Bandon Pacific, Inc. v. Environmental Quality Commission

359 P.3d 394, 273 Or. App. 355, 2015 Ore. App. LEXIS 1024
CourtCourt of Appeals of Oregon
DecidedAugust 26, 2015
Docket1001950; A150445
StatusPublished
Cited by2 cases

This text of 359 P.3d 394 (Bandon Pacific, Inc. v. Environmental Quality Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bandon Pacific, Inc. v. Environmental Quality Commission, 359 P.3d 394, 273 Or. App. 355, 2015 Ore. App. LEXIS 1024 (Or. Ct. App. 2015).

Opinion

GARRETT, J.

Petitioner seeks judicial review of a final order by the Environmental Quality Commission (EQC) that imposed a civil penalty of $200,266. Between January 2004 and December 2008, a seafood processing plant owned by petitioner committed numerous violations of its National Pollution Discharge Elimination System (NPDES) permit and state laws applicable to the disposal of solid fish waste. Conceding that the violations occurred, petitioner nonetheless argues, in four assignments of error, that the EQC erred in its calculation and imposition of the civil penalty. We reject three of those assignments without further discussion, writing only to address petitioner’s argument that the EQC should have deemed the violations “minor” rather than “moderate” for purposes of calculating the penalty. For the reasons that follow, we conclude that EQC’s determination that petitioner’s violations were moderate in magnitude is not supported by substantial reason. We therefore reverse and remand.

We take the findings of historical fact as they were determined by the administrative law judge (AL J), because those findings were adopted by the EQC and, in any event, petitioner does not challenge them on judicial reviews. WaterWatch of Oregon, Inc. v. Water Resources Dept., 259 Or App 717, 720, 316 P3d 330 (2013), rev allowed, 355 Or 317 (2014). Petitioner owned and operated a seafood processing facility in Bandon, along the Coquille River, approximately one-half mile up from where the river enters the Pacific Ocean. Historically, the facility processed millions of pounds of fish each year. In 1999, however, petitioner stopped producing large quantities of seafood at that location and turned the site into a retail-only operation that processed only as much fish as needed to serve the facility’s retail customers.

During the relevant time, January 2004 to December 2008, the facility processed between 49,000 and 59,000 pounds of fish per year. It operated under an NPDES permit issued by the Oregon Department of Environmental Quality (DEQ).1 Although NPDES permits are required by the [357]*357federal Clean Water Act, in Oregon, the permitting program is administered by the DEQ. See ONRC Action v. Columbia Plywood, Inc., 332 Or 216, 218, 26 P3d 142 (2001) (explaining permitting scheme). In this case, the permit imposed four requirements on petitioner. First, it required all “waste-waters” to pass through “at least a 40 mesh screen * * * prior to discharge.”2 Second, it required petitioner to seek approval from DEQ before disposing “seafood processing residuals” into the waters of the state. Third, it required that petitioner monitor its wastewater by performing a series of specified tests and measurements. Fourth, it required petitioner to record the results of those measurements and submit a “discharge monitoring report” (DMR) to DEQ each month.

During the relevant period, petitioner violated the terms of the permit in several ways. The facility’s employees flushed the wastewater from the processed fish through a square drain on the floor of the facility that emptied directly into the Coquille River. The drain had a screen that caught some solid waste, but that screen did not meet the “40 mesh” requirement of the permit. Employees discharged the “seafood processing residuals” (fish carcasses) onto a chute that led directly into the Coquille River without, as the permit required, first obtaining DEQ approval. Petitioner also did not monitor its wastewater discharge. From January 2004 to December 2008, it submitted monthly DMRs to DEQ that simply stated “no production.”

On December 3, 2008, petitioner’s attorney sent a letter to DEQ that advised the agency that petitioner had committed permit violations and submitted inaccurate DMRs. Petitioner later submitted corrected DMRs that provided estimates of the amount of seafood processed each month, but did not include any information about water sampling results or about solid waste disposal. Petitioner [358]*358stopped disposing of solid wastes directly into the river sometime in December 2008. In January 2009, petitioner installed a drain screen that satisfied the “40 mesh” permit requirement. Eventually, petitioner connected the drain to the city sewer and stopped discharging wastewater directly into the Coquille River.

In November 2009, DEQ issued to petitioner a notice of civil penalty. According to the department’s formula (which was included in the notice), the “base penalty” for a violation is determined in part by the magnitude of that violation. Thus, for example, a violation that is determined to be “moderate” will result in a higher penalty than a violation that is determined to be “minor.” See OAR 340-012-0140. DEQ’s notice classified all of petitioner’s violations as “moderate” in magnitude. Petitioner requested a contested case hearing and argued, among other things, that the proposed penalty of $208,554 contained in DEQ’s notice should be reduced because the violations should be classified as minor rather than moderate.

By administrative rule, DEQ has assigned specific magnitudes to some categories of violations. The violations that petitioner committed are not among those that are assigned a magnitude by rule. See OAR 340-012-0135. Violations that are not assigned a different magnitude by rule are presumed to be moderate. OAR 340-012-0130(1). That presumption, however, is rebuttable. According to OAR 340-012-0130(2), a party may prove that a lesser magnitude applies by producing evidence that a lesser magnitude is “more probable than the presumed magnitude.” OAR 340-012-0130(4) explains what must be true for a violation to be minor:

“The magnitude of the violation is minor if [DEQ] finds that the violation had no more than a de minimis adverse impact on human health or the environment, and posed no more than a de minimis threat to human health or other environmental receptors. In making this finding, [DEQ] will consider all reasonably available information including, but not limited to: the degree of deviation from applicable statutes or commission and [DEQ] rules, standards, permits or orders; the extent of actual or threatened effects [359]*359of the violation; the concentration, volume, or toxicity of the materials involved; and the duration of the violation.”

At the contested case hearing, petitioner submitted evidence that included an underwater survey of the river near the processing facility. The AL J made specific findings with respect to that evidence:

“In 2010, [petitioner] retained the services of Alan Ismond, a chemical engineer, and his company Aqua-Terra Consultants. Mr. Ismond formed the company in 1993 to provide engineering and environmental consulting services to the seafood processing industry. In late 2010, Mr. Ismond commissioned a survey of the Coquille River bed in the area near [petitioner’s] facility. The survey revealed no visible remains of fish carcasses. [Petitioner] discharged fish wastes in an area of the river near the mouth of the Pacific Ocean. Because of that proximity, currents and tidal exchanges were substantial and likely dispersed any discharges of wastewater and fish carcasses very quickly. Because the waste did not accumulate on the river bed, Mr. Ismond concluded that the material was likely quickly dispersed into the ocean with no significant impact on the environment.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mendacino v. Board of Parole & Post-Prison Supervision
404 P.3d 1048 (Court of Appeals of Oregon, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
359 P.3d 394, 273 Or. App. 355, 2015 Ore. App. LEXIS 1024, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bandon-pacific-inc-v-environmental-quality-commission-orctapp-2015.