Perkins Oil Co. v. Eberhart

64 S.W. 760, 107 Tenn. 409
CourtTennessee Supreme Court
DecidedJune 22, 1901
StatusPublished
Cited by26 cases

This text of 64 S.W. 760 (Perkins Oil Co. v. Eberhart) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Perkins Oil Co. v. Eberhart, 64 S.W. 760, 107 Tenn. 409 (Tenn. 1901).

Opinion

McAlister, J.

The defendant (Eberhart), as the result of competitive bidding, was awarded a contract for the construction of an oil mill, in the city of Memphis, for the Perkins Oil Co. The contract price for the work was $26,000. Eberhart, the contractor, executed a bond with the American Bonding & Trust Co., as surety, in the penalty of $7,000, for the faithful performance of the work. Toward the close of the work complications arose. Mechanics, laborers, and material men filed notices of liens upon complainants’ property, and it was threatened with vexatious litigation and serious loss. Thereupon the present bill was filed by the Perkins [412]*412Oil Co. against Eberhart, the contractor, the American Bonding & Trust Co., his surety, and certain subcontractors and material men, to restrain them from prosecuting separate suits, and to give the Chancery Court jurisdiction of all matters involved. Answers and cross bills were filed by the subcontractors and material men, attaching the realty on which the mill was situated, and asking that their several statutory liens thereon be established. During the progress of the cause the claims of these subcontractors and material men were all paid, and are not now the subject of controversy. The defendant (Eberhart) also filed an answer and cross bill, claiming a balance due from the Perkins Oil Co.,* of 121,282.76. An attachment issued, and was levied on the property of the oil company. The bond company filed its answer, alleging that a number of changes in the plans and specifications were made during the progress of the building, and that the mill and seed house were erected, not upon the contract plans and specifications, as originally made, but upon entirely different plans and specifications, made and furnished long after the original contract was entered into; that it was bound only by the contract as entered into, and that as soon as the original contract was changed, and additional plans and specifications were furnished, additional obligations were imposed upon Eberhart, and that the bond company was relieved and discharged from any and all liability under its bond. It denied that it [413]*413was bound on its contract to any. extent. It alleged that there was a large outlay of labor and a great amount of extra lumber and material, which had been ordered and prepared for the changes made, which increased the liability of Eberhart to a material extent, and that the bond company was thereby relieved from any obligations whatever under the original contract.

The Perkins Oil Co. answered the cross bill of Eberhart, in which it denied that it was indebted to him in any amount. There was a reference to the Master to state an account between the 'parties, who, upon the proof, found the sum of $7,117 to be due Eberhart. Exceptions to the report were filed by both- sides, which were overruled by the Chancellor and the report confirmed, excepting an item of $500, which the Master reported in favor of Eberhart, but which the Chancellor disallowed, thus reducing the claim of Eberhart to $6,605.36. During the progress of the cause decrees for the sum of $9,795.91 were rendered against the property of the Perkins Oil Co., in favor of the various subcontractors and material men, which sum was fully paid off by the oil company. On final hearing, the Chancellor pronounced a judgment in favor of the Perkins Oil Co., and against Eberhart, for $3,190.55, the difference between $9,795.91, the sum which the oil company was required to pay to the several subcontractors and material men, to satisfy their liens upon the lands and buildings of the oil company, [414]*414and $6,605*36, the sum found to be due Eber-hart, including all extras. The decree of $3,190.55 was rendered both against Eberhart and' the American Bonding & Trust Co., surety on the bond as contractor. Eberhart and the trust company both appealed and have assigned errors.

On behalf of Eberhart the first assignment of error is that the Chancellor erred in his construction of article 1 of the contract between Eberhart and the oil company, which is in the words and figures following, viz.: “Article 1. The contractor, under the direction and to the satisfaction of A. H. D. .Perkins, or his supervisor, acting for the purposes of this contract as agents of the said owner, shall and will provide all the materials and perform all the work mentioned in the specifications and shown on the drawings, prepared by the said owner for an oil mill, according to plans and specifications, and foundations for presses, accumulators, and engine, to the amount of one hundred and twenty thousand brick (120,000), all in addition to that quantity to be $14 per thousand in Portland cement, $11.50 per thousand in Louisville cement. All fire doors single, which drawings and specifications are identified by the signatures of the parties hereto. ’ ’

