Wartsila N. Am., Inc. v. Int'l Ctr. for Dispute Resolution
This text of 387 F. Supp. 3d 715 (Wartsila N. Am., Inc. v. Int'l Ctr. for Dispute Resolution) is published on Counsel Stack Legal Research, covering District Court, S.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Gray H. Miller, United States District Judge
Pending before this court are (1) a motion to dismiss filed by defendant International Centre for Dispute Resolution, a division of the American Arbitration Association, Inc. ("ICDR") (Dkt. 23); and (2) a motion to dismiss filed by defendant Hartford Steam Boiler Inspection and Insurance Company ("Hartford") (Dkt. 24). Having considered the motions, responses, replies, and the applicable law, the court is of the opinion that both motions (Dkts. 23, 24) should be GRANTED.
I. BACKGROUND
The plaintiffs in this case, Wärtsilä North America, Inc. ("Wartsila NA") and Wärtsilä Finland Oy ("Wartsila Finland") (collectively, "Wartsila"), seek a declaration that the parties do not have an agreement to arbitrate with the ICDR or American Arbitration Association ("AAA") and an injunction prohibiting the defendants from proceedings with a currently-pending ICDR arbitration. Dkt. 19. Wartsila NA is in the business of servicing power plant engines in North America. Id. According to Wartsila, the city of Raton, New Mexico, was at some point a member of the Arkansas River Power Authority ("ARPA"). Id. Wartsila NA entered into a contract with ARPA on or about May 6, 2002, to supply ARPA with a reciprocating engine to be used at a power plant in Raton (the "Equipment Supply Contract"). Id. On or about October 1, 2004, Wartsila *720and ARPA entered into another agreement for Wartsila to provide spare parts and maintenance for the power plant in Raton (the "Maintenance Agreement"). Id. In 2008, Raton and ARPA had a dispute relating to Raton's payment of its share of costs for ARPA's projects. Id. Seemingly as a result of a settlement of that dispute, Raton ceased its membership in ARPA in 2009. Id. Raton also purchased the engine in the power plant that Wartsila had sold to ARPA. Id. It purchased the engine "as-is" under an asset purchase agreement (the "Asset Purchase Agreement"). Id.
Approximately two years later, Raton Public Service ("RPS"), which is Raton's publicly-run electric company, requested a cost estimate from Watsila NA for the performance of inspection and maintenance services on the engine. Id. Wartsila NA provided a proposal on or about March 7, 2012. Id. Wartsila NA claims that Raton accepted the proposal (the "Inspection Contract"), which included accepting Wartsila's 2011 Terms and Conditions, including a term requiring that disputes be arbitrated before the International Court of Arbitration of the International Chamber of Commerce (the "ICC") and take place in Paris, France. Id. Wartsila claims that it completed its work under the Inspection Contract on September 10, 2012. Id. On or around October 2012, the engine and facility housing the engine suffered damage.1 Id.
On January 31, 2014, Hartford, which is an insurer and subrogee for Raton and RPS, along with Raton and RPS, initiated an arbitration with the AAA/ICDR2 against Wartsila NA and Wartsila Finland. Id. ; Dkt. 19-2, Ex. 6 (statement of claim). This statement of claim asserted breach of contract, breach of express and implied warranties, negligence and gross negligence, failure to warn, products liability, fraud or fraudulent inducement, breach of the duties of good faith and fair dealing, duties of care, trust, full disclosure and/or loyalty, and/or fiduciary duties, quantum meruit, unjust enrichment, promissory estoppel, and negligent misrepresentation. Dkt. 19; Dkt. 19-2, Ex. 6. In support of the ICDR's jurisdiction, the claimants identified a dispute resolution clause from the Maintenance Agreement between ARPA and Wartsila NA. Dkt. 19.
Wartsila claims that the terms of the Maintenance Agreement are inconsequential since Raton is not a party to the agreement and the only parties that can enforce that agreement are the named parties. Id. It asserts that the Maintenance Agreement specifically states that neither party can assign any of its rights under the contract without the written consent of the other party, and ARPA never asked Wartsila to consent to an assignment of the agreement to Raton. Id. Additionally, Wartsila points out that the agreement does not include Wartsila Finland, so even if an assignment to Raton were valid, the agreement does not bind Wartsila Finland. Id.
