Lease v. Corvallis Sand & Gravel Co.

185 F.2d 570, 1950 U.S. App. LEXIS 3335
CourtCourt of Appeals for the Ninth Circuit
DecidedNovember 28, 1950
Docket12435
StatusPublished
Cited by6 cases

This text of 185 F.2d 570 (Lease v. Corvallis Sand & Gravel Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lease v. Corvallis Sand & Gravel Co., 185 F.2d 570, 1950 U.S. App. LEXIS 3335 (9th Cir. 1950).

Opinion

POPE, Circuit Judge.

In May, 1947, the appellants Lease and Leighland, entered into a contract with the Oregon State Board of Higher Education, for the construction by them of a women’s dormitory at the Oregon State College at Corvallis, all in accordance with the plans and specifications and other contract documents referred to in the agreement. Lease and Leighland then entered into a subcontract with the appellee John H. Gallagher, Inc. whereby the latter agreed to furnish the ready mixed concrete required by the specifications. The latter agreed to deliver the concrete at the job for a unit price of $9.50 per cubic yard. (A provision for increasing or decreasing the price should bulk cement prices increase or decrease pending the performance of the contract, is not material here.)

John H. Gallagher, Jr. was managing officer of both appellees, John IT. Gallagher, Inc. and Corval-lis Sand and Gravel Company, Oregon corporations. The appellants, Lease and Leighland, are citizens of the State of Washington.

The sub-contractor appears to have proceeded under its contract sometimes in the name of John H. Gallagher, Inc., and sometimes in the name of Corvallis Sand and Gravel Co. E'or the purpose of this opinion the two appellee corporations will be considered as a single entity as they appear to have been regarded by all of the parties through the period here involved.

The action below was one brought by the appellees, for convenience here called Sand and Gravel Company, against appellants and the sureties on their construction contract, to recover an amount alleged to be due them in excess of the amount stipulated in the contract. Appellees asserted that during the progress of the contract they were required by Lease and Leighland to furnish quantities of cement in excess of that called for by the contract. They sought to recover the reasonable value of the excess cement so furnished. Appellees recovered a judgment substantially as prayed for.

Appellants assert that the trial judge, before whom the case was tried without a jury, was in error in finding that the Sand and Gravel Company had been called upon to furnish cement in excess of the quantities required by the contract. They also say that in any event the court’s calculation of the amount and value of the cement alleged to constitute an extra was erroneous and unwarranted by the evidence.

The specifications did not list the proportions of the materials such as sand, gravel, water and cement required to make the concrete, but specified that the concrete should be such as would be found on application of standard tests to be sufficient to withstand certain designated pressures. The relevant specifications provided:

“804- la. All cast in place concrete shall have a minimum ultimate 28 day compressive strength of 2500 pounds per square inch. * * *
“804-2fo. Proportions of the materials and water content for the concrete strengths shall be established by tests which shall be made in advance of the beginning o f operations, using the consistencies suitable for the work and in accordance with the Standard Method of Making Compression Tests of Concrete, ASTM Serial Designation C39-44. At least four test specimens shall be made for each strength of concrete and should show an ultimate strength of at least 15 per cent greater than the strength specified. No substitution shall be made in the materials used on the work without additional tests in accordance herewith to show that the quality of the concrete is satisfactory.
“8Q4-2c. All concrete tests shall be made by an established testing laboratory approved by the Architect. The Contractor shall include the cost of the tests in the contract sum.
“804-2d. During the progress of the work compression tests shall be made in accordance with the Standard Method of *572 Making and Storing Compression Test Specimens of Concrete in the Field, ASTM Serial Designation C31-44. Each test shall be made on one laboratory control cylinder and one field control cylinder. There shall be at least one test for each strength of concrete placed on any one day and at least one test for each 250 cubic yards of concrete or fraction thereof on the job.
“804-2e. The standard age of tests shall be 28 days, but 7 day tests may be used provided that the relation between the 7 and 28 day strengths of the concrete is established by test for the materials and proportions used.
“804-2'f. In all cases where the average strength of the laboratory control cylinders shown by these tests for any portion of the structure falls below the minimum ultimate compressive strengths called for on the plans, the Architect shall have the right to order a change in the mix or in the water content for the remaining portion of the structure. In cases where the average strength of the cylinders cured on the job falls below the required strength, the Architect shall have the right to require conditions of temperature and moisture necessary to secure the required strength and may require load tests to be made on the portions of the- building so affected.”

It will be noted that the important section of these specifications is 8CH-2b, for it prescribes how the required concrete strengths are to be established. Hence, it is necessary to understand the meaning of the term “Standard Method otf Making Compression Tests of Concrete”, used in that paragraph, but not there defined except by reference.

The evidence shows that such tests are made upon test specimens of concrete cast in cylinders six .inches in diameter, 12 inches high, and allowed to “cure” or “set” for 28 days, when concrete is deemed to reach maximum strength. They are then broken through application of pressure, and the pounds of pressure per square inch required to break the cylinder constitutes the measure of its strength. This is stated in terras of pounds per square inch, abbreviated, p.s.i.

The tests may also be made after 7 days, and from the result then obtained the probable result at 28 days can be estimated, once a conversion factor has been ascertained by experiment. Thus, if a conversion factor of 1.5 is determined, it signifies that it has been ascertained that the particular concrete will probably attain at 28 days 1.5 times its strength at 7 days.

Tests are “field tests” or “laboratory tests”. When cast and hardened in the laboratory, the cylinders are kept at constant and ideal temperatures and moistures, and hence such test specimens are apt to disclose greater strength than field cast specimens of the same “mix”. This is the reason for the requirement, stated in section 804-2b, that such tests disclose strengths 15 per cent greater than the strengths specified. It is to assure a margin of safety for the concrete poured in place.

Although the proportions of the materials for the concrete strength were to be established “by tests which shall be made in advance of the beginning of operations”, as provided in § 804-2b quoted above, it was determined, apparently with the consent of all parties, and certainly without objection from any of them, that the pouring of the concrete should start about July 1, 1947, and at a date before such advance tests had been made.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
185 F.2d 570, 1950 U.S. App. LEXIS 3335, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lease-v-corvallis-sand-gravel-co-ca9-1950.