Walsh v. East Butte Copper Mining Co.

214 P. 641, 66 Mont. 592, 1923 Mont. LEXIS 66
CourtMontana Supreme Court
DecidedMarch 29, 1923
DocketNo. 5,081
StatusPublished
Cited by10 cases

This text of 214 P. 641 (Walsh v. East Butte Copper Mining Co.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walsh v. East Butte Copper Mining Co., 214 P. 641, 66 Mont. 592, 1923 Mont. LEXIS 66 (Mo. 1923).

Opinions

MR. CHIEF COMMISSIONER LAW

prepared the opinion for the court.

The plaintiff in this cause seeks to recover damages from the defendant company on account of certain alleged negligent acts which resulted in flooding and depositing on the property of the plaintiff tailings, filth and debris. The district court, at the close of the evidence on behalf of the plaintiff, dismissed the case as to the defendant Beaudin. This ruling of the court has not been challenged, and the case will be considered without reference to this defendant. At the close of all of the evidence in the case, upon- motion of the defendant company, the court directed the jury to return a verdict in its favor on the issues involved. The appeal to this court is from the judgment entered upon the verdict in favor of the defendant company.

During the years 1915 to 1920, inclusive, the defendant company owned and operated a mining, concentrating, and smelting plant located approximately one and one-half miles east of the Harrison Avenue bridge in the city of Butte and about one-half mile from Silver Bow Creek. From November, 1915, to and inclusive of the month of January, 1920, the company by means of ditches conveyed to and dumped into Silver Bow Creek its tailings and refuse from its mining, milling and smelting operations at a point approximately 1,800 feet east of the Harrison Avenue bridge. In January and February, 1920, a dam was constructed along the banks of Silver Bow Creek for the purpose of collecting the tailings and refuse then carried from the plant into the creek, and was used for such purpose until about the 20th of March following, at which time the dam was abandoned and the tailings collected at another place. The plaintiff owned certain property adjacent to the Harrison Avenue bridge, and in the years 1916 and 1917 constructed an apartment house thereon, and approaching within fifteen feet of Silver Bow Creek. On June 28, 1920, between 7 and 8 o’clock P. M., there occurred a heavy fall of rain in the vicinity of the [595]*595plant of the defendant company and within the watershed of Silver Bow Creek; a large volume of water came down the creek and from the property surrounding the tailings dam, a part of which flowed into the reservoir. The banks of the reservoir gave way, and as a result the contents of the dam, consisting of water, tailings, slimes, stable manure and other debris, were carried down the stream. The banks of the creek adjacent to the plaintiff’s property at the Harrison Avenue bridge were overflowed, and the plaintiff’s apartments on the lower floor were flooded, the basement filled with water, and about four feet of sediment, consisting of tailings and slime, were deposited therein. Portions of the broken dam and its contents, consisting of stable manure, gravel and tailings, were lodged upon plaintiff’s yards and surrounding properties.

All assignments of error worthy of discussion may be disposed of in two general propositions, namely: Was it necessary for plaintiff to prove more than one of the several alleged acts of negligence? Was the evidence introduced sufficient to require the submission of the ease to the jury upon any theory alleged?

As to the first proposition, we believe that the following general rule may be deduced from the discussion of the necessity of proving all of several acts of negligence charged in the complaint contained in the decisions in the cases of Forsell v. Pittsburgh, & Montana Copper Co., 38 Mont. 403, 100 Pac. 218, and Frederick v. Hale, 42 Mont. 153, 112 Pac. 70. When plaintiff in an action states several distinct acts of negligence, any one of which is, when proved, shown to be a proximate cause of the injury, his action will not be defeated by failure to prove all, and he may recover on proof of one or more of the acts of negligence complained of; but, where the injury upon which the suit for damages is based is alleged to be the result of several acts of negligence, no one of which however is charged to have caused it alone, proof of a single one of the acts will not suffice. [596]*596Tested, then, by the foregoing rule, can it be said that the plaintiff was entitled to recover on proof of any one of the acts complained of? One of the acts charged is that prior to the year 1918 the channel of the creek was sufficiently large to properly carry off all flood and surface waters, but that, by reason of the defendant dumping its tailings into the creek, the channel was filled and the bottom of the creek bed raised so that its capacity for carrying off surface waters became smaller. Another allegation is to the effect that the defendant in the year 1920 constructed so-called ponds or impounding dams for impounding tailings, water and filth from the properties of the defendant company near Silver Bow Creek; that the dam was carelessly and negligently constructed in certain parts, and that it was not sufficiently strong to withhold any average or heavy flow of water, and that the defendant was repeatedly advised of such negligent construction and dangerous condition of the dam or pond; and, finally, it is alleged that on June 28, 1920, many thousands of gallons of water and thousands of tons of filth and tailings were in said pond, and that on said day occurred a rainstorm which caused some water to flow into the pond, when the banks gave way, and the contents of the dam, composed of tailings, water and filth, were caused to flow upon and into the property of the plaintiff; that, by i’eason of the fact that the defendant company had theretofore caused the creek-bed of said Silver Bow Creek to be filled and raised with tailings from its properties, and, because of the breaking of said impounding dam, the waters and tailings from said pond were prevented from flowing through the creek, and were caused to flow upon plaintiff’s property in a large volume, causing the basement of his apartment house to be filled with water, tailings, filth and debris. It seems clear from the foregoing that neither the construction and maintenance of the dam nor the filling of the channel alone would have caused or contributed proximately to plaintiff’s damage on June 28. So far as we are advised in the complaint, the [597]*597channel of the creek in its then condition would have taken care of the waters on June 28, had the dam not broken and released its contents, and, likewise, if the channel had not been partially filled, it would have taken care of the contents of the pond on June 28 without damage to the plaintiff. Thus from the pleadings we may properly conclude that neither of the alleged acts of negligence, operating independently of the other, would have caused the damage to plaintiff’s property. It was therefore necessary for the plaintiff to prove as alleged the two acts of negligence on the part of defendant before he was entitled to recover.

Plaintiff relies upon Frederick v. Hale, supra, to sustain his contention that proof of any one of the alleged acts of negligence was sufficient to entitle him to recover. We cannot regard that case as an authority for any other than the general propositions of law hereinbefore stated. In Frederick v. Hale the court said: “The complaint in this action charges negligence with respect to the upper reservoir, but it also discloses beyond question that it was the breaking of the dam at the lower reservoir which caused plaintiff’s injury.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Richland County v. Anderson
291 P.2d 267 (Montana Supreme Court, 1955)
Bruton v. Carolina Power & Light Co.
217 N.C. 1 (Supreme Court of North Carolina, 1940)
Bruton v. . Light Co.
6 S.E.2d 822 (Supreme Court of North Carolina, 1940)
Brennan v. City of Kalispell
74 P.2d 6 (Montana Supreme Court, 1937)
Wibaux Realty Co. v. Northern Pacific Railway Co.
54 P.2d 1175 (Montana Supreme Court, 1935)
Heckaman v. Northern Pacific Railway Co.
20 P.2d 258 (Montana Supreme Court, 1933)
Southern Indiana Gas & Electric Co. v. Winstead
175 N.E. 281 (Indiana Court of Appeals, 1931)
Burns v. Eminger
276 P. 437 (Montana Supreme Court, 1929)
Watts v. Billings Bench Water Assn.
253 P. 260 (Montana Supreme Court, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
214 P. 641, 66 Mont. 592, 1923 Mont. LEXIS 66, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walsh-v-east-butte-copper-mining-co-mont-1923.