Wartsila notes in its complaint that the arbitration claimants allege that two additional contracts-the Equipment Supply Contract between ARPA and Wartsila NA and the Inspection Contract between Raton and Wartsila NA-authorize the arbitration. Id. Wartsila contends that neither of these contracts confers jurisdiction on the ICDR or AAA as (1) neither Raton nor Wartsila Finland is a party to or contemplated *721assignee of the Equipment Supply Contract; (2) Wartsila NA did not consent to an assignment of the Equipment Supply Contract to Raton, which is required under the contract; (3) the Inspection Contract's dispute resolution provision does not support ICDR or AAA jurisdiction; and (4) the Inspection Contract does not include Wartsila Finland. Id.
In February 2018, Wartsila sent a series of letters to the ICDR addressing these jurisdictional issues. Id. On March 8, 2018, ICDR responded that it would proceed with the administration of the arbitration and that any further arguments about jurisdiction should be made to the tribunal, once appointed. Id. According to Wartsila, in a letter dated March 12, 2018, the ICDR advised that it relied on the dispute resolution clause found on page 12 of the Maintenance Agreement. Id. The ICDR requested that the parties select three arbitrators from a list of fifteen by May 14, 2018. Id.
Wartsila filed its complaint and request for injunctive relief against both the ICDR and Hartford in this court on May 11, 2018. Dkt. 1. The defendants filed motions to dismiss the complaint. Dkts. 8, 14. On June 15, 2018, before the court ruled on the motions to dismiss or held a hearing on the request for injunctive relief, Wartsila filed its first amended complaint. Dkt. 19. In the amended complaint, Wartsila requests a declaratory judgment and injunction and asserts claims for tortious interference with contract against all parties and breach of contract against Hartford. Dkt. 19. Hartford and ICDR both filed amended motions to dismiss. Dkts. 23, 24. The ICDR seeks dismissal under the doctrine of arbitral immunity. Dkt. 23. Hartford seeks dismissal under Federal Rules of Civil Procedure 12(b)(1), 12(b)(2), 12(b)(3), 12(b)(6), and 12(b)(7). Dkt. 24. These motions are now ripe for disposition. The court will address the ICDR's motion first and then turn to Hartford's motion.
II. ICDR
The ICDR contends that the doctrine of arbitral immunity bars all of Wartsila's claims against it and that the ICDR is not a proper party to any dispute between Wartsila and Hartford relating to the enforceability of the arbitration provisions. Dkt. 23. Wartsila contends that immunity does not bar its claims against the ICDR because there is no specific agreement between the parties to be bound by the ICDR and because there was a clear absence of jurisdiction when the arbitration was initiated. Dkt. 28.
Free access — add to your briefcase to read the full text and ask questions with AI
Gray H. Miller, United States District Judge
Pending before this court are (1) a motion to dismiss filed by defendant International Centre for Dispute Resolution, a division of the American Arbitration Association, Inc. ("ICDR") (Dkt. 23); and (2) a motion to dismiss filed by defendant Hartford Steam Boiler Inspection and Insurance Company ("Hartford") (Dkt. 24). Having considered the motions, responses, replies, and the applicable law, the court is of the opinion that both motions (Dkts. 23, 24) should be GRANTED.
I. BACKGROUND
The plaintiffs in this case, Wärtsilä North America, Inc. ("Wartsila NA") and Wärtsilä Finland Oy ("Wartsila Finland") (collectively, "Wartsila"), seek a declaration that the parties do not have an agreement to arbitrate with the ICDR or American Arbitration Association ("AAA") and an injunction prohibiting the defendants from proceedings with a currently-pending ICDR arbitration. Dkt. 19. Wartsila NA is in the business of servicing power plant engines in North America. Id. According to Wartsila, the city of Raton, New Mexico, was at some point a member of the Arkansas River Power Authority ("ARPA"). Id. Wartsila NA entered into a contract with ARPA on or about May 6, 2002, to supply ARPA with a reciprocating engine to be used at a power plant in Raton (the "Equipment Supply Contract"). Id. On or about October 1, 2004, Wartsila *720and ARPA entered into another agreement for Wartsila to provide spare parts and maintenance for the power plant in Raton (the "Maintenance Agreement"). Id. In 2008, Raton and ARPA had a dispute relating to Raton's payment of its share of costs for ARPA's projects. Id. Seemingly as a result of a settlement of that dispute, Raton ceased its membership in ARPA in 2009. Id. Raton also purchased the engine in the power plant that Wartsila had sold to ARPA. Id. It purchased the engine "as-is" under an asset purchase agreement (the "Asset Purchase Agreement"). Id.
