or for any other omission or neglect of the parties of the second part of any of the requirements of this agreement and specifications, said engineer may, at his discretion, terminate this contract by a notice in writing delivered to one of the parties of the secend part, or, if they are absent from the' work, addressed to their residence by mail, which notice and failure shall exonerate the party of the first part from all obligations and liabilities arising under this contract the same as if the agreement had no-t been made; and the reserved ten per cent upon any work done by the parties of the second part shall be retained by the party of the first part as liquidated damages.”

The evidence shows that plaintiffs entered upon the work about the first of May, and that they continued to work until about the ninth of September following, when they quit the work finally. At that time less than one-half of the work bf grading said railroad was completed. On the second of September one member of plaintiffs’ firm had an interview with the president of the defendant’s company, at which its chief engineer was present. At this meeting it was agreed that plaintiff's should continue on the work for a few days, until [385]*385defendant could organize a force to continue the work, or pro-' cure other parties to prosecute it, when they should abandon it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Independent School District v. Dudley
195 Iowa 398 (Supreme Court of Iowa, 1923)
State v. Brocks
192 Iowa 1107 (Supreme Court of Iowa, 1922)
Joeckel v. Johnson
178 Iowa 231 (Supreme Court of Iowa, 1916)
Webster County v. Nelson
135 N.W. 390 (Supreme Court of Iowa, 1912)
Stony Creek Lumber Co. v. Fields & Co.
45 S.E. 797 (Supreme Court of Virginia, 1903)
Sun Printing and Publishing Assn. v. Moore
183 U.S. 642 (Supreme Court, 1902)
Beeman Bros. v. Hexter
67 N.W. 270 (Supreme Court of Iowa, 1896)
Hennessy v. Metzger
38 N.E. 1058 (Illinois Supreme Court, 1894)
DeGraff, Vrieling & Co. v. Wickham
89 Iowa 720 (Supreme Court of Iowa, 1892)
Jaqua v. Headington
16 N.E. 527 (Indiana Supreme Court, 1888)

Cite This Page — Counsel Stack

Bluebook (online)
20 N.W. 481, 64 Iowa 380, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wolf-v-des-moines-ft-dodge-ry-co-iowa-1884.