Violet v. Federal Energy Regulatory Commission

800 F.2d 280, 1986 U.S. App. LEXIS 29461
CourtCourt of Appeals for the First Circuit
DecidedSeptember 5, 1986
Docket85-1734
StatusPublished
Cited by1 cases

This text of 800 F.2d 280 (Violet v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Violet v. Federal Energy Regulatory Commission, 800 F.2d 280, 1986 U.S. App. LEXIS 29461 (1st Cir. 1986).

Opinion

800 F.2d 280

Arlene VIOLET, Attorney General of the State of Rhode Island
and the Rhode Island Division of Public Utilities
and Carriers, Petitioners,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent.
New England Power Company, Intervenor.

No. 85-1734.

United States Court of Appeals,
First Circuit.

Heard April 11, 1986.
Decided Sept. 5, 1986.

Sheldon Whitehouse, Sp. Asst. Atty. Gen., with whom Arlene Violet, Atty. Gen., Providence, R.I., was on brief, for petitioners.

Joseph S. Davies, with whom John N. Estes, III, William H. Satterfield, General Counsel, and Joshua Z. Rokach, Washington, D.C., were on brief, for respondent.

Edward Berlin, with whom Andrew D. Weissman, Kenneth G. Jaffe and Swidler & Berlin, Chartered, Washington, D.C., were on brief, for intervenor.

Before CAMPBELL, Chief Judge, and ALDRICH and COFFIN, Circuit Judges.

LEVIN H. CAMPBELL, Chief Judge.

The State of Rhode Island petitions for review of an order of the Federal Energy Regulatory Commission ("FERC" or "Commission") permitting intervenor New England Power Company ("NEP") to recover, by passing on to consumers, the costs it incurred as a participant in the construction of the Pilgrim II nuclear power plant during the last 15 months before the project was abandoned. We affirm the FERC order.

I.

In 1972 NEP, along with nine other utilities, entered into a Joint Ownership Agreement with the Boston Edison Company ("Edison" or "BEC") for the construction and operation of the Pilgrim II nuclear generation unit in Plymouth, Massachusetts. Edison, the lead owner, retained a 59 percent interest in the project. NEP's interest was initially 9.97 percent, later increased to 11.16 percent.

The Joint Ownership Agreement gave Edison control over essentially all aspects of the project, including design, construction, operation, maintenance, cancellation, termination, suspension, and shutdown of the unit. The Agreement also limited Edison's liability to other joint owners to "damages resulting from a deliberate violation of the agreement occurring pursuant to authorized corporate action by Edison."

On September 23, 1981, Edison announced that it was cancelling the Pilgrim II project, citing as reasons the increased costs due to licensing delays, regulatory requirements, and uncertainty surrounding various other aspects of the project. In a rate proceeding brought by Edison, the Massachusetts Department of Public Utilities ("MDPU") ruled that project uncertainty had become intolerably high by June 30, 1980, and that Edison was imprudent in not cancelling the project by that date. It accordingly refused to allow Edison to recover its project expenditures from July 1, 1980 until the cancellation. Boston Edison Co., MDPU 906 (1982), aff'd, Attorney General v. Department of Public Utilities, 390 Mass. 208, 455 N.E.2d 414 (1983).

In 1982, NEP filed a wholesale rate increase request with FERC,1 seeking, in part, to recover its Pilgrim II investments. In 1983, NEP, Rhode Island, and the MDPU entered into a stipulation whereby NEP agreed not to contest the MDPU's finding that Edison had acted imprudently by continuing the Pilgrim II project beyond June 30, 1980. The stipulation preserved NEP's right to argue that its own conduct was prudent and that Edison's imprudence should not be imputed to NEP. See New England Power Co., 23 FERC p 61,314 (1983). At the hearing on NEP's rate request, therefore, the sole issue addressed was NEP's right to recover its investment in the Pilgrim II plant for the period of June 30, 1980 to September 23, 1981. No party challenged NEP's right to recoup investments made prior to that period.2

The administrative law judge hearing the case ruled against NEP. Focusing on the negotiations culminating in the signing of the 1972 Joint Operating Agreement, the ALJ found that NEP had been imprudent in giving Edison sole control over decisionmaking involving the plant, and in agreeing to the clause limiting Edison's liability to those damages resulting from deliberate violations of the agreement. He concluded, in essence, that since NEP had been imprudent in entering into these terms in the Agreement, and since Edison had been found imprudent in continuing expenditures in the plant after June 30, 1980, "[i]t follows that NEP's investment in Pilgrim II after June 30, 1980 was not prudently made." New England Power Co., 27 FERC p 63,037, at 65,170 (1984).3

The Commission reversed. New England Power Co., 31 FERC p 61,047 (1985). It ruled that the ALJ had erred in focusing on the terms of the 1972 agreement rather than on the prudence of NEP from July 1, 1980 to September 23, 1981, the challenged period. The Commission found that NEP had in fact been prudent in continuing to incur expenses during 1980-1981. Accordingly, the Commission ordered that NEP be permitted to amortize the requested portion of its Pilgrim II investment.

Rhode Island and the MDPU filed a petition for rehearing, which was denied. 62 FERC p 61,112 (1985). This petition for review, brought by Rhode Island alone, followed.

II.

Under the Administrative Procedure Act, we may set aside a FERC order only if we determine that it is arbitrary, capricious, an abuse of discretion, or in excess of statutory authority. 5 U.S.C. Sec. 706(2) (1982). We thus look to see whether the decision was based on a consideration of the relevant factors and whether there has been a clear error of judgment. Citizens to Preserve Overton Park v. Volpe, 401 U.S. 402, 416, 91 S.Ct. 814, 823-24, 28 L.Ed.2d 136 (1971). All findings of the Commission, if supported by substantial evidence, are conclusive upon us. Federal Power Act, 16 U.S.C. Sec. 825l (b) (1982); In re Permian Basin Area Rate Cases, 390 U.S. 747, 766, 88 S.Ct. 1344, 1359, 20 L.Ed.2d 312 (1968). With this deferential standard in mind, we examine the arguments made by Rhode Island.

The Commission, in exercise of its power "to devise methods of regulation capable of equitably reconciling diverse and conflicting interests," Mobil Oil Corp. v. Federal Power Commission, 417 U.S. 283, 331, 94 S.Ct. 2328, 2356, 41 L.Ed.2d 72 (1974) (quoting Permian Basin Area Rate Cases, 390 U.S. at 767, 88 S.Ct. at 1360), has applied the "prudence" test to determine the recoverability of a utility's expenses. Under this test, NEP is entitled to recover its costs from consumers if it acted "prudently" in incurring those costs, or stated conversely, NEP may not recover its costs if those costs were incurred "imprudently." See Missouri ex rel. Southwestern Bell Telephone Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
800 F.2d 280, 1986 U.S. App. LEXIS 29461, Counsel Stack Legal Research, https://law.counselstack.com/opinion/violet-v-federal-energy-regulatory-commission-ca1-1986.