Approximately two years later, Raton Public Service ("RPS"), which is Raton's publicly-run electric company, requested a cost estimate from Watsila NA for the performance of inspection and maintenance services on the engine. Id. Wartsila NA provided a proposal on or about March 7, 2012. Id. Wartsila NA claims that Raton accepted the proposal (the "Inspection Contract"), which included accepting Wartsila's 2011 Terms and Conditions, including a term requiring that disputes be arbitrated before the International Court of Arbitration of the International Chamber of Commerce (the "ICC") and take place in Paris, France. Id. Wartsila claims that it completed its work under the Inspection Contract on September 10, 2012. Id. On or around October 2012, the engine and facility housing the engine suffered damage.1 Id.
On January 31, 2014, Hartford, which is an insurer and subrogee for Raton and RPS, along with Raton and RPS, initiated an arbitration with the AAA/ICDR2 against Wartsila NA and Wartsila Finland. Id. ; Dkt. 19-2, Ex. 6 (statement of claim). This statement of claim asserted breach of contract, breach of express and implied warranties, negligence and gross negligence, failure to warn, products liability, fraud or fraudulent inducement, breach of the duties of good faith and fair dealing, duties of care, trust, full disclosure and/or loyalty, and/or fiduciary duties, quantum meruit, unjust enrichment, promissory estoppel, and negligent misrepresentation. Dkt. 19; Dkt. 19-2, Ex. 6. In support of the ICDR's jurisdiction, the claimants identified a dispute resolution clause from the Maintenance Agreement between ARPA and Wartsila NA. Dkt. 19.
Wartsila claims that the terms of the Maintenance Agreement are inconsequential since Raton is not a party to the agreement and the only parties that can enforce that agreement are the named parties. Id. It asserts that the Maintenance Agreement specifically states that neither party can assign any of its rights under the contract without the written consent of the other party, and ARPA never asked Wartsila to consent to an assignment of the agreement to Raton. Id. Additionally, Wartsila points out that the agreement does not include Wartsila Finland, so even if an assignment to Raton were valid, the agreement does not bind Wartsila Finland. Id.
Wartsila notes in its complaint that the arbitration claimants allege that two additional contracts-the Equipment Supply Contract between ARPA and Wartsila NA and the Inspection Contract between Raton and Wartsila NA-authorize the arbitration. Id. Wartsila contends that neither of these contracts confers jurisdiction on the ICDR or AAA as (1) neither Raton nor Wartsila Finland is a party to or contemplated *721assignee of the Equipment Supply Contract; (2) Wartsila NA did not consent to an assignment of the Equipment Supply Contract to Raton, which is required under the contract; (3) the Inspection Contract's dispute resolution provision does not support ICDR or AAA jurisdiction; and (4) the Inspection Contract does not include Wartsila Finland. Id.
In February 2018, Wartsila sent a series of letters to the ICDR addressing these jurisdictional issues. Id. On March 8, 2018, ICDR responded that it would proceed with the administration of the arbitration and that any further arguments about jurisdiction should be made to the tribunal, once appointed. Id. According to Wartsila, in a letter dated March 12, 2018, the ICDR advised that it relied on the dispute resolution clause found on page 12 of the Maintenance Agreement. Id. The ICDR requested that the parties select three arbitrators from a list of fifteen by May 14, 2018. Id.
Wartsila filed its complaint and request for injunctive relief against both the ICDR and Hartford in this court on May 11, 2018. Dkt. 1. The defendants filed motions to dismiss the complaint. Dkts. 8, 14. On June 15, 2018, before the court ruled on the motions to dismiss or held a hearing on the request for injunctive relief, Wartsila filed its first amended complaint. Dkt. 19. In the amended complaint, Wartsila requests a declaratory judgment and injunction and asserts claims for tortious interference with contract against all parties and breach of contract against Hartford. Dkt. 19. Hartford and ICDR both filed amended motions to dismiss. Dkts. 23, 24. The ICDR seeks dismissal under the doctrine of arbitral immunity. Dkt. 23. Hartford seeks dismissal under Federal Rules of Civil Procedure 12(b)(1), 12(b)(2), 12(b)(3), 12(b)(6), and 12(b)(7). Dkt. 24. These motions are now ripe for disposition. The court will address the ICDR's motion first and then turn to Hartford's motion.
