Wagner v. Frazier

712 S.W.2d 109, 1986 Tenn. App. LEXIS 2762
CourtCourt of Appeals of Tennessee
DecidedFebruary 11, 1986
StatusPublished
Cited by15 cases

This text of 712 S.W.2d 109 (Wagner v. Frazier) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wagner v. Frazier, 712 S.W.2d 109, 1986 Tenn. App. LEXIS 2762 (Tenn. Ct. App. 1986).

Opinion

OPINION

CANTRELL, Judge.

This is a dispute between an owner-developer and the general contractor and his surety. The contractor asserts on appeal that the evidence preponderates against the judgment of the Chancellor. The surety asserts, in addition to several suretyship defenses, that because the plaintiff died during the pendency of the suit and the case was not revived within ninety days of the suggestion of death the Chancellor should have dismissed the action.

In 1975 Clara Brainard owned a farm in Montgomery County near the City of Clarksville. Part of the farm lay along the bank of the Cumberland River. In 1977 she decided to construct a marina at the river’s edge and sought a loan guarantee from the Small Business Administration. With the help of the Small Business Administration guarantee, she obtained the loan from the United American Bank in Memphis. At the same time Mrs. Brainard was also developing a subdivision on another part of the property and she hired Mr. Walter G. Frazier to do some of the grading on that project. While thus engaged, Mr. Frazier became interested in doing the work on the marina and he helped Mrs. Brainard to get the loan documents together. His estimate of the cost of the project was used in the loan application. Mr. Frazier actually did some of the preliminary grading on the marina site before the loan was approved by the United American Bank. For this work Mrs. Brainard paid Mr. Frazier on an hourly basis.

On May 23, 1978, Mr. Frazier and Mrs. Brainard signed an agreement whereby Mr. Frazier agreed to construct the marina according to the plans and specifications for a price of $249,762.00. The price included $31,132.00 for work that Mr. Frazier had previously done and for which he had been paid by Mrs. Brainard. Mr. Frazier furnished Mrs. Brainard a performance bond and a labor and materials payment bond with the United States Fidelity and Guaranty Company as surety. The bonds were procured through the Reed Insurance Agency in Ashland City, Tennessee.

After the execution of the contract, Mr. Frazier continued the excavation work and made good progress until July of 1978 when he struck rock and a heavy rain flooded the site. The record is in conflict *112 about whether Mr. Frazier ever returned to the job site in an effort to complete the job. It is undisputed that he and Mrs. Brainard agreed to secure the help of another excavating contractor to be paid on an hourly rate from the construction loan.

In .January of 1979 Mrs. Brainard had some meetings with Mr. Frazier about getting the work finished. About that time she also decided to call on USF&G, the bonding company, and have it pick up the work for Mr. Frazier. When she called the bonding company Mrs. Brainard discovered that they did not have a record of the bond in Nashville. Apparently because of a call from USF & G to the agency in Ashland City, Mr. Reed and Mr. Denney from the agency visited Mrs. Brainard and told her that they had pocketed the premium, and that there was no performance bond. They persuaded her to call USF&G in Nashville and tell them that she had been mistaken, that the bond had been placed with another company. She proceeded to do so, as she testified, upon their promise to see that she did not lose anything from not having a bond.

Later, Mr. Denney and Mr. Reed returned the bond premium to Mrs. Brainard in three separate checks. Although the bond premium had been paid by Mr. Frazier, Mrs. Brainard deposited the checks in her account, because, she said, she thought the payments from Mr. Denney and Mr. Reed were in fulfilment of their promise to help pay the outstanding bills and to see that she did not suffer from losing the bond.

After some extended negotiations and an examination of all the relevant transactions, Mrs. Brainard and Mr. Frazier executed an agreement on February 23, 1979 whereby Mr. Frazier agreed to pay approximately $58,000.00 of the cost overruns on the excavation contract, to complete certain phases of the work as outlined by the engineering company and to pay other incurred expenses up to a total of $109,000.00 if they did not result from additions to the original contract.

