Walton Construction Co. v. MGM Masonry, Inc.

199 S.W.3d 799, 2006 Mo. App. LEXIS 971, 2006 WL 1737939
CourtMissouri Court of Appeals
DecidedJune 27, 2006
DocketWD 63735, WD 63771
StatusPublished
Cited by11 cases

This text of 199 S.W.3d 799 (Walton Construction Co. v. MGM Masonry, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walton Construction Co. v. MGM Masonry, Inc., 199 S.W.3d 799, 2006 Mo. App. LEXIS 971, 2006 WL 1737939 (Mo. Ct. App. 2006).

Opinion

JAMES M. SMART, JR., Judge.

This case involves cross-appeals arising out of a jury verdict and award of damages in favor of MGM Masonry, Inc. against Walton Construction Inc. Each party had sued the other for breach of a construction contract. Walton contends, inter alia, that it was reversible error for the court to refuse to poll the jury after verdicts on the parties’ respective claims, and that it was prejudiced thereby because the verdicts were inconsistent. MGM, which received a purported verdict from the jury, appeals the trial court’s denial of its post-trial motion for attorneys’ fees and interest.

In November 2005, we reversed and remanded for a new trial. After opinion, we granted rehearing.

Background

In July 1999, Walton was hired as the general contractor for construction of a large store in Kansas City. The project was to be constructed primarily of concrete masonry blocks. Walton subcontracted with MGM to perform the masonry work on the project. The original contract price for MGM’s work was $1,257,800, to be paid in periodic installments. MGM began work on the project on August 2, 1999. The contract included various “completion dates” for different aspects of the work MGM was to perform. According to Walton, MGM failed to satisfactorily meet the contract completion dates. Beginning in October, Walton began claiming that MGM was failing to perform under the contract, and began withholding amounts due MGM under the contract. Ultimately, Walton withheld the sum of $242,384.

Walton filed a breach of contract lawsuit against MGM. The petition alleged that MGM’s failure to perform according to the contract caused Walton to incur costs and expenses. Walton also alleged that MGM failed to protect and indemnify it from Hens or claims from its suppliers, as required by the contract. Walton sought indemnification for over $90,000 in unpaid invoices from the material supplier. Walton also sought reimbursement for costs, expenses, and attorneys’ fees, pursuant to the contract.

MGM brought a counterclaim against Walton, alleging that Walton had first breached the contract by failing to properly manage the project and by failing to make timely payments due it under the contract. MGM sought damages in excess *802 of $350,000, consisting of the unpaid contract balance plus additional damages MGM claimed as a result of Walton’s other breaches.

Proceedings at Trial

The case proceeded to trial before a jury in September 2003. Walton’s position at trial was that MGM had breached the contract by failing to timely perform its work under the contract. Walton presented evidence that this failure caused it to incur additional costs and expenses in order to finish the project on time. Walton also presented evidence that it had satisfied $70,000 in supplier invoices and sought reimbursement from MGM for that.

MGM sought to prove at trial that Walton had breached the contract by withholding $242,384 in payments due under the contract and by mismanaging the project, which caused $92,898 in additional damages to MGM.

MGM presented evidence that Walton mismanaged the project by, inter alia, failing to properly coordinate the work at the construction site, allowing conflicts and interference with MGM’s work, and inconsistently redirecting MGM’s work. MGM claimed that Walton did not have sufficient footings available at the start of the project for MGM to install the material. MGM asserted that its delay in getting the colored blocks delivered was due in part to Walton’s failure to provide MGM timely written confirmation of the contract, and in part to the contract’s requirement that MGM use Midwest Block & Brick as the supplier. MGM presented evidence of other failures by Walton, which need not be detailed here.

At the instruction conference, the parties proposed one set of instructions for Walton’s claim against MGM and a separate set of instructions for MGM’s counterclaim against Walton. The jury was given two separate verdict forms: Verdict A on Walton’s claim against MGM, and Verdict B on MGM’s counterclaim. Instruction 5 informed the jury: “Nine or more of you must agree in order to return any verdict. A verdict must be signed by each juror who agrees to it.” (Emphasis added.)

The claims were submitted to the jury with the following pertinent instructions. On Walton’s claim, the verdict director (which directed resolution on Verdict A) directed the jury:

Your verdict must be for plaintiff Walton Construction Company, Inc. [] if you believe:
First, Walton and defendant MGM Masonry, Inc. [ ] entered into an agreement whereby Walton and MGM agreed to perform their respective duties and obligations as described in subcontract documents for the Home Depot project, and
Second, Walton performed its agreement, and
Third, MGM failed to perform its agreement, and
Fourth, Walton was thereby damaged.

On MGM’s counterclaim, the verdict director (which directed resolution on Verdict B) instructed the jury:

Your verdict must be for defendant MGM Masonry, Inc. [] if you believe:
First, MGM and plaintiff Walton Construction Company, Inc. [ ] entered into an agreement whereby MGM and Walton agreed to perform their respective duties and obligations as described in the subcontract documents for the Home Depot project, and
Second, MGM substantially performed its agreement, or was prevented from performing its agreement, and
Third, Walton failed to perform its agreement, and
*803 Fourth, MGM was thereby damaged.

The jury found in favor of MGM on Walton’s breach of contract claim (Verdict A). The jury also found in favor of MGM and against Walton on MGM’s counterclaim (Verdict B), and assessed damages at “$242,384, plus interest, plus $12,030.” Both verdict forms were signed by nine jurors. Juror Janner, the foreman, had signed verdict B in favor of MGM, but did not sign verdict A. Juror Shockley had signed verdict A, but not verdict B. The judge read the verdicts in open court within the hearing of the jury. He noted that verdict A was signed by nine jurors and stated that it appeared to be in proper form. He made the same statement with regard to verdict B.

Counsel for Walton requested that the jury be polled. The court refused, believing that the right to poll juries was applicable only in criminal cases. The judge then discharged the jury. After the jury was discharged, the judge, the attorneys, and the parties became aware that the two verdicts were not signed by the same nine jurors.

Walton moved for judgment notwithstanding the verdict or alternatively for new trial. The court denied the motion, concluding that the verdicts were not inconsistent, and that nothing would have been gained by polling the jury. MGM maintained the verdicts were not inconsistent and opposed the new trial motion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Advantage Buildings & Exteriors, Inc. v. Mid-Continent Casualty Co.
449 S.W.3d 16 (Missouri Court of Appeals, 2014)
Norfolk Southern Railway Co. v. Crown Power & Equipment Co.
385 S.W.3d 445 (Missouri Court of Appeals, 2012)
Westerman v. Shogren
392 S.W.3d 465 (Missouri Court of Appeals, 2012)
Weitz Co. v. MH WASHINGTON
631 F.3d 510 (Eighth Circuit, 2011)
Wiseman v. Armstrong
989 A.2d 1027 (Supreme Court of Connecticut, 2010)
Glenstone Block Co. v. Pebworth
264 S.W.3d 703 (Missouri Court of Appeals, 2008)
Anthony Petruccelli v. State
Court of Appeals of Texas, 2005

Cite This Page — Counsel Stack

Bluebook (online)
199 S.W.3d 799, 2006 Mo. App. LEXIS 971, 2006 WL 1737939, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walton-construction-co-v-mgm-masonry-inc-moctapp-2006.