Wakefield v. Supple

160 P. 376, 82 Or. 595, 1916 Ore. LEXIS 135
CourtOregon Supreme Court
DecidedOctober 17, 1916
StatusPublished
Cited by10 cases

This text of 160 P. 376 (Wakefield v. Supple) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wakefield v. Supple, 160 P. 376, 82 Or. 595, 1916 Ore. LEXIS 135 (Or. 1916).

Opinion

Opinion by

Me. Chief Justice Mooee.

1, 2. In Smith Typewriter Co. v. McGeorge, 72 Or. 523 (143 Pac. 905), it was held that when the trial court, within the time allowed, discovers that such a mistake of law has been made at the hearing of a cause as would necessitate a reversal of the judgment if brought up for review, such final determination may be set aside and a new trial ordered. To the same effect, see, also, Rudolph v. Portland Ry., L. & P. Co., 72 Or. 560 (144 Pac. 93); Frederick & Nelson v. Bard, 74 Or. 457 (145 Pac. 669); McGinnis v. Studebaker, 75 Or. 519 (146 Pac. 825, 147 Pac. 525, L. R. A. 1916B, 868); Delovage v. Old Oregon Creamery Co., 76 Or. 430 (147 Pac. 392, 149 Pac. 317); Pullen v. Eugene, 77 Or. 320 (146 Pac. 822, 147 Pac. 768, 1191, 151 Pac. 474). Predicated upon this rule, the question to be considered is whether or not the evidence received in respect to the alleged oral modification of the original contract was sufficient to authorize a submission of the cause to the jury. The rule is settled that the terms of a written contract may be altered by a subsequent parol agreement of the parties: Pippy v. Winslow, 62 Or. 219 (125 Pac. 298); City Messenger Co. v. Postal Tel. Co., 74 Or. 433 (145 Pac. 657). The plaintiff’s testimony tends to support the averments of the complaint in respect to the delay occasioned by failing to deliver the material within the time expected, and also as to the extra amount of labor necessitated by reaming the punched holes in the plates. In a letter which he wrote to the defendant May 28, 1913, in referring to these matters, he says:

[603]*603“Of course, this long wait has caused me considerable expense, as I have had to keep men within call and keep a plant down there ready at all times to unload the material. I think I am entitled to some compensation for all this delay and should be pleased to hear from you in the matter, as I do not wish to be unreasonable or make any unreasonable demands. Further, when I took the work it was expected that the erection bolts would be furnished with the material. I have had to furnish these bolts and think it would be no more than right that you should pay for them, as I took the work at a very low figure. As there is considerable of the material on hand now, we have started to get it together and think we should have some understanding about the lost time that has passed before going any further.”

Plaintiff on June 11, 1913, again wrote the defendant as follows:

“I am assembling and riveting hulls for the two government dredges, the work having been undertaken, as per my contract of February 11, 1913. Not having specifications or plans showing details and descriptions of the work, I derived my information for the work required from Fred A. Ballin. At the time our contract was signed it was expected that the steel would arrive in a few days. The last four cars of this steel arrived yesterday, being about two months later than expected and the other cars having been strung along one at a time made it necessary to keep a force of men on hand in readiness to unload this material and adding additional expense to the cost of the work. It was expected that erection bolts would be furnished with this material and as I furnished these bolts I should be paid for the same. The plates that have to be calked were to have been beveled-sheared, which was not done. All connections were to have been riveted to the large members. Failure to do this has increased the number of rivets to be driven and the steel being in small pieces adds to the difficulty and cost of handling same. The wedges to be used [604]*604as stop waters at the butt of the lower sheets should have been punched at the shop, and this will have to be done before they are driven, as it would be too expensive to drill them after they are in place. As these changes will make the work cost more than the prices given in my contract, I suggest that you and Mr. Baffin meet me at the yard at your earliest convenience and reach some agreement to take care of this additional cost. I do not wish you to be dissatisfied nor do I wish to be out any money on account of this work. ’ ’

From a letter written by Wakefield to Supple July 12,1913, an excerpt is taken as follows:

“I have written to you repeatedly stating the difference between the job we are doing and the job we contracted to do. The contract expressly stated that the material is to be fabricated, which Í understand, means ready to put together, while the actual work we are doing is reaming the thing entirely all over, or, in other words, there has been no work done except merely punching and a very poor job at that. The material is badly marked so that it is very difficult to find the pieces that belong together and lots of the material that should be put together under the clause ‘Fabrication’ is shipped loose, little pieces of angle 2x2, 4 to 6 ft. in length. I have written you a great many times about these differences, but do not seem to get any direct results from them other than, ‘will make it all right in the end’ but there is so much to be made right that I think we ought to have an understanding now. I am perfectly willing to do as we agreed in our contract to leave our differences to the inspector for the government, Mr. Baxter. The clause in the contract referring to your having an agreement with the Great Lakes Engineering Company for the fabrication in which they are responsible for the proper execution of the same, their representative disclaims any responsibility for mistakes and says that the reaming is especially excluded from their contract.”

[605]*605Replying to this communication, the defendant on July 14, 1913, wrote the plaintiff a letter, from which extracts are taken, viz.:

“Dear Sir: Your favor of the 12th inst. duly noted. You state that you have written a number of letters regarding our contract for the building of the two government dredges, and that I have failed to answer them in writing. Permit me to state that as far as differences are concerned, there is no need to take up any generalities, inasmuch as the contract itself, states very definitely and positively what part of the work is to be done by yourself and me. * # You further agreed to settle with the representative of the Great Lakes Engineering Works, any discrepancies which may be discovered on the work and material, and make your own agreements for extra charges, and for their collection for the correction of any possible changes or mistakes discovered, due to faulty fabrication on the part of the Great Lakes Engineering Works. * # You further state, that I made you understand that I would ‘Make it all right in the end,’ implying that I acknowledged that there was something to make all right. I wish to dispel this impression emphatically, as so far nothing has appeared on which you could base any claims against me under our contract. I did say and meant to say, that where you could show that I owed you any money in the end, I would pay you, provided you could make the right kind of a showing. * * .1 understand from Capt. Haight, representing the G. L. E. W., that he is willing to correct any mistakes made in fabrication.”

The quotations from these letters partly express the dispute existing between the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beglau v. Albertus
536 P.2d 1251 (Oregon Supreme Court, 1975)
Lease v. Corvallis Sand & Gravel Co.
185 F.2d 570 (Ninth Circuit, 1950)
Krause v. Bell Potato Chip Co.
39 P.2d 363 (Oregon Supreme Court, 1934)
Ahlquist v. Alaska-Portland Packers' Ass'n
39 F.2d 348 (Ninth Circuit, 1930)
Duniway v. Hadley
178 P. 942 (Oregon Supreme Court, 1919)
Archambeau v. Edmunson
171 P. 186 (Oregon Supreme Court, 1918)
Webb v. Isensee
166 P. 544 (Oregon Supreme Court, 1917)
Speer v. Smith
163 P. 979 (Oregon Supreme Court, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
160 P. 376, 82 Or. 595, 1916 Ore. LEXIS 135, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wakefield-v-supple-or-1916.