O’CONNELL, J.

Defendants appeal from a decree enjoining them from diverting the waters in an unnamed draw which are used by plaintiffs for irrigation purposes.

The suit may be described roughly as a contest between an irrigation district and two owners of farm land over the right to water in a draw extending through a part of the irrigation district. Defendants *268 contend that aside from surface water runoff the water in the draw consists solely of waste and seepage water from its irrigation project and that they have a right to recapture these waters while still within the boundaries of the reclamation project. Plaintiffs contend that the waters are not solely waste and seepage waters but consist, in part at least, of water having a source other than the irrigation project.

The defendant Payette Oregon Slope Irrigation District was organized in 1912 to provide water for the irrigation of agricultural lands within its boundaries. In 1919 and 1922 plaintiffs predecessors obtained water right certificates for the limited use of water flowing along the draw. Defendants do not contest plaintiffs’ claim to the water under these certificates. In 1937 the Owyhee Federal Reclamation Project was extended to the Owyhee District and the additional water used on the project began to create a drainage problem in the draw. A drain was constructed in 1938 to alleviate the problem. After the construction of the drain plaintiffs took water from that structure for irrigation purposes.

In early 1956 the project undertook construction of a ditch to recover for re-use in the district some of the *269 waste water flowing in the draw. Later in 1956 plaintiffs filed application for and received permits from the Oregon State Engineer for the irrigation of lands in addition to those covered by the 1919 and 1922 certificates. After issuance of the permits the plaintiffs opened the diversion ditch to allow the water to flow to their land. Defendants rebuilt the ditch and plaintiffs brought suit to enjoin the diversion of the water.

The trial court based its decision for the plaintiffs upon the ground that the certificates of water right issued to plaintiffs, not having been contested within three months after issuance, were conclusive evidence of plaintiffs’ rights, applying OBS 537.270, which reads as follows:

“A water right certificate issued in accordance with the provisions of OBS 537.250 which, after the expiration of three months from the date it is issued, has not been contested and canceled in the manner provided in OBS 537.260, and a water right certificate, when issued under OBS 539.140, shall be conclusive evidence of the priority and extent of the appropriation therein described in any proceeding in any court or tribunal of the state, except in those eases where the rights of appropriation thereby described have been abandoned subsequent to issuance of the certificate.”

It will be noted that OBS 537.270 makes the water right certificate conclusive only if not contested “in the manner provided in OBS 537.260.” OBS 537.260 (3) provides :

“ (3) Any person owning an application, permit or water right certificate subsequent in priority *270 may jointly or severally contest before the State Engineer the issuance of the water right certificate at any time before it has issued, and after the time has expired for the completion of the appropriation under the permit, or within three months after issuance of the certificate. The contest shall be brought upon application made, and hearing shall be had in the same manner and after notice as provided in OES 587.420 and 537.430 for proceedings for cancelation of permits. * * *”

It is apparent that OES 537.270, read together with 537.260, was intended to make a water right certificate conclusive only against a person whose water right was “subsequent in priority.” OES 537.270 does not purport to foreclose the interest of an owner whose water right originated prior to that claimed by a subsequent certificate holder. The question is, then, whether defendants’ right to the waters flowing in the draw were subsequent or prior to the rights of plaintiffs. If, as contended by plaintiffs, the waste and seepage waters from defendants’ irrigation project join with the waters of a natural stream flowing in the draw, then defendants would lose their right to recapture such waste and seepage waters. Under such circumstances all of the water in the stream would be subject to appropriation and plaintiffs’ permits and certificates being prior to any appropriation by defendants would render OES 537.260 applicable. If, however, the waters in the draw have their source solely in the waste and seepage waters and the occasional surface water runoff, then defendants would be entitled to recapture the water before it left the lands of the district.

The evidence is conflicting as to whether the waters flowing in the draw had their source solely from *271 waste, seepage and surface runoff or from other sources sufficient to characterize the watercourse as a stream. Examining the record de novo, as we must, we are of the opinion that the evidence supports defendants’ contention that a natural stream has never existed in the unnamed draw in question.

Free access — add to your briefcase to read the full text and ask questions with AI

Cleaver v. Judd, 393 P.2d 193, 238 Or. 266, 1964 Ore. LEXIS 410 (Or. 1964).

393 P.2d 193 (Cleaver v. Judd) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Waterwatch of Oregon, Inc. v. Water Resources Department
316 P.3d 330 (Court of Appeals of Oregon, 2013)
Wilber v. Wheeler
543 P.2d 1052 (Oregon Supreme Court, 1975)
Wilber v. Wheeler
534 P.2d 520 (Court of Appeals of Oregon, 1975)
Vandehey v. Wheeler
499 P.2d 1319 (Court of Appeals of Oregon, 1973)