II. ICDR
The ICDR contends that the doctrine of arbitral immunity bars all of Wartsila's claims against it and that the ICDR is not a proper party to any dispute between Wartsila and Hartford relating to the enforceability of the arbitration provisions. Dkt. 23. Wartsila contends that immunity does not bar its claims against the ICDR because there is no specific agreement between the parties to be bound by the ICDR and because there was a clear absence of jurisdiction when the arbitration was initiated. Dkt. 28.
"As with judicial and quasi-judicial immunity, arbitral immunity is essential to protect decision-makers from undue influence and protect the decision-making process from reprisals by dissatisfied litigants....In proper circumstances, organizations that sponsor arbitrations, as well as arbitrators themselves, enjoy this immunity from civil liability." New England Cleaning Servs., Inc. v. Am. Arbitration Ass'n ,
Wartsila notes in its response to the ICDR's motion to dismiss that while the ICDR "demanded that Hartford and Wärtsilä press forward with the selection of 3 arbitrators from a supplied list of 15 potential arbitrators so the ICDR [could] appoint an arbitration panel" after Wartsila "point[ed] out the clear absence of AAA/ICDR jurisdiction on the face of Hartford's Statement of Claim and accompanying documents," the ICDR later stayed the administration of the arbitration pending this court's resolution of Wartsila's claims. Dkt. 28. The ICDR argues that the intake manager for AAA/ICDR should not be tasked with making a determination regarding whether there is an enforceable arbitration agreement between the parties, which would be equivalent to having the court's clerk issue of ruling on the jurisdiction of the court. Dkt. 23.
The court finds the First Circuit's opinion in New England Cleaning Services , which addressed a similar issue, instructive and persuasive. In New England Cleaning Services , the district court dismissed New England Cleaning Services' complaint for an injunction and damages against the AAA.
On appeal, the AAA argued that "arbitral immunity protect[ed] its processing of a facially valid demand for arbitration pursuant to a collective bargaining agreement that names it as the arbitral agency."
The relevant question for courts following the reasoning in New England Cleaning Services is whether the resolution of the arbitrability issue is facially obvious. If it is not facially obvious, then immunity should apply to the administrative stages prior to an official appointment of an arbitrator or panel or arbitrators.
Here, in the Statement of Claim, Raton and Hartford contended that Raton is a member of ARPA. Dkt. 19-2, Ex. 6 at 1. They stated that Raton, in conjunction with ARPA, requested proposals for the installation of power equipment at RPS. Id. at 2. They also stated that "Raton and/or ARPA on Raton's behalf and [Wartsila NA and Wartsila Finland] entered into a contract" for Wartsila to install its product in 2002 and that in 2004 "Raton and [Wartsila NA and Wartsila Finland] entered into a contract whereby [Wartsila NA and/or Wartsila Finland] were to provide maintenance for the operation of" the equipment. Id. The statement of claim indicated that "[p]ursuant to two contracts pursuant to which Raton and [Wartsila NA and Wartsila Finland] did business, a dispute resolution provision required arbitration with AAA in Colorado." Id. at 3.
On February 15, 2018, Wartsila wrote a letter to the ICDR and argued that the initial agreement submitted by Raton and Hartford to support jurisdiction was between parties that were not even named in the arbitration and the agreement could not be assigned without written consent. Dkt. 19-2, Ex. 12.
On February 16, 2018, Raton and Hartford sent a letter responding to Wartsila's February 15 email and asserted that various contracts amongst the parties conferred jurisdiction on the AAA. Dkt. 19-2, Ex. 9. They attached a copy of Wartsila NA's initial proposal and asserted that the arbitration clause in that agreement defines the parties as "Wartsila Group" and "Customer," which is Raton. Dkt. 19-2, Ex. 9 at 1-2. It also lists the "orderer" as "Raton Public Service." Dkt. 19-2, Ex. 9, Ex. 1. It states the proposal is extended under "Wartsila General Terms and Conditions-Service Work (2011)." Id. The arbitration provision in the terms and conditions states that claims arising out of the contract should be submitted to arbitration with the International Court of Arbitration of the International Chamber of Commerce (the "ICC") and take place in Paris, France. Id. Raton and Hartford argued in this February 16 letter that under the International Arbitration Rules, issues relating to jurisdiction that are raised before the tribunal is constituted should be " 'referred to the tribunal for determination once constituted.' "3 Id. at 2 (quoting the International Arbitration Rules, Rule 19).