On June 14, 1979, Mr. Frazier received a handwritten list from the engineering company containing five items that had to be completed. On June 28, 1979, he reported that these items had been finished. In an answer to his letter the engineering company replied that the original list had not been satisfactorily finished and that other work that was included in the original contract remained unfinished.

In the meantime, on June 13, 1979, Mrs. Brainard’s attorney sent a letter to the Reed agency with a copy to USF & G saying that Mrs. Brainard did not consider the bond cancelled and that she had accepted a return of the bond premium under a mistake of fact. The letter tendered a check for $4,500.00 to the agency for the bond premium and declared that Mr. Frazier was in default. Although the agency returned the check tendered by Mrs. Brai-nard, for some reason USF & G billed the agency and collected the premium on the bond.

Mrs. Brainard brought this action on March 4, 1980. After a hearing to determine the question of liability and another to determine her damages, Mrs. Brainard died on September 27, 1983, while a decision on the amount of damages was pending. One of the defendants filed a suggestion of death on October 7, 1983. When no action was taken to substitute the proper parties as plaintiffs within ninety days after the suggestion of death, the defendants filed a motion to dismiss under Rule 25.01 of the Tennessee Rules of Civil Procedure. In response to the motion to dismiss, the co-administratrixes of Mrs. Brainard’s estate filed two motions on January 16, 1984. The first motion sought to substitute the two administratrixes as plaintiffs, asserting that letters testamentary had been issued to them on October 24, 1983. The second motion sought an extension of time beyond the ninety days allowed in Rule 25.01 for filing a motion of substitution. The defendants opposed both motions on the ground that Rule 25.01 was mandatory and that, in any event, the movants had not shown any reason for the extension. The Chancellor overruled the motion to dismiss *113 and granted the motion for an extension of time for the substitution. The reasons given by the Chancellor were (1) the time lapse was not an unreasonable one, (2) the case had been heard in its entirety, and (3) as a matter within the court’s discretion only “dire” circumstances would compel dismissal.

The Rule 25 Issue

The rule governing substitution of parties upon a suggestion of death is Rule 25.01 of the Tennessee Rules of Civil Procedure. It reads as follows:

25.01 DEATH (1) If a party dies and the claim is not thereby extinguished, the court may order substitution of the proper parties. The motion for substitution may be made by any party or by the successors or representatives of the deceased party and, together with the notice of hearing, shall be served on the parties as provided in Rule 5 and upon persons not parties in the manner provided in Rule 4 for the service of process.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barbara Cunningham v. Fresenius Medical Care, Inc.
Court of Appeals of Tennessee, 2022
Deric J. Mead v. James Loyd Tucker
Court of Appeals of Tennessee, 2021
Walter Joshlin v. Hollis H. Halford, III, M.D.
Court of Appeals of Tennessee, 2019
Katherine C. Dubis v. Yolanda E. Loyd
540 S.W.3d 4 (Court of Appeals of Tennessee, 2016)
Brandon v. WILLIAMSON MEDICAL CENTER
343 S.W.3d 784 (Court of Appeals of Tennessee, 2010)
Sam McCormick v. Illinois Central Railroad Company
Court of Appeals of Tennessee, 2009
Kenyon v. Handal
122 S.W.3d 743 (Court of Appeals of Tennessee, 2003)
Hickman v. Tennessee Board of Paroles
78 S.W.3d 285 (Court of Appeals of Tennessee, 2001)
J.D. Hickman v. TN Board of Paroles
Court of Appeals of Tennessee, 2001
Joe/Lovie Ross v. Shelby Co. Healthcare
Court of Appeals of Tennessee, 2001
Darron Smith v. Ed Mullikin
Court of Appeals of Tennessee, 2000
Douglas v. Estate of Robertson
876 S.W.2d 95 (Tennessee Supreme Court, 1994)
Hayes v. Brookwood Hosp.
572 So. 2d 1251 (Supreme Court of Alabama, 1990)
Valley Fidelity Bank & Trust Co. v. Cain Partnership, Ltd.
738 S.W.2d 638 (Court of Appeals of Tennessee, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
712 S.W.2d 109, 1986 Tenn. App. LEXIS 2762, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wagner-v-frazier-tennctapp-1986.