Warm Springs Dam Task Force v. Gribble

378 F. Supp. 240, 6 ERC 1737
CourtDistrict Court, N.D. California
DecidedJune 1, 1974
DocketC-74-0649-SW
StatusPublished
Cited by15 cases

This text of 378 F. Supp. 240 (Warm Springs Dam Task Force v. Gribble) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Warm Springs Dam Task Force v. Gribble, 378 F. Supp. 240, 6 ERC 1737 (N.D. Cal. 1974).

Opinion

MEMORANDUM

SPENCER WILLIAMS, District Judge.

Plaintiffs seek a preliminary injunction to delay the award of a contract for the construction of a major segment of the proposed Warm Springs Dam and Lake Sonoma Project (Project) until such time as alleged deficiencies in the environmental impact statement (EIS) can be remedied.

The Project consists of a dam across Dry Creek, a major tributary of the Russian River in Sonoma County, California, a reservoir, a spillway, outlet facilities, recreation facilities, a fish hatchery, and channel improvements on Dry Creek downstream of the dam. The Project also includes 17,658 acres of land, 24 miles of relocated roads, several miles of relocated utilities, various public use facilities, such as campgrounds and picnic areas and a wildlife management area. The general location of the Project is in the Russian River Basin approximately fifty (50) miles northwesterly of San Francisco. It was authorized by the Flood Control Act of 1962, Public Law 87-874 approved 23 October 1962 by the 87th Congress, 2d Session. The project then authorized was smaller than the one now planned. Project design, land acquisition and road relocations were the major activities from that date to January 1, 1970 when the National Environmental Protection Act became law. In June 1973 the Draft Environmental Impact Statement was completed and distributed. On August 30 and September 5, 1973 public hearings were held and on December 4, 1973, the Final Environmental Impact Statement was filed with the Council on Environmental Quality. 1 Additional copies were distributed to various interested persons with the invitation to file comments with the Council within thirty (30) days. On February 14, 1974, the Council on Environmental Quality made its comments on the report. On February 15, 1974 the Corps called for bids and bids have been received, the low being in excess of 13 million dollars. On March 22, 1974 the complaint and motion for a preliminary injunction were filed and a temporary restraining order and order to show cause issued. The hearing on the matter was set for March 29th, but continued by stipulation to April 22. The temporary restraining order was continued by '-stipulation to May 27th. On April 2, 1974, the Secre *243 tary of Interior determined that the Dry Creek Warm Springs Valley Archeological District may be eligible for inclusion in the National Register of Historical Places, 2 and on May 9th, following twelve (12) days of hearings, the matter was submitted for decision.

It is estimated that the total Project will cost $114 million. The Corps claims that approximately $35 million has already been expended.

The complaint alleges jurisdiction under 5 U.S.C. § 702 (Review of Agency Action), 28 U.S.C. § 1331(a) (Federal Question), 28 U.S.C. § 133?" (Regulation of Interstate Commerce) and 28 U.S.C. §§ 2201 and 2202 (Declaratory Judgment). It sets forth twelve (12) separate claims arising under a number of Federal Statutes and Regulations 3 but the attack is focused in two areas: (1) violations of National Environmental Policy Act § 102(2) (A) and (2) noncompliance with the National Registration of Historic Places Act (§16 U.S.C. § 470 et seq. and Executive Order 11593).

The issues before the Court must be considered under 5 U.S.C. § 706(2) (D), 4 and are: (1) whether the Environmental Impact Statement conforms to the requirement of the National Environmental Policy Act and the regulations issued pursuant thereto, (2) whether the Corps has complied with the requirements of the National Historical Preservation Act and Executive Order 11593, (3) what remedy, if any, can be fashioned by the Court which would best effectuate the policies of the President and the Congress as such policies are set forth in the Executive Order and the statutes in question.

The EIS attack follows the standard pattern of many such challenges, namely that the discussion is not sufficiently detailed nor is it sufficiently descriptive of the environmental impact to be caused by the proposed Project. The complaint in this instance alleges seven (7) deficiencies:

1. Failure to discuss ecological impact that would result should the contemplated dam fail;

*244 2. Insufficient discussion of the existence and amount of mercury that will be present in the reservoir water due to the flooding of a mercury mine, and in the fish due to a build-up of mercury in the food chain;

3. Adequacy of coverage on the various alternatives to the proposed Project;

4. Failure to adequately consider and discuss a geothermal resource loss which may result from the inundation of hot springs in the reservoir area;

5. Insufficient discussion of the downstream improvements and channelization which are contemplated by the Project;

6. Alleged defects in the computation of the benefit cost ratio and particularly in the use of 3%o% interest rate; and

7. Failure to discuss the growth-inducement factor of the additional water supply which will be made available by the Project.

The question of whether an EIS complies with the mandates of NEPA has been extensively litigated. While the circuits do not agree on what purpose is to be served by an EIS, the Ninth Circuit holds that it is to inform the decision makers of the environmental ramifications of the proposed action, nothing more and nothing less. Life of the Land v. Brinegar, 485 F.2d 460 (9th Cir. 1973). The EIS should provide a basis for evaluation of the benefits of the proposed Project in light of its environmental risks and draw a comparison of the net balance for the proposed action with the environmental risks presented by other alternative courses of action. Natural Resources Defense Council, Inc. v. Morton, 148 U.S.App.D.C. 5, 458 F.2d 827 (1972); Life of the Land v. Brinegar, supra.

More specifically, an EIS must at a minimum contain such information as will alert the President, the Council on Environmental Quality, the public and the Congress to all known possible environmental consequences of an agency’s action. Environmental Defense Fund v. Armstrong, 352 F.Supp. 50 (N.D.Cal.1972); affirmed at 487 F. 2d 814 (9th Cir. 1973); cert. denied 416 U.S. 974, 94 S.Ct. 2002, 40 L.Ed.2d 564 (1974).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Oregon Environmental Council v. Kunzman
817 F.2d 484 (Ninth Circuit, 1987)
Oregon Environmental Council v. Kunzman
614 F. Supp. 657 (D. Oregon, 1985)
Ecology Action v. Van Cort
99 Misc. 2d 664 (New York Supreme Court, 1979)
Central Okl. Preservation A. v. OKL. CITY, ETC.
471 F. Supp. 68 (W.D. Oklahoma, 1979)
Warm Springs Dam Task Force v. Gribble
431 F. Supp. 320 (N.D. California, 1977)
Andujar v. Weinberger
69 F.R.D. 690 (S.D. New York, 1976)
Bucks County Board of Commissioners v. Interstate Energy Co.
403 F. Supp. 805 (E.D. Pennsylvania, 1975)
San Francisco Ecology Center v. City & County of San Francisco
48 Cal. App. 3d 584 (California Court of Appeal, 1975)
Sierra Club v. Froehlke
392 F. Supp. 130 (E.D. Missouri, 1975)
Save the Courthouse Committee v. Lynn
408 F. Supp. 1323 (S.D. New York, 1975)
Citizens Against the Destruction of Napa v. Lynn
391 F. Supp. 1188 (N.D. California, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
378 F. Supp. 240, 6 ERC 1737, Counsel Stack Legal Research, https://law.counselstack.com/opinion/warm-springs-dam-task-force-v-gribble-cand-1974.