Waterwatch of Oregon, Inc. v. Water Resources Department

316 P.3d 330, 259 Or. App. 717, 2013 WL 6498547, 2013 Ore. App. LEXIS 1463
CourtCourt of Appeals of Oregon
DecidedDecember 11, 2013
DocketS42117; A147071
StatusPublished
Cited by5 cases

This text of 316 P.3d 330 (Waterwatch of Oregon, Inc. v. Water Resources Department) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Waterwatch of Oregon, Inc. v. Water Resources Department, 316 P.3d 330, 259 Or. App. 717, 2013 WL 6498547, 2013 Ore. App. LEXIS 1463 (Or. Ct. App. 2013).

Opinion

ARMSTRONG, P. J.

Petitioner WaterWatch of Oregon, Inc., seeks judicial review of a final order in a contested case in which the Water Resources Department (the department) granted the City of Cottage Grove (Cottage Grove or the city) an extension of time to perfect its water rights under a permit first issued in 1977. Petitioner contends that the department erroneously interpreted ORS 537.230(2)1 by failing to condition the permit extension on the protection of certain fish species, ORS 537.230(2)(c), and on the development of a water management and conservation plan, ORS 537.230(2)(b). It also contends that the order is inconsistent with the department’s implementing rule, OAR 690-315-0010(6)(g),2 or, alternatively, that that rule is invalid because it exceeds the statutory authority of the department.

As an initial matter, respondents — the city, the department, and the Water Resources Commission — contend [720]*720that the case is moot because, after the extension order issued, the city perfected its water right under the permit and the department issued a “Certificate of Water Right,” which petitioner did not challenge. Thus, in respondents’ view, no decision by us can have any effect on the city’s water rights under the permit. On the merits, respondents contend that the department correctly interpreted and applied ORS 537.230(2)(b) and (c) and OAR 690-315-0010(6)(g) and that the rule does not exceed the department’s statutory authority.3

As explained below, we conclude that the case is not moot. On the merits, we conclude that the department erroneously construed ORS 537.230(2) and, consequently, failed to condition the extension of the permit as required in ORS 537.230(2)(b) and (c). Accordingly, we reverse and remand the department’s final order extending the city’s permit with instructions to the department to vacate the city’s water-right certificate and to reconsider the city’s permit extension request in accordance with this opinion.

The department’s final order adopted the findings of the administrative law judge (ALJ), which petitioner does not challenge.4 Those facts are as follows:

“1. The City of Cottage Grove holds permit S-42117 (permit), issued by the [department] on November 14,1977. Under the permit, Cottage Grove is authorized to divert [721]*721up to 6.2 cubic feet per second (cfs) of water from the Row River for municipal use.
“2. According to the permit, Cottage Grove was required to complete construction of a water development project by October 1, 1979 and make complete application of water on or before October 1, 1980.
“3. Between 1977 and 1999, [the department] granted multiple extensions to the permit to allow Cottage Grove to complete construction of a water treatment plant on the Row River and make full application of the water claimed in the permit. The last extension granted by [the department] expired on October 1, 1999.
“4. Sometime prior to October 1,1999, due to protracted rulemaking proceedings regarding permit extensions, [the department] suspended all applications for extension of time and did not require municipal permit holders to submit new applications for permit extensions. [The department’s] new rules became effective November 22, 2005.
“5. In November 2007, Cottage Grove completed an enlargement of the Row River Water Treatment Plant (RRWTP) designed to accommodate a new membrane filtration system. In May 2008, Cottage Grove completed construction of a larger diversion structure which allowed it to divert up to 6.2 cfs of water.
“6. On December 11, 2007, Cottage Grove submitted an application for extension of time to perfect water rights under the permit. On January 30, 2008, Cottage Grove requested its application be placed on administrative hold. [The department] granted this request.
“7. On July 10, 2008, Cottage Grove diverted 6.2 cfs of water into the RRWTP over a period of approximately six hours. The purposes of the diversion included meeting end user demands, storage for fire suppression, and filling Cottage Grove’s finished water reservoirs to ensure maintenance of minimum line pressure necessary for proper functioning.
“8. On or about August 4, 2008, Cottage Grove requested [the department] remove the administrative hold from the application for extension and continue processing the application. At this time, Cottage Grove provided information to [the department] supplementing its original application.
[722]*722“9. In addition to uses identified in its administrative rules, [the department] also considers uses aimed at maintaining municipal water systems, including flushing lines and maintaining system pressure, to be valid municipal uses of water.”

(Record citations omitted.)

On August 19, 2008, the department issued a proposed final order that proposed to grant Cottage Grove an extension of time, from October 1, 1999, to October 1, 2013, to complete construction of its water system and to apply water to full beneficial use under permit S-42117. Petitioner filed a protest, see OAR 690-315-0060 (governing process for protesting the department’s final order on an extension application); OAR 690-315-0100 (providing that OAR 690-315-0060 applies to extension applications for municipal water-use permits), the department referred the matter to the Office of Administrative Hearings, and an AL J ultimately held a contested case hearing to resolve certain issues. On December 15, 2009, the ALJ issued an amended proposed order affirming the department’s proposed order, concluding that “[t]here is no undeveloped portion of the permit and therefore no basis exists for evaluating the extension pursuant to ORS 537.[2]30(2)(c) and OAR 690-315-0080(l)(f)” and “no basis for conditioning the extension on the development of a Division 86 [water management and conservation] plan.” Petitioner filed exceptions to the amended proposed order, including exceptions to those conclusions. In a final order issued September 14, 2010, the department denied all but one of petitioner’s exceptions,5 adopted the amended proposed order, and granted the city an extension of time, from October 1, 1999, to October 1, 2013, for it to perfect permit S-42117.

On October 15, 2010 — approximately one month later, and during the time allowed for filing a petition for judicial review of that final order — the city requested, and the department issued, a “Certificate of Water Right” to the city for the water right perfected under permit S-42117. See

Free access — add to your briefcase to read the full text and ask questions with AI

Related

WaterWatch of Oregon v. Water Resources Dept.
324 Or. App. 362 (Court of Appeals of Oregon, 2023)
Oregon Natural Resources Council Fund v. Port of Portland
398 P.3d 923 (Court of Appeals of Oregon, 2017)
Bandon Pacific, Inc. v. Environmental Quality Commission
359 P.3d 394 (Court of Appeals of Oregon, 2015)
WaterWatch of Oregon, Inc. v. Water Resources Department
342 P.3d 712 (Court of Appeals of Oregon, 2014)
City of Damascus v. Brown
337 P.3d 1019 (Court of Appeals of Oregon, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
316 P.3d 330, 259 Or. App. 717, 2013 WL 6498547, 2013 Ore. App. LEXIS 1463, Counsel Stack Legal Research, https://law.counselstack.com/opinion/waterwatch-of-oregon-inc-v-water-resources-department-orctapp-2013.