Vs DiCARLO CONSTRUCTION CO., INC. v. State

485 S.W.2d 52, 1972 Mo. LEXIS 876
CourtSupreme Court of Missouri
DecidedJuly 17, 1972
Docket56142
StatusPublished
Cited by46 cases

This text of 485 S.W.2d 52 (Vs DiCARLO CONSTRUCTION CO., INC. v. State) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vs DiCARLO CONSTRUCTION CO., INC. v. State, 485 S.W.2d 52, 1972 Mo. LEXIS 876 (Mo. 1972).

Opinion

FINCH, Chief Justice.

The question presented by this appeal is whether contract rights of a private citizen under a validly executed contract with the State may be asserted and established in a judicial proceeding.

We have jurisdiction because the State of Missouri is a party and more than $30,000 is involved. At the time this appeal was taken, those facts placed jurisdiction of the appeal in this Court. Article V, § 3, Constitution of Missouri, 1945, V. A.M.S. § 477.040, V.A.M.S.

The trial court sustained a motion to dismiss filed by the State. The parties agree that the only ground urged in support of such action was that sovereign immunity of the State prevented the maintenance of said suit and that the court dismissed the petition on that basis. We reverse and remand.

The pleadings disclose that the General Assembly passed and the Governor signed an Act appropriating money to the Division of Planning and Construction for construction of a building for the Adjutant General and Emergency Operation Center in Jefferson City, Missouri. (§ 9.040, C. C.S.H.B. No. 9, an Act of the 74th General Assembly, 1967.) 1 Thereafter, the State prepared plans and specifications and advertised for bids. Plaintiff was the low bidder and subsequently a contract between plaintiff and the State was approved by the Board of Public Buildings and executed on behalf of the State by the Director of the Division of Planning and Construction. Chap. 8, V.A.M.S.

Plaintiff’s petition consists of six counts. Count I seeks recovery for extra compensation for rock excavation above the elevation at which the specifications stated rock would commence. This count seeks to recover at the unit price specified in the contract for extra rock excavation. Count II asserts an alternative ground of recovery for the same rock excavation. Count III complains of wrongful assessment of liquidated damages and seeks recovery of the balance of the contract price due but for assessment of liquidated damages. Count IV seeks recovery for extra work which plaintiff was required to perform but which it says was not its obligation under the contract. Count V seeks recovery for the cost of some repairs resulting from acts by other contractors employed by the State. Count VI seeks recovery for extra expense caused by a change in sequence of the work directed by the State.

For the purposes of this appeal, the petition alleges sufficient facts to state a cause of action, but we do not reach or consider on this appeal the merits of any of plaintiff’s contentions. Those questions will be considered on remand by the trial court. Our decision is limited to the single issue of whether the doctrine of sovereign immunity denies to plaintiff in this case the opportunity to have such contract claims against the State heard and adjudicated.

As the brief filed on behalf of the State observes, “The courts of this State have consistently held that the State may not be sued without its consent.” Kleban v. Mor *54 ris, 363 Mo. 7, 247 S.W.2d 832, 836. 2 However, plaintiff does not attack the doctrine of sovereign immunity as such or ask that we discard it. Instead, its position is that the doctrine does not bar suit in this instance because the State has consented to be sued by entering into a validly authorized contract with plaintiff. 3 It is plaintiff’s position that when the General Assembly appropriated funds for the requested office building for the Adjutant General, it impliedly waived the sovereign immunity of the State and consented that the State might be sued in connection with questions arising in the performance of that contract.

Is the plaintiff’s analysis of the effect of legislative approval of the contract for erection of the Adjutant General’s building sound? Can it properly he said that by this action the General Assembly consented that the State should be bound by the terms of the construction contract and that it might be sued for any breach thereof? We answer these questions in the affirmative. Our conclusion is based on the assumption that the General Assembly did not intend a contract completely lacking in mutuality — one obligating the contractor to live up to its promises but imposing no binding obligation or responsibility on the State. It is based on the conclusion that when the State enters into a validly authorized contract, it lays aside whatever privilege of sovereign immunity it otherwise possesses and binds itself to performance, just as any private citizen would do by so contracting.

