Noram Drilling Co. v. E & Pco International, LLC

178 So. 3d 1061, 2015 La. App. LEXIS 1906, 2015 WL 5714571
CourtLouisiana Court of Appeal
DecidedSeptember 30, 2015
DocketNo. 50,052-CA
StatusPublished
Cited by1 cases

This text of 178 So. 3d 1061 (Noram Drilling Co. v. E & Pco International, LLC) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Noram Drilling Co. v. E & Pco International, LLC, 178 So. 3d 1061, 2015 La. App. LEXIS 1906, 2015 WL 5714571 (La. Ct. App. 2015).

Opinion

MOORE, J.

JjThe operator, E & Pco International (“E & Pco”), appeals' a judgment finding that it breached its daywork' drilling contract with the contractor, NorAm Drilling Co., by failing to pay any amount due under the contract, and ordering E & Pco to pay $2.01 million plus contractual interest and reasonable attorney fees. • We affirm.

Factual Background

The key players in E & Pco were its president, C.E. Edwards, and its vice-president, Osman Kaldirim Jr., exploration geologists who had formerly worked for CDX Gas but left to form their own companies, including E & Pco, for the purpose of evaluating projects for CDX. Later, Osman Jr.’s father, Osman Kaldirim Sr., joined the company, and E & Pco’s lawyer, Bob Leidich, of Jones-Day in Houston, acquired an interest in it.

In late 2007, E & Pco bought two leases in coalbed methane fields in Louisiana, including a tract in Caldwell Parish (the I.P. No. 3). All E & Pco’s witnesses stressed that at the time, E & Pco had virtually no capital, but it badly wanted to secure an operator for the LP. No. 3 while the market was prime. Edwards and Osman Jr. were very impressed with the Super Single Rig, with a long horizontal reach,. being made by N or Am.

NorAm is a subsidiary of a Norwegian company, Global Rig. The key players in NorAm were its president, Bruce Seeley, its vice-president and chief operating officer, Herman Mclnnis, another partner, Steiner Bakke, and the CEO of Global Rig, Jan Skaara. In December 2007, NorAm had just finished building three Super Single Rigs. Mclnnis testified that this model of rig was ideally suited to the needs of coalbed methane drilling 12in Caldwell Parish and was not available from any other drilling contractor at the time.

' The record shows that Edwards (E <& Pco) and Bakke (NorAm) began exchanging emails in August 2007, with Bakke responding that it was his “responsibility to ensure that the rigs get a signed operating contract as soon as possible.”

The Addendum

On December 6, 2007, before any contract :was signed, Leidich emailed Edwards, Osman Jr. and Osman Sr., stating, “We will also , need an agreement with whomever [sic] is funding the deposit— how is this to be repaid?” He attached a document labeled “Addendum to ContRact Dated DecembeR _ 2007 By and Between E & Peo LLC and NorAm Drilling Company Dated DecembeR 4,2007.” At the time, no contract had yet been signed, and there is no evidence that .the Addendum was forwarded to anybody at NorAm, but it reads, in -pertinent part,, with emphasis added: ,

Notwithstanding anything to the contrary in this Contract, the Parties agree as follows: .
1. On or before November 20, 2007, E & P or its designee shall deposit One Million U.S. Dollars ($1,000,000) (“De- . posit”) to an account at_to serve as a [1064]*1064fund against which payment of invoices submitted to E & P by NorAm for services and materials, all of which will- be in proper.form, may be drawn on the due date thereof. * * *
2. In the event the Deposit is not timely made, NorAm shall immediately cause and direct that the ■ Deposit be refunded to E & P by wire transfer to an account designated by E & P.
3. In the event the deposit is not timely made, this Contract shall terminate and be of no further force or effect | nand neither Party shall have any liability or obligation to the■ other nor in connection herewith (“Termination”).
[[Image here]]

The Daywork Contract

The following day, December 7, .2007, E & Pco (through Edwards) and NorAm (through Seeley) executed a Drilling Bid Proposal and Daywork Contract (“the Daywork Contract”). A standard-form International Association of Drilling Contractors document, the Daywork Contract obligated NorAm to commence operations for drilling by December 15, 2007, “or a mutually agreed date by both parties,” for a period of one year, and specified the use of Rig No. 2. • It further obligated E & Pco to pay a day rate of $22,500 per day, a “moving rate” of 90% of the day rate, and to pay all invoices within 30 days of receipt. The contract contained the notation, “see special provisions,” and attached to it was a handwritten document labeled Exhibit A, § 7 (“the Escrow Clause”):

An escrow account to be established up to an equivalent $ amount to cover mob [mobilization] and demob [demobilization] & int plus 3 months of operation.

Both sides concede this was a part of the Daywork Contract. Osman Jr. testified that Bakke insisted on the Escrow Clause because NorAm knew E & Pco did not have any funds’ to begin with; Osman Jr. estimated the escrow would need to be $2.5 million. All witnesses agreed that E & Pco never paid a dime into escrow, and Mclnnis testified that NorAm never demanded that the Escrow Clause be satisfied.

Early Dealings and the . Email Agreement

Mclnnis testified that after the Daywork Contract was signed, he started asking Edwards and other E & Pco people when he could move RigLNo. 2 to the IP. No. 3 site, but they kept putting him off. Initially, they were preparing the pad and laying the road to the remote site; mostly, however, E & Pco was waiting on funding to start actual operations. Mclnnis testified that at all times, Rig No. 2 (or its exact replica,. Rig No. 3) was ready to mobilize, with its fully trained crew (at a payroll of $7,000.a day, $140,000 a month).

On January 16, 2008, Seeley emailed Edwards, advising that “NorAm cannot simply sit around and wait for your permit or money problems to be solved.” He offered to put Rig No. 2 on a standby rate of $15,500, effective January 21, for 14 days, and if the rig was not mobilized at the end of the 14 days, they would “sit down and discuss the entire situation.” On January 18, Edwards responded, reminding Seeley of the “circumstances surrounding the signing” of the Daywork Contract that it was “contingent upon a required Letter of Credit or Escrow Deposit in the amount of $l,000i000[,]” which was never met by the deadline; as a'result, E & Pco personnel “were surprised” by the email proposing to “meliorate losses occasioned by the delay[.]” He acknowledged NorAm’s' “unusual efforts to hold the rig for E & Pco’s project” and the “inconvenience and potential economic impact[,]” but said E & Pco intended “to do whát is right for all parties[.]”

[1065]*1065A month later, on February 18, Seeley emailed Edwards, stating “my understanding that we have agreed” that the Day-work Contract would cover Rig No. 3, and that “it will go on a standby rate of. $15,000 per day commencing Monday, February 11,2008, and continue thereafter on a daily Ubasis until such time as the Rig is ready to move to the first location under the contract[.]” On February 21, Edwards responded by email:

This e-mail response acknowledges E & Pco’s request to place NorAm # 3 rig on standby @ $15,000 per day. I have discussed this with Mac Mclnnis [No-rAm’s vice-president] and copied him by e-mail.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Estate of Gadash
2017 COA 54 (Colorado Court of Appeals, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
178 So. 3d 1061, 2015 La. App. LEXIS 1906, 2015 WL 5714571, Counsel Stack Legal Research, https://law.counselstack.com/opinion/noram-drilling-co-v-e-pco-international-llc-lactapp-2015.