Warner v. Cox

487 F.2d 1301
Court of Appeals for the Fifth Circuit·Decided January 11, 1974·No. Nos. 73-1627, 73-2275·Published·Cited by 52 cases

Opinion

GEE, Circuit Judge:

On May 1, 1969, Appellee, Litton Systems, Inc. (Litton), and the Navy Department executed a multi-billion dollar contract for the procurement of five large ships, each about the size of an aircraft carrier, described as Landing Helicopter Assault Vessels (LHA). The contract’s novel concept, and at least a remote if not a proximate cause of this suit, was “total package procurement.” Litton was not only to construct but to design the vessels, a departure from received procurement wisdom.

Litton’s design responsibility entailed a substantial paper-work phase preceding any hardware production, thus requiring modification of the Navy’s standard “per cent of physical completion” payment clause. In so doing, the scriveners fathered what we may charitably call a hybrid: for the first forty months, a period deemed sufficient for completion- of design and a good start on production, Litton was to be reimbursed weekly for its actual costs incurred; thereafter, payment was to be made upon the conventional percentage-of-completion plan. Transition from one payment plan to another was to be accomplished by determining the amount which would have been due on. a percentage-of-completion basis at the end of the initial forty-month period and comparing it with actual payments made to Litton. Any overage was to be refunded by Litton under an arrangement, appar[1303] ently intended as an exclusive remedy, whereby Litton would continue work without pay for a period not exceeding three months and would then repay in cash any amount remaining due after credit for the unpaid work.

At the end of the initial period and one agreed six-month extension, the officer in charge of the contract for the Navy (contracting officer) denied any further extension of the cost refund pro-' gram, thus placing payment on a percentage-of-completion basis, and determined that at the point of transition Litton had received nearly fifty-five million dollars in overpayments. Litton promptly took an administrative appeal to the Armed Services Board of Contract Appeals, where it pends. At about the same time, Litton applied to a different official, the financing officer, for an unrelated administrative remedy, deferment of the repayment until the contract appeal fixed its amount. This remedy, founded in regulations of general application1 2and not in the text of the contract, but similar or identical in effect to the extension sought of the contracting officer, was also denied. Litton sued in United States District Court to reverse this denial, asserting that the financing officer had violated various regulations in ruling adversely on its request for deferred payment. Jurisdiction was pleaded in the federal question, mandamus and declaratory judgment statutes (28 U.S.C. 1331, 1361, 2201-2202) and in the Administrative Procedure Act (5 U.S.C. 702-706). The United States resisted, asserting mandatory and exclusive jurisdiction in the Court of Claims under the Tucker Act.

The court below ruled it had federal question arid Administrative Procedure Act (APA) jurisdiction, concluded that the Navy had indeed transgressed various procurement regulations, and entered an injunction obliquely ordering the defendants to continue to pay Litton’s vouchers currently,2 an expenditure averaging approximately three million dollars per week. This appeal and a petition for writ of mandamus or prohibition to confine the court below to its jurisdiction followed, were heard and will be decided together. After argument of this case, we stayed the district court injunction pending our decision on the merits. We now reverse.

This is a suit against the United States, though in form against its ministers, Dugan v. Rank, 372 U.S. 609, 620, 83 S.Ct. 999, 10 L.Ed.2d 15 (1963). The order of the court below amply meets the Dugan test, expending itself (with sensible impact) on the public treasury and compelling the government to pay money in advance of the time specified in its contract, money which it conceivably might never otherwise have to pay at all.

Litton virtually conceded at oral argument that jurisdiction in the district court must stand on the APA or fall.3 In the view which we take of the case, a correct resolution of the issues raised by the briefs of soveriegn immunity and its waiver vel non, of the extent to which the APA is to be deemed a grant of jurisdiction, and of the interplay of the APA and the Tucker Act4 commences and virtually ends with analysis and characterization of Litton’s claim and of the relief Litton seeks and has received [1304] from the district court. Once this claim is properly identified, the rest becomes plain.

None of the substantive claims presented to the court below concerned anything but the payment of money— when, how much, and by whom it should be paid. The government contends that all were founded solely in Litton's express contract with the United States, and that it has consented to be sued ex contractu only in the Court of Claims under the Tucker Act. Litton urges that its sole claim below was for review of administrative errors committed in the process of refusing a deferred payment agreement, noting that such agreements have their source in general procurement regulations rather than in this contract. It points out in this connection that the more distinctively contract claims — the amount of the overpayment and termination of the cost reimbursement scheme of payment — are already on administrative appeal and “. are not before the District Court.” (emphasis Litton’s)

The court below adopted Litton’s view:

This suit against these government officials in their official capacity is undeniably a suit against the United States, but it is not for the recovery of any money from the United States or the Defendants. The sole purpose of this suit is for a review of the administrative actions of these defendants in arbitrarily and capriciously denying deferment of the immediate payment of approximately $54,660,000 as advancements or payments in that amount in excess of the amount payable under progress estimates under the contract, (emphasis the court’s)

Free access — add to your briefcase to read the full text and ask questions with AI

Warner v. Cox, 487 F.2d 1301 (5th Cir. 1974).

487 F.2d 1301 (Warner v. Cox) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Reich v. Berryhill
N.D. Texas, 2019
Doe v. United States
372 F.3d 1308 (Federal Circuit, 2004)
Tucson Airport Authority v. General Dynamics Corp.
922 F. Supp. 273 (D. Arizona, 1996)
Robishaw Engineering, Inc. v. United States
891 F. Supp. 1134 (E.D. Virginia, 1995)
Pender Peanut Corp. v. United States
20 Cl. Ct. 447 (Court of Claims, 1990)
Bowen v. Massachusetts
487 U.S. 879 (Supreme Court, 1988)
Divine Farms, Inc. v. Block
679 F. Supp. 867 (S.D. Indiana, 1988)
Esch v. Lyng
665 F. Supp. 6 (District of Columbia, 1987)
Ingersoll-Rand Company v. United States
780 F.2d 74 (D.C. Circuit, 1985)
Management Science America, Inc. v. Pierce
598 F. Supp. 223 (N.D. Georgia, 1984)
Jesko v. United States
3 Cl. Ct. 730 (Court of Claims, 1983)
Group Health Inc. v. Schweiker
549 F. Supp. 135 (S.D. Florida, 1982)
Megapulse, Inc. v. Lewis
672 F.2d 959 (D.C. Circuit, 1982)
Oliver v. Veterans Administration
519 F. Supp. 112 (D. Puerto Rico, 1981)
Graham v. Henegar
640 F.2d 732 (Fifth Circuit, 1981)