Such a view was expressed by the Supreme Court of Delaware in George & Lynch, Inc. v. Delaware, Del., 197 A.2d 734, 736, when it said:

“By 17 Del.C. § 132(b) (9), the State Highway Department is authorized to ‘make and enter into any or all contracts, agreements or stipulations.’ It must be assumed that the General Assembly, in granting to the State Highway Department the power to contract, intended that it should have power to enter into only valid contracts. A valid contract is one which has mutuality of obligation and remedy between the parties to it. 1 Williston on Contracts (3rd Ed.) § 1. It follows, therefore, that in authorizing the State Highway Department to enter into valid contracts the General Assembly has necessarily waived the State’s immunity to suit for breach by the State of that contract.”

Cases from other states have expressed like views. In Ace Flying Service, Inc. v. Colorado Department of Agriculture, 136 Colo. 19, 314 P.2d 278, 280, the court said:

“All contracts entered into by the State of Colorado or by any of the Departments in its behalf, are required to be awarded, pursuant to statute, to the lowest responsible bidder. Once entered into they are binding upon the state as well as upon the other contracting party. To hold that the state may enter into a contract by which the other party is compelled to expend large sums in acquiring material, machinery and personnel to enable it to perform its obligation, and then arbitrarily repudiate the contract relegating the injured party to the doubtful remedy of appealing to the legislature for justice in the form of a bill for relief, would be to sanction the highest type of governmental tyranny.

*55 “The applicable principle is that when a state enters into authorized contractual relations it thereby waives immunity from suit.”

In Regents of University System of Georgia v. Blanton, 49 Ga.App. 602, 176 S.E. 673, 675, the court said:

“A state or any of its departments entering into contracts lays aside its attributes of sovereignty, and binds itself substantially as one of its citizens does when he enters into a contract, and, in general, its contracts are interpreted as the contracts of individuals are, and are controlled by the same laws. Ohio Life Ins. & Trust Co. v. Debolt, 16 How. 416 [57 U.S. 416], 14 L.Ed. 997; notes, 42 L.R.A.(N.S.) 117.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blair v. City of Hannibal
179 F. Supp. 3d 901 (E.D. Missouri, 2016)
STATE EX REL. REDMOND v. State
328 S.W.3d 818 (Missouri Court of Appeals, 2011)
State Ex Rel. Kansas City Symphony v. State
311 S.W.3d 272 (Missouri Court of Appeals, 2010)
Kunzie v. City of Olivette
184 S.W.3d 570 (Supreme Court of Missouri, 2006)
184 Windsor Avenue, LLC. v. State
875 A.2d 498 (Supreme Court of Connecticut, 2005)
Kubley v. Brooks
141 S.W.3d 21 (Supreme Court of Missouri, 2004)
State ex rel. Missouri State Highway Patrol v. Atwell
119 S.W.3d 188 (Missouri Court of Appeals, 2003)
Pellegrino v. Rhode Island Ethics Commission
788 A.2d 1119 (Supreme Court of Rhode Island, 2002)
Federal Sign v. Texas Southern University
951 S.W.2d 401 (Texas Supreme Court, 1997)
Erickson Oil Products, Inc. v. State
516 N.W.2d 755 (Court of Appeals of Wisconsin, 1994)
Ferrell v. Department of Transportation
435 S.E.2d 309 (Supreme Court of North Carolina, 1993)
Kabir v. Missouri Department of Social Services
845 S.W.2d 102 (Missouri Court of Appeals, 1993)
Hackman v. Director of Revenue
771 S.W.2d 77 (Supreme Court of Missouri, 1989)
Krasney v. Curators of the University of Missouri
765 S.W.2d 646 (Missouri Court of Appeals, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
485 S.W.2d 52, 1972 Mo. LEXIS 876, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vs-dicarlo-construction-co-inc-v-state-mo-1972.