Wadley Crushed Stone Company, LLC v. Positive Step, Inc.

34 F.4th 1251
CourtCourt of Appeals for the Eleventh Circuit
DecidedMay 24, 2022
Docket21-11002
StatusPublished
Cited by5 cases

This text of 34 F.4th 1251 (Wadley Crushed Stone Company, LLC v. Positive Step, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wadley Crushed Stone Company, LLC v. Positive Step, Inc., 34 F.4th 1251 (11th Cir. 2022).

Opinion

USCA11 Case: 21-11002 Date Filed: 05/24/2022 Page: 1 of 17

[PUBLISH] In the United States Court of Appeals For the Eleventh Circuit

____________________

No. 21-11002 ____________________

WADLEY CRUSHED STONE COMPANY, LLC, an Alabama Limited Liability Company, Plaintiff-Counter Defendant-Appellant, versus POSITIVE STEP, INC., a Georgia Corporation d.b.a. 1st Quality Equipment Company,

Defendant-Counter Claimant-Appellee,

1ST QUALITY EQUIPMENT COMPANY, INC., USCA11 Case: 21-11002 Date Filed: 05/24/2022 Page: 2 of 17

2 Opinion of the Court 21-11002

Defendant-Counter Claimant,

THOMAS W. CURLEY,

Defendant.

Appeal from the United States District Court for the Middle District of Alabama D.C. Docket No. 3:17-cv-00852-KFP ____________________

Before NEWSOM, TJOFLAT, and HULL, Circuit Judges. TJOFLAT, Circuit Judge: This is a case about whether Wadley Crushed Stone Com- pany, LLC, (“Wadley”) has filed its breach of contract claim against 1st Quality Equipment Company (“1st Quality”) within the appli- cable statute of limitations. And the applicable statute of limita- tions depends on whether the contract is for goods under the Uni- form Commercial Code (“UCC”) or for services under traditional contract law. Because we hold that the contract is for goods, and the applicable statute of limitations under the UCC has already run, we affirm the District Court’s ruling that Wadley’s claim was time- barred. We also affirm the District Court’s grant of summary USCA11 Case: 21-11002 Date Filed: 05/24/2022 Page: 3 of 17

21-11002 Opinion of the Court 3

judgment and denial of reconsideration as to 1st Quality’s counter- claim for unpaid invoices. I. To sum up this case, it’s all fun and games until the granite plant turns out to be inefficient. Wadley is an Alabama corporation in the granite processing business. In 2009, Wadley wanted to build a granite plant in Alabama that, among other specifications, would process 500 tons of granite per hour. 1st Quality is a Georgia cor- poration that represents manufacturers in the sale of equipment used in the granite industry. 1st Quality sells equipment, provides customer support in connection with equipment sales, and supplies parts for some equipment from its warehouse. Based on prior busi- ness dealings between the executives of both companies, Wadley reached out to 1st Quality as it began the process of planning to build the granite plant. 1st Quality worked with both Wadley and several third par- ties to figure out how big the equipment would have to be to sup- port the plant and sub-contracted with engineers, contractors, and other vendors to figure out how the plant would operate. In other words, 1st Quality was doing its due diligence to figure out what kind of equipment the new Wadley plant would need. After this investigation period, 1st Quality and Wadley entered into a con- tract worth $5,579,255, which allocated $4,140,255 for 27 line items of equipment, $1,384,000 for erection, installation, and electrical, and $55,000 for extra electrical. The parties expected that 1st Qual- ity would hire Gaston Construction Company to complete the line USCA11 Case: 21-11002 Date Filed: 05/24/2022 Page: 4 of 17

