Southern Construction Co. v. Southern Surety Co.

10 Tenn. App. 506, 1926 Tenn. App. LEXIS 1
CourtCourt of Appeals of Tennessee
DecidedAugust 7, 1926
StatusPublished
Cited by3 cases

This text of 10 Tenn. App. 506 (Southern Construction Co. v. Southern Surety Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Construction Co. v. Southern Surety Co., 10 Tenn. App. 506, 1926 Tenn. App. LEXIS 1 (Tenn. Ct. App. 1926).

Opinion

SNODGRASS, J.

This bill was filed by the complainants to recover the sum of $2139, alleged to be an unearned premium on a *507 policy of contract insurance, and to enjoin tlxe defendant from instituting any suit against the complainant in Davidson county or elsewhere, but requiring it to come into this cause and set up any rights and claims which it may have against complainant, and that the defendant, its agents, attorneys and servants be enjoined from filing its alleged claim against the complainant with the department of highways of the State of Tennessee, and from in any other manner interfering with, impeding or delaying the settlement of the department of highways with complainant on account of the construction of Federal Aid Project No. 12.

An injunction was issued and served.

The answer was filed as a cross-bill. It was admitted that on October 20, 1919 complainant entered into a contract with the department of highways of the State of Tennessee for the construction of a certain highway located in Union and Claiborne counties and known as Federal Aid Project No. 12; that the estimated cost of this construction work was $258,670.27, and that on the same date complainant entered into a similar contract with the department of highways of the State of Tennessee for the construction of a concrete bridge on said Federal Aid Project No. 12, the estimated cost of which work was the sum of $11,203.84.

It was further admitted that the complainant was required to execute bonds as averred in paragraph three of the original bill; that application was made to the defendant for such bonds, and that complainant had correctly quoted a portion of such application, the original of which it was promised would be filed, and it was filed. The part quoted is as follows:

“The amount of contract is-dollars and the undersigned hereby agrees to pay to the company as a premium or charge for the bond applied for the sum of - dollars, being at the rate of fifteen ($15) dollars per one thousand of contract amount, in advance of the first two years or fraction thereof, and the sum of- dollars annually in advance thereafter, until the undersigned shall serve upon the company at its general office in the City of Des Moines, Iowa, competent written evidence showing it has been fully discharged and released from any and all liability upon said bond, and all matters arising therefrom.”

And also this provision:

“It is agreed that, should the actual contract price when ascertained on final settlement exceed the amount of contract above stated, the undersigned agrees to pay the company, on demand, as additional premium, a' further sum calculated at the same rate per one thousand dollars on such excess contract amount as shown in condition 3 above, and further, as addi *508 tional premium on account of the maintenance or guarantee of the work or supplies, on demand, a further sum calculated at the same rate per one thousand dollars on such excess contract amount as shown in condition 3 above.”

It was admitted, as averred in the 4th paragraph of the bill, that the defendant for the stipulated price agreed to become the surety of the complainant upon these bonds, as required by Acts of 1889 and 1917, and accordingly, on November 3, 1919, it executed one bond to the State of Tennessee department of highways in the sum of $3600.96, which bond covered the concrete' structure on said highway, and that on the same day the defendant executed a like bond to the State of Tennessee in the sum of $65,467.57, the highway proper; that complainant paid to defendánt as premium in cash, on account of the execution of said bonds by the defendant as surety for this complainant, the sum of $4,048.10.

It was further admitted that the complainant entered upon the execution of said work as contracted, but it was averred that defendant was not able to say just what portion of said work was completed at the end of two years, and demanded strict proof thereof in case it became material.

We may remark in' passing that it had been averred in said paragraph of the bill that—

“Complainant entered upon the execution of the work contemplated in said contracts, and at the date of the expiration of the two years for which said original premium was paid the complainant had done approximately one hundred forty-four thousand five hundred and forty and 27/100 ($144,540.27) dollars of the estimate contract on the highway; and on said date the complainant had executed work under the smaller contract amounting to approximately three thousand one hundred and twenty-seven and 1/100 ($3,137.01) d.ollars.”

We think the proof substantially establishes this to be true. The answer further admitted:

“The bill averred that sometime prior to November 7, 1921, the department of highways became convinced that the highway being constructed by complainant, and being Federal Aid Project No. 12, should for satisfactory reasons be radically changed. The contract originally called'for crushed stone base and a water bound macadam top. The department of highways deemed it advisable to change the construction to a hand placed coarse stone base and an asphalt penetration top. As a consequence on the date mentioned, November 7, 1921, what is denominated as a supplemental agreement was entered into by the complainant with the depart *509 ment of highways, whereby the character of the said road being constructed was changed as indicated, and the estimated cost of construction was increased from $150,000 to $200,000, the exact amount will be shown in the proof.” That—
“The department of highways was either of opinion that no additional bond was required by the laws of Tennessee when this supplemental agreement wlas entered into, or upon the other hand, if as a matter of fact the laws did require an additional bond, the said department overlooked that fact and complainant was not advised that any additional bond was necessary. However that may be, the complainant was not at the time called upon by the department or required to execute any additional bond. About three months after said supplemental agreement was entered into, and on the 9th day of February, 1922, the complainant, being of the opinion that the department of highways might require an additional bond covering the additional cost represented by .said supplemental agreement, and being of opinion that the department might require the assent of the department surety to the change which had been made in the contract, wrote to the agent of the defendant submitting certain data and figures with reference to the estimated cost of this construction work, the amount of work that had been done up to November 1, 1921, and the amount of premium that had been paid for the bond, and this complainant then suggested that the defendant execute for the complainant a new bond covering the additional estimated cost of the work, and that the complainant be allowed a credit of $2139 on account of the premium which it had paid to the defendant, which had not been earned bv the defendant because of the cancellation of Work representing that amount of the premium under-the original contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wagner v. Frazier
712 S.W.2d 109 (Court of Appeals of Tennessee, 1986)
Smith v. Sloan
225 S.W.2d 539 (Tennessee Supreme Court, 1949)
Hartford Accident & Indemnity Co. v. White
115 S.W.2d 249 (Court of Appeals of Tennessee, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
10 Tenn. App. 506, 1926 Tenn. App. LEXIS 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-construction-co-v-southern-surety-co-tennctapp-1926.