Vinci Development Co. v. Connell

509 So. 2d 1128, 12 Fla. L. Weekly 1373
CourtDistrict Court of Appeal of Florida
DecidedMay 29, 1987
Docket86-726
StatusPublished
Cited by11 cases

This text of 509 So. 2d 1128 (Vinci Development Co. v. Connell) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vinci Development Co. v. Connell, 509 So. 2d 1128, 12 Fla. L. Weekly 1373 (Fla. Ct. App. 1987).

Opinion

509 So.2d 1128 (1987)

VINCI DEVELOPMENT COMPANY, a Florida Corporation, Appellant/Cross-Appellee,
v.
Peter W. CONNELL, Trustee, Appellee/Cross-Appellant.

No. 86-726.

District Court of Appeal of Florida, Second District.

May 29, 1987.
Rehearing Denied July 15, 1987.

*1129 V. James Dickson of Rahdert, Acosta & Dickson, P.A., St. Petersburg, for appellant/cross-appellee.

Michael J. Keane and Sarah M. Chaves of Keane, Hayes & Reese, P.A., St. Petersburg, for appellee/cross-appellant.

PER CURIAM.

We have before us an appeal and cross-appeal that arise from an amended final judgment in an action that was started in the trial court by appellant/cross-appellee's (Contractor) complaint for breach of contract and for foreclosure of a mechanic's lien. Appellee/cross-appellant (Owner) counterclaimed in three counts seeking compensatory damages for breach of the construction contract for failure of satisfactory performance and on a theory of constructive fraud, and a claim for punitive damages under the provisions of section 713.31, Florida Statutes (1983), alleging that Contractor exaggerated its claim of lien.

A jury returned a verdict finding Contractor was entitled to $10,791.43 as additional compensation on its contract for work performed for Owner. The jury also returned a general verdict for Owner on the two counts of his counterclaim seeking compensatory damages, but awarded zero damages to Owner.

The Contractor's mechanic's lien foreclosure and Owner's claim based on Contractor's alleged exaggerated lien were both tried before the court. The trial judge, because the jury returned a verdict for Contractor in an amount substantially less than his claim of lien, reluctantly concluded that section 713.31 required him to find that the claim of lien filed by Contractor was an "exaggerated claim" regardless of Contractor's "good-faith" in filing the claim. Therefore, under the terms of section 713.31(2)(b), the trial judge declared that the amount the jury found was owed *1130 Contractor under its contract with Owner was unenforceable as a claim of lien.

The trial judge also reluctantly concluded that section 713.31(2)(c) required an award to Owner of punitive damages in an amount equal to the difference between the amount claimed by Contractor and the amount found due it by the jury verdict. The trial judge determined that difference to be $34,201.23 which amount he awarded (plus $2,000.00 interest on monies placed in escrow) to Owner as "statutory damages." He then set off the amount found due to Contractor from the amount found due Owner as "statutory damages" and entered judgment for Owner for the balance of $25,409.89. Finding Owner to have been the prevailing party, he awarded Owner costs in the amount of $1,194.75 and attorney's fees of $16,500.

On its appeal, Contractor asserts as error two issues which relate to the jury's verdict as to the amount of Contractor's damages. We find no merit in either of those issues. Contractor also asserts as error the trial court's findings, and awards based thereon, that Contractor's claim of lien was a willfully exaggerated claim and, therefore, under the terms of section 713.31(2)(a), a fraudulent lien. We find merit in Contractor's assertions on this point for several reasons which we will later discuss. Based on that finding of error, we reverse the trial court's determination that the amount found by the jury to be due Contractor was unenforceable as a lien. We also reverse the award of punitive damages, costs, and attorney's fees to Owner.

Owner, on his cross-appeal, challenges the zero verdict rendered on his counterclaim. He alleges as error in that regard only an evidentiary issue relating to the court's admission into evidence of a financial statement pertaining to Owner and his wife. Owner argues on his cross-appeal that the evidence of his financial worth in the amount of some $4,000,000 was so prejudicial as to cause the jury to award zero damages even though the jury found for Owner on his counterclaim. We find no merit to that argument by Owner.

