Voight v. R.L. Eldridge Construction Inc.

422 F. Supp. 2d 742, 2006 U.S. Dist. LEXIS 10975, 2006 WL 318818
CourtDistrict Court, E.D. Texas
DecidedFebruary 8, 2006
Docket1:04-CV-532
StatusPublished
Cited by1 cases

This text of 422 F. Supp. 2d 742 (Voight v. R.L. Eldridge Construction Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Voight v. R.L. Eldridge Construction Inc., 422 F. Supp. 2d 742, 2006 U.S. Dist. LEXIS 10975, 2006 WL 318818 (E.D. Tex. 2006).

Opinion

ORDER ADOPTING MAGISTRATE JUDGE’S REPORT AND RECOMMENDATION

HEARTFIELD, District Judge.

The court referred this case to the Honorable Earl S. Hines, United States magistrate judge, at Beaumont, Texas, for consideration pursuant to applicable laws and orders of this court. The court has received and considered the Report and Recommendation of the United States Magistrate Judge pursuant to such order, along with the record, pleadings and all available evidence.

The magistrate judge recommended that defendants’ motions to dismiss and for partial summary judgment be granted. Further, because that will dispose of all parties and claims, final judgment should be entered.

Plaintiff has not objected to the magistrate judge’s proposed findings, conclusions of law or recommendation of disposition. However, defendants filed an objection to footnote nine (9) in the report (See Docket No. 61). For the purpose of preserving their argument in the event of appeal, defendants request that the court amend the magistrate judge’s report by excluding footnote nine. Defendants claim footnote nine suggests they “failed to specifically address the issue of whether the work barges in question qualify as ‘vessels’ for the purposes of the Jones Act” (See Def.’s Objections at 1).

Upon conducting a de novo review of the magistrate judge’s report and defendant’s objection, the court first concludes footnote nine does not intimate that defendants failed to address the vessel issue. Rather the magistrate judge’s analysis does not specifically address the vessel issue. The magistrate judge’s report correctly determined that plaintiff was not a “seaman” under the Jones Act because no admissible evidence showed he contributed to the function of a vessel or that he had a substantial connection to a vessel. Footnote nine merely recites that the magistrate judge’s report only “assumes arguendo” that the work barges in question were vessels.

In any event, Fifth Circuit precedent has changed the definition of a “vessel” under the Jones Act since the magistrate judge’s report was filed. In response to Stewart v. Dutra Construction Co., 543 U.S. 481, 125 S.Ct. 1118, 160 L.Ed.2d 932 (2005), the circuit court in Holmes v. Atlantic Sounding Company, Inc. recently adopted Title 1, United States Code, Section 3, as the definition of “vessel” for claims under the Jones Act. Section 3 provides: “The word ‘vessel’ includes every description of watercraft or other artificial *745 contrivance used, or capable of being used, as a means of transportation on water.” See 437 F.3d 441 (5th Cir.2006) (emphasis in original). The Supreme Court in Stewart held that, “[ujnder § 3, a ‘vessel’ is any watercraft practically capable of maritime transportation, regardless of its primary purpose or state of transit at a particular moment.” Id. at 1129. The circuit’s new definition of “vessel” is now sweepingly broad, and it reveals that watercrafts formerly held not to be “vessels” under the Jones Act may now be “vessels” for “seaman” status purposes. Consequently, the magistrate judge’s arguendo assumption was not error.

The court has considered the magistrate judge’s report and conducted a de novo review of defendant’s objection. The court concludes that the findings of fact and conclusions of law of the magistrate judge are correct. Defendant’s objection is OVERRULED. Accordingly, the report of the magistrate judge is ADOPTED. It is therefore

ORDERED that defendant’s motion for partial summary judgment (Docket No. 46) is GRANTED. It is further

ORDERED that defendant’s Rule 12(b)(1) motion to dismiss (Docket No. 47) is GRANTED. The purpose of referral having been served, it is further

ORDERED that the reference to the magistrate judge is VACATED.

Because both motions above dispose of all parties and claims, the court will enter final judgment separately.

REPORT AND RECOMMENDATION OF UNITED STATES MAGISTRATE JUDGE

HINES, United States Magistrate Judge.

This report addresses defendants’ motions to dismiss and for partial summary judgment. 1

I. Nature of Suit; Parties

Plaintiff sues his former employer to recover compensatory damages for on-the-job personal injuries sustained by plaintiff and allegedly caused by his employer’s negligence. Plaintiff invokes this court’s subject-matter jurisdiction under two federal statutes: (1) Longshore & Harbor Worker’s Compensation Act, 33 U.S.C. §§ 901-950 (2000), and (2) Jones Act, 46 U.S.C.App. § 688 (2000).

Plaintiff is Charles W. Voight (Voight), a resident of Port Arthur, Texas. Plaintiff appears pro se (self represented). 2

Defendants are R.L. Eldridge Construction, Inc. (Eldridge) and Gabby’s Dock Shipyard. Eldridge is a Texas corporation with its principal office in Sabine Pass, Texas. Eldridge is a marine construction company that during relevant times operated a docking facility known as “Gabby’s Dock” located near the farthest point of Sabine Pass, Texas, and extending into the Gulf of Mexico.

II. Factual Background

This report generally adopts the version of facts advocated by plaintiff (the nonmovant), or as recited by defendant without opposition from plaintiff. 3

*746 In July, 2003, Voight was employed by Eldridge as a crane rigger. 4 His duty station was Gabby’s Dock, which Eldridge leased to R & R Marine for refurbishing an oil drilling rig. The project was known as the “Ensco 60 project.”

Eldridge’s flat-top barges were used as work platforms and for movement of construction materials from Gabby’s Dock to the rig. Compl. at 3, Aug. 19, 2004; Def.’s Partial Summ. J. Mot. at 2, ¶ 3, June 29, 2005; Pl.’s Resp. at 8, ¶ 3, Aug. 1, 2005. Eldridge’s barges were moved into place alongside the drilling rig by push boats, and then were secured to the dock and rig legs. PL’s Resp. at 8. Construction materials were moved from Gabby’s Dock onto the barges by Eldridge’s dockside crane. 5 Compl. at 3; Def.’s Partial Summ. J. Mot. at 2.

Eldridge sub-contracted its dockside crane riggers to assist R & R Marine in loading materials for the Ensco 60 project. Eldridge’s crane riggers prepared loads of materials on the dockside while R & R Marine and Ensco employees unloaded materials onto the barges. Although Eldridge crane riggers primarily worked on the dockside, they occasionally assisted on the barges. Def.’s Partial Summ. J. Mot. at 2, ¶ 4; see also Aff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
422 F. Supp. 2d 742, 2006 U.S. Dist. LEXIS 10975, 2006 WL 318818, Counsel Stack Legal Research, https://law.counselstack.com/opinion/voight-v-rl-eldridge-construction-inc-txed-2006.