Wagner & Brown v. E.W. Moran Drilling Co.

702 S.W.2d 760, 90 Oil & Gas Rep. 571, 1986 Tex. App. LEXIS 12011
CourtCourt of Appeals of Texas
DecidedJanuary 30, 1986
Docket2-84-246-CV
StatusPublished
Cited by11 cases

This text of 702 S.W.2d 760 (Wagner & Brown v. E.W. Moran Drilling Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wagner & Brown v. E.W. Moran Drilling Co., 702 S.W.2d 760, 90 Oil & Gas Rep. 571, 1986 Tex. App. LEXIS 12011 (Tex. Ct. App. 1986).

Opinion

OPINION

FENDER, Chief Justice.

This is an appeal from a judgment in a daywork drilling contract case in favor of E.W. Moran Drilling Company, Inc. appel-lee — plaintiff, hereafter “Moran”, against Wagner & Brown, Jack E. Brown and Cyril Wagner, Jr., appellants — defendants, hereafter “Wagner & Brown”. Moran sued upon a printed and typewritten daywork drilling contract providing for payment of $11,000.00 per day, alleging that the fixed term of the contract was for 550 days and that Wagner and Brown only paid for 430 days and were thus liable for 120 days payment, totalling $1,320,000. Wagner and Brown asserted numerous defenses including unilateral mistake as to the term provision of the contract and illegality and usury with respect to the interest charged in the contract. Immediately prior to the trial they sought leave to amend their pleadings to allege Moran’s failure to perform certain conditions precedent and upon denial of leave to amend, requested a continuance, which was denied. The judgment awarded Moran $1,111,000.00 with prejudgment and post-judgment interest of 18% and attorney’s fees of $107,975.00 with additional fees of $25,000.00 and $15,000.00 in the case of appeal to the Court of Appeals and the Supreme Court. The forfeitures and penalties sought on Wagner & Brown’s claim of usury were denied.

We affirm.

In considering the forty-three points of error presented we shall treat them as grouped for discussion in appellee’s brief. We deem it necessary to a full understanding of our disposition of these points that the record as to the negotiations and execution of the contract document, the document itself, and the parties performance under it, be summarized.

Moran has been in the oil and gas drilling business in Wichita Falls since 1950. Wagner & Brown are engaged in exploration, drilling and production of oil and gas with headquarters at Oklahoma City. During the time from August 1980 to August 1981 there was a great deal of drilling activity in Western Oklahoma so that the demand for drilling rigs was heavy and the only rigs available which were capable of drilling to depths of 24,000 feet were new rigs coming out of construction.

Wagner & Brown were desirous of drilling a well to a depth of 24,200 feet and wanted a rig capable of drilling to that depth and another thousand feet if needed. Moran was approached about the availability of such a rig in January of 1981. After negotiations between Jack D. Semon, operations manager of Wagner & Brown and E.W. Moran, Jr. and Eric Zepp, Moran’s contract manager, a written contract was prepared by E.W. Moran, Jr., utilizing a standard printed form captioned “International Association of Drilling Contractors Drilling Bid Proposal and Daywork Drilling Contact — U.S.,” and mailed to Semon who signed it on behalf of Wagner and Brown. The agreement was signed by Moran on February 27, 1981 and by Semon on March 12, 1981.

*763 The basic contractual provisions of the document upon which this dispute arises are found within the first six of its paragraphs and in addition, paragraph number 21. As edited those provisions and their material elements follow:

[[Image here]]

*764 [[Image here]]

21. SPECIAL PROVISIONS:

21.1 In that the full Initial term of this contract 1s for a period of eighteen (18) months (550 days), the standby rate without crew will apply for each day the rig is not on an operating status for the Operator. Should the Operator terminate this contract before the eighteen month term 1s fulfilled, the Operator shall be obligated to the Contractor to pay the daily standby rate without crew (paragraph 4.6) until this eighteen month term contract is concluded; however, the Operator will not be charged the standby rate without crew for periods of time that this Contract is assigned to a third party operator at the same rates as outlined in Paragraph 4.1 through. 4.7 of this Contract. Notwithstanding Paragraph 19 above, Operator will, not be liable to Contractor as guarantor of the performance of the assignee if written approval of the Contractor is given for the assignment of this Contract.