On February 16, 2018, Wartsila again wrote to the ICDR stating that Raton and *724Hartford's letter relied on a contract not in their petition that is "null and void" by its express terms and, at any rate, calls for arbitration with the ICC, not ICDR. Dkt. 19-2, Ex. 13. Wartsila also argued that it would be an "incredible waste of ICDR's and the would-be respondent's time and resources" for the panel to decide arbitrability. Id.
On February 23, 2018, Hartford and Raton sent an email to the ICDR stating that there is "no doubt that the AAA has jurisdiction over this matter" and attaching (1) the Equipment Supply Contract; (2) the December 3, 2001 Request for Proposals; (3) the Asset Purchase Agreement between ARPA and Raton; (4) the Maintenance Agreement; (5) an agreement between Raton and Wartsila NA from 2012; and (6) the 2011 terms and conditions. Dkt. 19-2, Ex. 10. Hartford and Raton's counsel advised the "Administrator" that "this is not the simple matter that Respondents claim. Instead, the issues are complex, and Claimants are entitled under fundamental due process to a determination of these issues by a Panel as required by the AAA Rules." Id.
• The Equipment Supply Contract is clearly between ARPA as the "Buyer" and Wartsila NA as the "Seller." Id. The Equipment Supply Contract calls for arbitration of claims arising out of or relating to that agreement by the AAA. Id. ¶ 16.2.1. Another provision of the agreement states that it is "intended for the sole benefit of Buyer and Seller, and there are no third-party beneficiaries other than assignees contemplated by the terms herein." Id. ¶ 18.8. Attached to the Equipment Supply Contract is a Seller Performance Guaranty by Wartsila Finland in favor of ARPA "and its successors and assigns." Id. , Ex. 2.2.
• The December 3, 2001 request for proposal states that Raton is a member of ARPA and that "ARPA, in conjunction with Raton, is requesting proposals...." Id.
• The Asset Purchase Agreement, dated January 15, 2010, is between ARPA and Raton. Dkt. 19-2, Ex. 4. The assets include the Wartsila engine. Id. , Ex. A.
• The Maintenance Agreement, dated October 1, 2004, is between ARPA and Wartsila NA. Dkt. 19-2, Ex. 5. This agreement requires that claims originating under the agreement must be arbitrated with the AAA. Id. ¶ 17. In another section, it clearly states that the parties cannot assign obligations under the contract without the written consent of the other party and that there are "no third-party beneficiaries other than assignees contemplated by the terms herein." Id. ¶¶ 21-22.
• The 2011 terms and conditions relate to Wartsila's work for a "customer." Dkt. 19-2, Ex. 14, Ex. C. It calls for arbitration of any dispute arising from the contract to be held with the ICC in Paris, France. Id.
On February 23, 2018, Wartsila provided "one last statement" on the jurisdiction matter, and it attached the Maintenance Agreement, the March 7, 2012 Proposal, the 2011 terms and conditions, and two letters from Wartsila's counsel to Hartford's counsel. Dkt. 19-2, Ex. 14. It asserted that no claimant was a party to the Maintenance Agreement, there can be no third-party beneficiaries or assignments of the agreement unless there is written consent, and the agreement expired on October 2, 2007. Id. It argued that both the 2008 and 2011 terms and conditions call for arbitration with the ICC, not the ICDR. Id. The March 7, 2012 Proposal includes the 2008 terms and conditions, which Wartsila contends are inapplicable.
*725Dkt. 19-2, Ex. 14, Ex. B. Regardless, the 2008 terms and conditions, like the 2011 terms and conditions, call for arbitration of disputes arising from the contract to be arbitrated with the ICC in Paris, France. Id.
On February 26, 2018, Wartsila sent a letter asserting that the Equipment Supply Contract does not vest ICDR with jurisdiction because none of the named parties is a party to the Equipment Supply Contract. Dkt. 19-2, Ex. 15. It also asserted that even if the claimants were somehow parties to the contract, the contract requires arbitration under the AAA's construction arbitration rules, not the ICDR. Id.