4 Opinion of the Court 21-11002

items for erection, installation, and electrical work for the plant (and 1st Quality would pay Gaston Construction Company accord- ingly). In February 2012, Wadley asked 1st Quality if Wadley could work directly with Gaston Construction Company on the erection, installation, and electrical work. 1 1st Quality agreed to that ar- rangement, and the parties signed a modified contract in May 2012, which subtracted out almost $1.5 million for the work Gaston Con- struction Company would do independently. 2 In the modified contract, worth $ 4,059,224.43, there were 27 line items. Twenty- five of the line items were for individual pieces of equipment, add- ing up to $3,887,274.43. The other two line items were for instal- lation, setup, and calibration of scales and for engineering, which combined, only added up to $171,950, less than five percent of the contract price. Both parties understood that the engineering line item would be done by a third party, whom 1st Quality would pay. Wadley received all the contracted-for equipment but did not pay the invoices for some of that equipment because Wadley was not satisfied with the functioning of the plant. On its own dime, 1st Quality visited the plant to try to figure out why the

1 Apparently, this is because 1st Quality was not a licensed contractor in Ala- bama. 2 Any further references to the “contract” refer to this modified contract, which omitted the erection, installation, and electrical work that would now be done by Gaston Construction Company. USCA11 Case: 21-11002 Date Filed: 05/24/2022 Page: 5 of 17

21-11002 Opinion of the Court 5

equipment it sold Wadley did not meet the 500 ton-per-hour re- quirement. 1st Quality understood that the plant was supposed to process 500 tons of granite per hour when it sold the equipment to Wadley. About five years after the plant was completed, Wadley sued 1st Quality in Alabama state court, arguing, among other things, that 1st Quality breached its contract with Wadley when the gran- ite plant did not meet the 500 ton-per-hour requirement. 3 1st Qual- ity removed that case to federal district court in the Middle District of Alabama. The procedural history of this case from there is con- voluted, and, frankly, irrelevant for our purposes until we get to Wadley’s Fourth Amended Complaint.4 In that complaint, Wadley alleged breach of contract as to the 500 ton-per-hour re- quirement and as to the loadout capacity and also alleged misrep- resentation by 1st Quality as to the specifications of the plant. 1st Quality moved to dismiss, arguing that both the breach of contract claims as well as the misrepresentation claim were barred by the applicable statute of limitations. Specifically, 1st Quality argued that the UCC’s four-year statute of limitations applied to the breach

3 Wadley also alleged breach of contract as to the loadout capacity of the plant and misrepresentation as to the design of the granite plant. Wadley wanted a plant that had a “rail ballast load out system that could load out 2,000 ton[s] of granite per hour.” 4 The short story is that the District Court afforded Wadley multiple opportu- nities to amend its complaint to allege facts establishing that it filed within the applicable statute of limitations. USCA11 Case: 21-11002 Date Filed: 05/24/2022 Page: 6 of 17

6 Opinion of the Court 21-11002

of contract claims because, 1st Quality said, the contract was for goods rather than services. And 1st Quality argued that a two-year statute of limitations applied to the misrepresentation claim. The District Court then dismissed the misrepresentation claim as barred by the two-year statute of limitations but allowed the breach-of-contract claims to proceed because Wadley had alleged enough facts to make it plausible that the contract was for services rather than goods, so that it was plausible the action was not time- barred. 5 1st Quality then answered the Fourth Amended Complaint and counterclaimed against Wadley for breach of contract (and un- just enrichment) for failing to pay 1st Quality for some of the equip- ment at the granite plant. In the midst of both discovery and trial preparation, 1st Quality then filed two summary judgment mo- tions, one for Wadley’s claims and one for its own counterclaims against Wadley. The District Court then granted both motions for summary judgment. As to Wadley’s breach of contract claims, the District Court determined that the contract was for goods under the UCC, so the applicable statute of limitations had passed before Wadley filed suit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

water.io Ltd v. Sealed Air Corp.
2025 NCBC 5 (North Carolina Business Court, 2025)
Brewfab, LLC v. George Russo
Eleventh Circuit, 2022

Cite This Page — Counsel Stack

Bluebook (online)
34 F.4th 1251, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wadley-crushed-stone-company-llc-v-positive-step-inc-ca11-2022.