During the trial, Owner attempted to depict himself as an unsophisticated, uneducated, and inexperienced businessman to the extent that Contractor was allegedly able to take advantage of him and thereby breach a fiduciary relationship. In reviewing the record, we find there was wide-ranging exploration on both direct and cross-examination of both the principal parties pertaining to their relative experience and business acumen which made the financial statement relevant and, therefore, no error was committed by allowing its introduction. We, therefore, affirm in regard to Owner's cross-appeal.

We now turn to an explanation of why we find that the trial judge erred when he reluctantly concluded that section 713.31, under the circumstances of this case, mandated his finding Contractor's claim of lien unenforceable, and further mandated his award of punitive or "statutory damages" to Owner.

A brief review of the facts pertaining to the case is necessary to our explanation. Contractor and Owner entered into a contract that called for Contractor to build Phase I of a shopping center on Owner's property located on U.S. 19 north of Clearwater. Phase I consisted of two buildings, one to have retail tenants and the other to have office space. The contract called for the construction of the shell of the buildings and some basic interior work. Additional interior finishing work was initially contemplated, but no plans existed for such further interior work at the time the formal contract was executed. Such additional interior work was dependent on the needs of the tenants ultimately leasing the space. All of the work for which plans existed was completed by Contractor. No additional plans existed, and no further work was ever offered for Contractor to complete.

Contractor's compensation under its contract with Owner was to be arrived at by utilization of a three-part formula. First, Contractor was to be paid all costs incurred in performance of the contract. Second, a contractor's fee of fifteen per cent of all costs was to be paid. Third, and finally, *1131 Contractor was to be paid an additional fee equal to fifty per cent of the difference between the maximum budgeted or projected contract total costs as adjusted by change orders and the actual costs incurred if less than the maximum projected costs.

This third and final part of the contract compensation formula was referred to at trial as a savings or under-budget bonus. Contractor prepared for Owner a maximum budget costs allocation for all phases of the work that was to be performed. Contractor completed all work he was given to perform at a cost substantially less than the allocated budget amount. When no further work was offered Contractor, it submitted a final billing for the work performed. This billing included the first two parts of the compensation formula, the costs incurred and the fifteen per cent Contractor's fee, which totalled $10,791.49, the amount ultimately found to be due by the jury verdict.

In addition, Contractor's final billing for the work performed also included the amount represented by the third part of the formula, the savings or under-budget bonus. That savings fee was billed at $34,131.17 and was arrived at basically by using calculations involving credits for the cost of completing the remaining interior work at the same rate of savings as had been achieved on the work already performed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

FARREY'S WHOLESALE HARDWARE CO., INC. v. COLTIN ELECTRICAL SERVICES, LLC
263 So. 3d 168 (District Court of Appeal of Florida, 2018)
Gator Boring & Trenching, Inc. v. Westra Construction Corp.
210 So. 3d 175 (District Court of Appeal of Florida, 2016)
Sharrard v. Ligon
892 So. 2d 1092 (District Court of Appeal of Florida, 2004)
Delta Painting, Inc. v. Baumann
710 So. 2d 663 (District Court of Appeal of Florida, 1998)
Scott v. Rolling Hills Place Inc.
688 So. 2d 937 (District Court of Appeal of Florida, 1997)
Wal-Mart Stores, Inc. v. AAA Asphalt, Inc.
677 So. 2d 93 (District Court of Appeal of Florida, 1996)
Casa Linda Tile & Marble Installers, Inc. v. Highlands Place 1981, Ltd.
642 So. 2d 766 (District Court of Appeal of Florida, 1994)
W. Dorsky Associates, Inc. v. Highlands Cty. Title and Guaranty Land Co.
528 So. 2d 411 (District Court of Appeal of Florida, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
509 So. 2d 1128, 12 Fla. L. Weekly 1373, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vinci-development-co-v-connell-fladistctapp-1987.