On March 8, 2018, the ICDR advised the parties that it decided to proceed with the administration of the matter in the absence of an agreement by the parties or a court order. Dkt. 19-2, Ex. 16. On April 30, 2018, it requested that the parties choose three arbitrators before May 14, 2018. Dkt. 19-2, Ex. 18. Three days later, Wartsila filed suit against the ICDR and Hartford in this court.
This case was not even in front of the arbitration panel yet and already the parties have made significant arguments pointing to multiple arbitration provisions that may or may not have been assignable. This was not the simple issue that Wartsila suggests. And it is certainly not an issue that seems appropriate to ask an administrator who is tasked with getting the parties to choose the panel to resolve. It is an issue more appropriately considered by the panel. There is not a "clear absence" of jurisdiction, and there is definitely not a "clear absence" of jurisdiction that is so obvious that it could be resolved before the arbitrators are even empaneled. The court finds that the ICDR is protected by arbitral immunity. The ICDR's motion to dismiss is GRANTED, and the claims against the ICDR are DISMISSED.
III. HARTFORD
Hartford seeks dismissal under Federal Rules of Civil Procedure 12(b)(1), (2), (3), (6), and (7). Dkt. 24. It claims that (1) the court lacks general and specific jurisdiction over Hartford; (2) the court lacks subject matter jurisdiction because the parties delegated the determination of arbitrability to the arbitrators; (3) this district is an improper venue; (4) Wartsila failed to join necessary parties: Raton and RPS; and (5) Watsila fails to state a claim for which relief can be granted under Rule 12(b)(6). Id. Wartsila objects to all of these arguments. Dkt. 30. The court addresses only subject matter and personal jurisdiction.
A. Subject Matter Jurisdiction
Hartford contends that if, as Wartsila contends, Hartford is bound by the terms of the Inspection Contract, then the court lacks subject matter jurisdiction because the ICC, and not this court, has subject-matter jurisdiction. Dkt. 24 at 14. Wartsila agrees that the ICC is the proper forum for claims between the parties to the Inspection Contract, but it asserts that Hartford is not a party to the Inspection Contract and cannot enforce its terms.4 Dkt. 30 at 18.
"Enforcement of an arbitration agreement involves two analytical steps. The first is contract formation-whether the parties entered in any arbitration *726agreement at all. The second involves contract interpretation to determine whether this claim is covered by the arbitration agreement. Ordinarily both steps are questions for the court." Kubala v. Supreme Prod. Servs., Inc. ,
"[P]arties are free to delegate questions to an arbitrator, including questions regarding the validity and scope of the arbitration provision itself." Arnold v. Homeaway, Inc. ,
In Brittania-U Nigeria, Ltd. v. Chevron USA, Inc. , the Fifth Circuit considered a case in which the defendant moved to dismiss based on an arbitration provision in a confidentiality agreement between the Brittania-U Nigeria, Ltd. ("Brittania") and Chevron U.S.A. Inc. ("Chevron").
Here, like in Brittania , a non-signatory is attempting to enforce the arbitration agreement that was clearly signed by Wartsila NA. Thus, Brittania is on point. The court, however, is not convinced that this is a jurisdictional question. In Brittania , the Fifth Circuit determined that the parties had contractually agreed to let the arbitrator determine arbitrability, but it did not indicate that there was an issue with the court having the power to make that initial call. Thus, to the extent Hartford relies on Brittania for dismissal based on lack of subject matter jurisdiction, the motion is DENIED.
B. Personal Jurisdiction
Turning to personal jurisdiction, the court will first set forth the legal standard, and then it will address general and specific jurisdiction, respectively.