21.2 It is agreed by Wagner and Brown and E. W. MORAN DRILLING COMPANY, INC. that the actual number of days required to move and rig up E. W. MORAN DRILLING COMPANY, INC. Rig 30 from MORAN's Wichita Falls yard to Wagner and Brown's first location will be billed at the moving and mobilization rates as outlined in Paragraph 4.3 and 4.1 of the Contract plus actual costs of trucking and crane service 'as outlined in Paragraph 6.11 of Exhibit "A" of the Contract.

All subsequent moves to the first well will be billed in the same manner except that Wagner and Brown and E. W. MORAN DRILLING COMPANY, INC. agree that the maximum number of days required for subsequent moves and rig up will be negotiated.

*765 Upon receipt of the signed contract, Moran began to firm up orders for parts and machinery needed to construct the rig. The rig had not been completely fabricated in Moran’s yard by mid-November when Moran was told by Wagner & Brown to move the incomplete rig to the drilling site and to complete its construction there. Moran complied, moved onto the drilling site, completed construction of the rig and began drilling (spudded) on December 12, 1981. Continuous drilling took place for 430 days and had reached a depth of approximately 22,000 feet by February 15, 1983. Prior thereto, on January 24, 1983, Wagner & Brown wrote to Moran pointing out that there had been a decrease of activity in the oil and gas industry and since “the contract signed was at a competitive industry rate, there should be a reduction in the rate, to a competitive industry rate.” It was requested that Moran “reduce the contract day rate charged, on the referenced well, to a competitive industry rate; with said day rate charge to be effective and retroactive to September 15, 1982”. Moran replied by letter of January 26, 1983, stating that in order to meet the unprecedented demand for rigs, Moran had to finance the purchase of equipment at prevailing prices to construct the rig and that its costs were remaining constant although market day rates had declined sharply, and that any change in contract terms would result in its being in default under its loan agreement since it was based almost exclusively on its contracts for the use of the rigs.

Well operations were ordered to cease on February 15, 1983; by Wagner & Brown. Moran then rigged down, removed from the site and on March 11, 1983 forwarded its standby rate invoice for the balance of the month of February and again tendered its rig # 30 “for further operations pursuant to the contract made with your company.” The rig was not further utilized by Wagner & Brown. Moran continued to send monthly invoices for the period of 120 days subsequent to the cessation of drilling on February 15, 1983. The invoices were not paid and suit followed to collect the day rate of $11,000.00 for the 120 day period. That period of time represents the difference between the 430 days of drilling operations after spudding on December 12, 1981, and the 550 days provided for in the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Noram Drilling Co. v. E & Pco International, LLC
178 So. 3d 1061 (Louisiana Court of Appeal, 2015)
in Re Stephanie Rios
Court of Appeals of Texas, 2015
McDaniel v. Spectrum Healthcare Resources, Inc.
238 S.W.3d 788 (Court of Appeals of Texas, 2007)
Austin v. Shampine
948 S.W.2d 900 (Court of Appeals of Texas, 1997)
McCreight v. City of Cleburne
940 S.W.2d 285 (Court of Appeals of Texas, 1997)
Citizens & Southern Corp. v. Commissioner
91 T.C. No. 35 (U.S. Tax Court, 1988)
Hill v. Whiteside
749 S.W.2d 144 (Court of Appeals of Texas, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
702 S.W.2d 760, 90 Oil & Gas Rep. 571, 1986 Tex. App. LEXIS 12011, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wagner-brown-v-ew-moran-drilling-co-texapp-1986.