Timber Ridge Escapes v. Quality Structures of Arkansas

6 F.4th 781
CourtCourt of Appeals for the Eighth Circuit
DecidedJuly 26, 2021
Docket20-2640
StatusPublished

This text of 6 F.4th 781 (Timber Ridge Escapes v. Quality Structures of Arkansas) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Timber Ridge Escapes v. Quality Structures of Arkansas, 6 F.4th 781 (8th Cir. 2021).

Opinion

United States Court of Appeals For the Eighth Circuit ___________________________

No. 20-2640 ___________________________

Timber Ridge Escapes, LLC

Plaintiff - Appellant

v.

Quality Structures of Arkansas, LLC

Defendant - Appellee

------------------------------

Plaintiff - Appellee

Welk Resort Group, Inc.

Defendant

Defendant - Appellant ___________________________

No. 20-2928 ___________________________ Timber Ridge Escapes, LLC

Defendant - Appellant ____________

Appeals from United States District Court for the Western District of Missouri - Springfield ____________

Submitted: June 16, 2021 Filed: July 26, 2021 ____________

Before LOKEN, KELLY, and ERICKSON, Circuit Judges. ____________

-2- ERICKSON, Circuit Judge.

This appeal arises out of a rancorous construction dispute between Timber Ridge Escapes, LLC (“Timber Ridge”) and Quality Structures of Arkansas, LLC (“Quality Structures”). After a nine-day bench trial, the district court awarded Timber Ridge $22,500 in damages and Quality Structures an amount in excess of $5 million in damages. Timber Ridge appeals.1 With one exception, we affirm.

I. BACKGROUND

Timber Ridge is a self-described owner/developer of a resort near Branson, Missouri. In July 2015, Timber Ridge entered into four virtually identical contracts with Quality Structures under the terms of which Quality Structures agreed to serve as the general contractor for the project (the “construction contracts”).2 Pursuant to the contract, Quality Structures agreed to construct two buildings (Buildings 8 and 9) and two building pads (Building Pads 10 and 11) for Timber Ridge. Over time the relationship between Timber Ridge and Quality Structures deteriorated, and on February 6, 2017, Timber Ridge terminated the contracts. After the termination, Timber Ridge seized some of Quality Structures’ property, including documentation for the project. Timber Ridge refused to return the property until the parties reached a partial settlement on June 1, 2017.

On June 12, 2017, Timber Ridge sued Quality Structures asserting claims sounding in both contract and tort. Timber Ridge sought over $2 million in damages on its claims for breach of contract, breach of the implied covenant of good faith and

1 Quality Structures initially filed a cross appeal, which it later moved to dismiss. We granted that motion. 2 The construction contracts each consist of a Standard Form Agreement, a Schedule of Values, and General Conditions.

-3- fair dealing, promissory estoppel, tortious interference with contractual relations, breach of contract to indemnify and defend as well as claims for a declaratory judgment and for injunctive relief. At its heart, Timber Ridge’s complaint alleges that Quality Structures caused undue delays and performed unsatisfactory work. Quality Structures filed an answer and counterclaim seeking over $6 million in damages for sums it claimed it was owed for the work it completed. The counterclaims sought to pierce the corporate veil and included claims for breach of contract, violation of the Missouri Prompt Pay Act, reformation, conversion, fraudulent inducement, quantum meruit, equitable entrustment, and promissory estoppel.

The lawsuit quickly descended into a quagmire of finger pointing, which was aptly described by the district court as involving the expenditure of “significant resources demonstrating every way that the other party breached the terms of the contracts and why they themselves are blameless.” This attitude on the part of parties made trial of the case exponentially more difficult.

Prior to trial, the court resolved such issues as it could on summary judgment. Following a bench trial, the court issued findings of fact and conclusions of law awarding Timber Ridge $22,500.00 for delays caused by Quality Structures, approximately $5.2 million in damages to Quality Structures, and $101,239.62 in attorney’s fees and $35,490.46 in costs to Quality Structures. Timber Ridge appeals, arguing the district court erred in awarding Quality Structures (1) damages for extra excavation work, (2) certain other damages, and (3) attorney’s fees.