*7271. Legal Standard
Federal courts are courts of limited jurisdiction. Ins. Corp. of Ir., Ltd. v. Compagnie des Bauxites de Guinee ,
When the court rules on personal jurisdiction without an evidentiary hearing, the plaintiff must make a prima facie showing of jurisdiction. The burden then shifts to the defendant to demonstrate that the assertion of jurisdiction would be unfair; however, such demonstrations are rare. Wien Air Alaska, Inc. v. Brandt ,
The Due Process analysis entails a two-part inquiry. Asarco, Inc. v. Glenara, Ltd. ,
Minimum contacts are established through the assertion of either general or specific jurisdiction. Panda Brandywine Corp. v. Potomac Elec. Power Co. ,
A court may exercise specific jurisdiction if "the cause of action arises out of a defendant's purposeful contacts *728with the forum." Dalton v. R&W Marine, Inc. ,
2. General Jurisdiction
Hartford, relying on the U.S. Supreme Court's requirement in Daimler AG v. Bauman that a corporation must be "at home" in a state in order for the state to exercise general jurisdiction, argues that it is not "at home" in Texas and that the court therefore cannot exercise general jurisdiction over it. Dkt. 24. Wartsila contends in its amended complaint that Hartford has purposefully availed itself of the privileges of conducting business in Texas as a licensed insurance company, maintains its regional headquarters in Houston, Texas, has its insurance rates and policies approved by the State of Texas so that it can issue policies to Texas citizens, employs a large number of Texas citizens, and on information and belief, conducts a significant portion of its overall business in Texas. Dkt. 19. It asserts that Hartford has not controverted any of these facts and that the court should therefore take all of these allegations as true and find that they establish that Hartford is "essentially at home and subject to general jurisdiction in Texas." Dkt. 30 at 20. Wartsila relies on Shelter Mutual Insurance Co. v. Dallas County Hospital District ,
a. Shelter
In Shelter , the Dallas Court of Appeals of Texas considered an interlocutory appeal filed by an insurer when the trial court denied the insurer's special appearance.
*729
b. Daimler
In Daimler , the plaintiffs brought suit in California and premised jurisdiction over DaimlerChrysler Aktiengesellschaft ("Daimler"), a German company, on the contacts of its U.S. subsidiary, Mercedes-Benz USA, LLC ("MBUSA").
The court did not "foreclose the possibility that in an exceptional case...a corporation's operations in a forum other than *730its formal place of incorporation or principal place of business may be so substantial and of such a nature as to render the corporation at home in that State," but pointed out that Daimler's activities did not approach that level.
c. Bors
Wartsila, nevertheless, urges the court to follow Shelter 's exercise of general jurisdiction when an insurance company is "doing business" in Texas, even though "doing business" and being "at home" are not similar standards. It uses Bors v. Johnson & Johnson to advocate for this position. The Eastern District of Pennsylvania considered Daimler when it decided Bors v. Johnson & Johnson . The Bors plaintiff alleged that Johnson & Johnson's baby powder caused ovarian cancer.
Bors would be on point if this court were located in Pennsylvania and or there was evidence that Hartford consented to general jurisdiction when it registered to do business in Texas. But here, there is no evidence or allegation that registering in Texas involves consent to general jurisdiction, and the word "consent" is not even used in Shelter .5 Instead, the Shelter court relied on its determination that the defendant's contacts with Texas were "continuous and systematic," not that they were "so continuous and systematic as to render it essentially at home" in Texas. Compare Shelter ,
*731Here, Wartsila contends Hartford is licensed in Texas, maintains its regional headquarters in Houston, Texas, has its insurance rates and policies approved by the State of Texas so that it can issue policies to Texas citizens, employs a large number of Texas citizens, and on information and belief, conducts a significant portion of its overall business in Texas. Dkt. 19. Hartford has not controverted theses assertions with affidavits and instead argues that, taking these allegations as true, these contacts are not sufficient for the exercise of general jurisdiction under Daimler . The court agrees. None of these allegations amounts to the exceptional type of case discussed by the Daimler court, and the court therefore finds that it may not exercise general jurisdiction over Hartford.
3. Specific Jurisdiction
The court now turns to specific jurisdiction. The court will first discuss the specific jurisdiction allegations contained in the amended complaint, and then it will set forth the parties' arguments relating to specific jurisdiction and determine whether the exercise of specific jurisdiction over Hartford is appropriate in this case.
a. Jurisdictional Allegations in the Amended Complaint
Wartsila alleges in its amended complaint that the Inspection Contract, entered into between Wartsila NA and RPS, was negotiated, formed, and partially performed in Houston, Texas, and is governed by Texas law.6 Dkt. 19. It asserts that the Inspection contract requires all disputes arising from the agreement be brought in an arbitration with the ICC in Paris, France.
b. Hartford's Arguments
Hartford contends that the court lacks specific jurisdiction because (1) Wartsila fails to state a claim for breach of contract and intentional interference with contract, so there can be no specific jurisdiction with regard to these claims; (2) claims over which the court does not have subject-matter jurisdiction cannot support specific contacts; and (3) the Inspection Contract and the alleged breach of it do not constitute specific contacts with Texas. Dk. 24.