It is said the learned Chancellor, in regard to this clause, held, in effect, that Eberhart was to be paid extra only for brick above the amount of 120,000, used in the foundations for presses, accu[415]*415mulators, and engine, which said foundations for presses, accumulators, and engine did' not require more than 120,000 brick, when, as a matter of law, the learned Chancellor should have so construed said contract as to allow Eberhart compensation for all brick furnished in the building of the entire oil mill above the amount of the 120,000 brick. The entire amount .of brick furnished by Eberhart above said 120,000 brick, in the construction of the entire oil mill, is shown to be 1,120,000, the whole amount used being 1,240,000. The total sum thus claimed to be due Eberhart for brick furnished over and above 120,000, amounts to $12,880.

It is insisted by counsel for appellant that the interpretation of the contract is a matter of law, for the Court, and we cannot look beyond its four corners for light. It is a cardinal rule of construction that all instruments are to be expounded and to have effect given them according to the manifest intention of the parties, as apparent from the whole instrument or agreement, if not incompatible with established principles of law or policy. Polk v. Buchanan, 5 Sneed, 726. Again, it was said by the Court in Barker v. Freeland, 91 Tenn., 116: “It is an indisputable proposition that, when a contract is in writing and its meaning is plain and unambiguous, its interpretation is a matter of law, for the Court. But, when the writing is not plain and unambiguous, parol evidence is admissible to' ascertain the situation and surrounding circumstances, [416]*416the nature and quality of the subject-matter,” etc. The sole object of the rules and principles laid down for the exposition of contracts is to do justice to the parties by enforcing a performance of their agreement according to the sense in which they mutually understood it at the time. Mills v. Farris, 12 Heis., 457. In ascertaining the intention, the situation of the parties, the motives that led to the agreement, and the objects designed to be effected by it, may all be looked to by the Court. Nunnelly v. Warner Iron Co., 94 Tenn., 282. It is also true, as contended by appellant’s counsel, that, in cases of doubt, the instrument will be construed most strongly against the person who actually drew up the paper, or in whose behalf it was drawn.

With these fundamental principles in view, we now proceed to examine the contract. The building for the construction of which the contract was awarded to Eberhart was to be used by the Perkins Oil Co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wagner v. Frazier
712 S.W.2d 109 (Court of Appeals of Tennessee, 1986)
Estate of Jessee v. White
633 S.W.2d 767 (Court of Appeals of Tennessee, 1982)
Ernst v. Conditt
390 S.W.2d 703 (Court of Appeals of Tennessee, 1964)
Patterson v. Anderson Motor Co.
319 S.W.2d 492 (Court of Appeals of Tennessee, 1958)
Scott v. McReynolds
255 S.W.2d 401 (Court of Appeals of Tennessee, 1952)
E. O. Bailey & Co. v. Union Planters Title Guaranty Co.
232 S.W.2d 309 (Court of Appeals of Tennessee, 1949)
Commerce Street Co. v. Goodyear Tire & Rubber Co.
215 S.W.2d 4 (Court of Appeals of Tennessee, 1948)
Earle v. Illinois Cent. R. Co.
167 S.W.2d 15 (Court of Appeals of Tennessee, 1942)
Queenan v. Mays
90 F.2d 525 (Tenth Circuit, 1937)
Gibson County v. Fourth & First Nat. Bank
96 S.W.2d 184 (Court of Appeals of Tennessee, 1936)
Kyle v. Kyle
74 S.W.2d 1065 (Court of Appeals of Tennessee, 1934)
Neubert v. Messer
15 Tenn. App. 210 (Court of Appeals of Tennessee, 1932)
Hibernia Bank & Trust Co. v. Boyd
48 S.W.2d 1084 (Tennessee Supreme Court, 1932)
Standard Oil Co. v. Petroleum Products Storage Co.
44 S.W.2d 317 (Tennessee Supreme Court, 1931)
Alexander v. Grenada Bank
2 Tenn. App. 580 (Court of Appeals of Tennessee, 1926)
Clark v. Duncanson
192 P. 806 (Supreme Court of Oklahoma, 1920)
Yowell v. Union Central Life Ins.
141 Tenn. 70 (Tennessee Supreme Court, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
64 S.W. 760, 107 Tenn. 409, Counsel Stack Legal Research, https://law.counselstack.com/opinion/perkins-oil-co-v-eberhart-tenn-1901.