II. DISCUSSION

A. Extra Excavation

The construction contracts originally contemplated excavation work at agreed upon prices: $75 per cubic yard for excavated rock and $6.85 per cubic yard for

-4- excavated dirt. About a month after the parties entered into the construction contracts, Timber Ridge sent Quality Structures written instructions that greatly expanded the scope of the excavation work. This expansion increased the amount of rock and dirt that Quality Structures had to excavate, especially the amount of rock that needed to be excavated.

Quality Structures performed the extra excavation work as instructed but before Quality Structures could request additional payment for the work, Timber Ridge terminated the contracts. When Quality Structures requested payment (about a month after the termination), Timber Ridge refused to pay. The district court concluded that Timber Ridge breached the construction contracts when it failed to pay for the additional excavation work. Timber Ridge contends Quality Structures (1) failed to substantially comply with “contractual predicates to payment,” and (2) did not put forth sufficient evidence to “prove damages from nonpayment.”

1. Substantial Compliance

We apply Missouri substantive law to this diversity action. See Erie R.R. Co. v. Tompkins, 304 U.S. 64, 78 (1938). To recover for a breach of contract under Missouri law, Quality Structures must establish that it substantially performed its obligations under the contracts. See Moore v. Armed Forces Bank, N.A., 534 S.W.3d 323, 327 (Mo. Ct. App. 2017) (listing the elements for breach of contract). A party substantially performs if the contract deviation is “very slight” and the opposing party has “received substantially the same benefit it would have from literal performance.” Pepsi MidAm. v. Harris, 232 S.W.3d 648, 653 (Mo. Ct. App. 2007).

While the parties apparently dispute whether federal law or Missouri law provides the standard of review for the district court’s substantial performance decision, they agree that the appropriate standard of review is for clear error. Because

-5- the standard of review under both Missouri law and federal law is for clear error we need not resolve the dispute over which law applies.

We will only reverse a finding under the clearly erroneous standard if it “is not supported by substantial evidence in the record, if it is based on an erroneous view of the law, or if we are left with the definite and firm conviction that an error was made.” Federated Mut. Ins. Co. v. Moody Station & Grocery, 821 F.3d 973, 977 (8th Cir. 2016) (citations omitted); Flooring Sys., Inc. v. Saat Constr. Co., 100 S.W.3d 835, 837 (Mo. Ct. App. 2003) (same). The evidence in the record makes clear that the scope of the work was both dramatically expanded and that Quality Structures performed the expanded scope of the work. The district court did not clearly err in finding substantial performance under the contracts related to the excavation work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Weitz Co. v. MH WASHINGTON
631 F.3d 510 (Eighth Circuit, 2011)
Vigoro Industries, Inc. v. Crisp
82 F.3d 785 (Eighth Circuit, 1996)
Flooring Systems, Inc. v. Staat Construction Co.
100 S.W.3d 835 (Missouri Court of Appeals, 2003)
Pepsi Midamerica v. Harris
232 S.W.3d 648 (Missouri Court of Appeals, 2007)
Denton Construction Co. v. Missouri State Highway Commission
454 S.W.2d 44 (Supreme Court of Missouri, 1970)
Williams v. Williams
99 S.W.3d 552 (Missouri Court of Appeals, 2003)
Comens v. SSM St. Charles Clinic Medical Group, Inc.
335 S.W.3d 76 (Missouri Court of Appeals, 2011)
Walton Construction Co. v. MGM Masonry, Inc.
199 S.W.3d 799 (Missouri Court of Appeals, 2006)
Knowlton v. Anheuser-Busch Companies Pension Plan
849 F.3d 422 (Eighth Circuit, 2017)
Moore v. Armed Forces Bank, N.A.
534 S.W.3d 323 (Missouri Court of Appeals, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
6 F.4th 781, Counsel Stack Legal Research, https://law.counselstack.com/opinion/timber-ridge-escapes-v-quality-structures-of-arkansas-ca8-2021.