c. Wartsila's Arguments
Wartsila argues that the court should exercise specific jurisdiction over Hartford because (1) Hartford, from its home office in Texas, directed and caused its Texas lawyer to hale a Texas citizen into arbitration for which no contract exists, causing Wartsila NA harm in Texas; (2) Hartford tortiously interfered with Wartsila NA's (a Texas citizen) rights in a contract negotiated, *732formed, and performable in part in Texas (the Inspection Contract), causing Wartsila NA harm in Texas; and (3) Hartford, standing in the shoes of RPS, breached Wartsila NA's (a Texas citizen) contract that was negotiated, formed, and performable in part in Texas and requires the application of Texas law, causing Wartsila NA harm in Texas. Dkt. 30 at 11. Wartsila asserts that Hartford bears the burden of presenting a "compelling case" that the exercise of jurisdiction would violate due process, and it has not done so.
d. Hartford's Contacts
The court's specific jurisdiction analysis starts and ends with Hartford's argument that its contacts with Texas do not support specific jurisdiction. Hartford argues that a nonresident contracting with a Texas resident is not a sufficient contact to subject the nonresident to the forum's jurisdiction. Dkt. 24 at 14. Additionally, while taking issue with Wartsila's assertion that the Inspection Contract requires the application of Texas law, Hartford asserts that even if it did, that is not enough to create specific jurisdiction in Texas. Id. at 15. Finally, Hartford argues that Wartsila's argument that the location of Wartsila's lawyers supports specific jurisdiction is "spurious and not supported by any authority." Id. Hartford asserts that its lawyers merely filed an arbitration electronically with the AAA, which is a citizen of New York, and they could have done so from anywhere in the world. Id. at 16. Hartford also asserts that Wartsila's contention that it was injured in Texas is insufficient to support specific jurisdiction. Id.
Hartford relies on Holt Oil & Gas Corp. v. Harvey . In Holt Oil , which was a breach-of-contract case, the Fifth Circuit determined that the following contacts were insufficient to support specific jurisdiction: (1) the defendant entered into a contract with the plaintiff, a Texas corporation; (2) the defendant sent a final revised agreement from Oklahoma to Texas; (3) the defendant sent three checks to Texas in partial performance of the contract; and (4) the defendant engaged in extensive telephonic and written communication with the plaintiff.
Holt Oil is on point to the extent that Wartsila asserts a breach-of-contract claim. However, the alleged breach in this case does not relate to the material performance of the contract, which Wartsila acknowledges it completed in 2012. Rather, it relates to bringing an arbitration in a forum other than the forum specified in the contract-neither of which is Texas. RPS may have reached out to Texas with regard to negotiating the arbitration clause, but it was contracting for a potential arbitration in Paris, France. The court notes that in this case, unlike Holt Oil , the contract allegedly called for the application of Texas law.7 While this is certainly a *733consideration in the jurisdictional analysis, it is not determinative. See Burger King ,
The tortious interference claim arises out of the filing of an arbitration, which Wartsila contends interfered with its contract with RPS to arbitrate claims with the ICC in Paris, France. Dkt. 19. The arbitration was filed by attorneys in Texas, but the court finds that fact to be of little consequence. See Thompson Hine, LLP v. Taieb ,
The court finds that Wartsila has not presented a prima facie case of specific jurisdiction with regard to the breach of contract and tortious interference claims. The other claims stem from these claims; thus, Hartford's contacts relating to the other claims also do not support personal jurisdiction. The court need not consider Hartford's other jurisdictional arguments or its other grounds for dismissal. Hartford's motion to dismiss for lack of personal jurisdiction is GRANTED. Wartsila's claims against Hartford are DISMISSED WITHOUT PREJUDICE.
IV. CONCLUSION
The ICDR's motion to dismiss (Dkt. 23) is GRANTED. Wartsila's claims against the ICDR are DISMISSED WITH PREJUDICE.
Hartford's motion to dismiss (Dkt. 24) is GRANTED. Wartsila's claims against Hartford are DISMISSED WITHOUT PREJUDICE for lack of personal jurisdiction.
The court will enter a final judgment concurrently with this memorandum opinion and order.