M.B. Hayes, Inc. v. Tak Chin Choi (In Re M.B. Hayes, Inc.)

305 B.R. 361, 17 Fla. L. Weekly Fed. B 102, 2003 Bankr. LEXIS 1927
CourtUnited States Bankruptcy Court, M.D. Florida
DecidedDecember 17, 2003
DocketBankruptcy No. 01-21054-8P1, Adversary No. 02-203
StatusPublished
Cited by1 cases

This text of 305 B.R. 361 (M.B. Hayes, Inc. v. Tak Chin Choi (In Re M.B. Hayes, Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, M.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M.B. Hayes, Inc. v. Tak Chin Choi (In Re M.B. Hayes, Inc.), 305 B.R. 361, 17 Fla. L. Weekly Fed. B 102, 2003 Bankr. LEXIS 1927 (Fla. 2003).

Opinion

FINDINGS OF FACT, CONCLUSIONS OF LAW, AND MEMORANDUM OF DECISION

ALEXANDER L. PASKAY, Chief Judge.

The matter under consideration in this Chapter 11 case are three claims asserted by M.B. Hayes, Inc. (Debtor), in three separate counts against Tak C. Choi, Yuet N. Choi, Chan C. Choy, and Wai Cheng Choy, all doing business as Albert’s Asian Bistro, Inc. (Owner-Defendants). On March 8, 2002, the Debtor originally filed the instant action seeking to foreclose its construction lien and for breach of cohtract (Document No. 1). The Debtor later amended its complaint joining additional defendants (“Third Party Defendants”) and asserting a third claim for declaratory relief to determine the extent, validity, and priority of liens against the contract proceeds and the Owner-Defendants’ real property (Document No. 27). 1

The Owner-Defendants filed an answer and counterclaims seeking damages pursuant to Florida Statute 713 and declaratory relief as to the Third Party Defendants (Document No. 71). In addition, this Court allowed Keene Brothers, Inc. (“Keene Brothers”) to intervene (Document No. 23). Keene Brothers, a subcontractor on the Project, filed a counterclaim and cross-claim against the Owner-Defendants asserting an interest in the contract proceeds and an equitable lien against the Owner-Defendants’ real property (Document No. 24). This Court subsequently dismissed Albert’s Asian Bistro, Inc. from the lawsuit.

This Court bifurcated the Debtor’s claims and tried its claims to foreclose its construction lien and for breach of contract with the Owner-Defendants’ counterclaims for relief pursuant to Section 713 Florida Statutes (Document No. 22).

This Court having considered the testimony of witnesses, the exhibits offered and admitted into evidence, the pleadings and stipulation offered by the parties, and the post-trial submissions by the parties, now finds and concludes as follows.

I.

On May 22, 2000, the Debtor entered into a stipulated sum contract with Wohup Development, Inc. to build a restaurant to be known as Albert’s Asian Bistro (the Project)(Debtor’s Exhibit No. 1). James H. Post signed the contract on behalf of the Debtor and Chan Choy signed the contract on behalf of the Owner-Defendants. The contract identified the architect as ROJO Architect. On August 1, 2000, the parties executed an addendum changing the owner’s name from Wohup Development, Inc. to Tak C. Choi, Yuet N. Choi, Chan C. Choy, and Wai Cheng Choy, all doing business as Albert’s Asian Bistro, Inc., previously defined as the Owner-Defendants.

The contract provided that the Debtor would commence work within ten days of the issuance of permits and substantially complete construction within 150 days. There were no penalties, however, for the Debtor’s failure to complete the Project within this time.

The contract stipulated the sum of $707,965 for the work contemplated. The *364 design and installation of an owner supplied Chinese arch and walkway was included in that price. The Debtor was entitled to periodic payments during the pendency of the construction subject to certain requirements. The Owner-Defendants were to make the final payment due on the contract no later than 30 days after the issuance of the final certificate, receipt of a certificate of occupancy, and receipt of all required lien waivers.

The contract provided a means by which the parties could vary its terms by the execution of mutually agreed upon change orders. A change order had to set forth in writing the change in work, adjustment in contract sum, if any, and adjustment in contract time, if any.

If the Debtor and Owner-Defendants could not agree on the terms of a change order, the architect could prepare a construction change directive with agreement by the Owner-Defendants. The construction change directive would direct the performance of the work but reserve for future determination the assessment of costs associated with the change. Under this procedure, the architect could later assess costs using one of three methods. Alternatively, the Debtor could keep an itemized accounting of the costs incurred in executing the change order — including labor, materials, equipment, insurance and other fees, and supervision — together with a reasonable allowance for overhead and profit. The architect determined all cost disputes for purposes of interim payments, subject to the rights of the parties to assert a formal claim.

To assert a formal claim, the parties had to do so in writing within 21 days of the occurrence of the event giving rise to the claim or the time that the claimant first recognized the condition giving rise to the claim, whichever occurred later. If the claim requested an increase in the contract price, the claimant had to initiate the claim before proceeding with the work, except in limited emergency situations. Claims for additional time had to include an estimate of the cost and probable effect of delay on the scheduled construction. In the case of continuing delay only one claim was required.

As is common in the construction business, the parties began to execute change orders almost immediately upon the Debt- or’s commencement of the Project. The vast majority of these change orders were at the Owner-Defendants’ behest or for reasons beyond the control of the Debtor. As a consequence of these change orders, the estimated completion time for the Project was extended by a further 201 days, more than doubling the original time estimate.

In December 2000, the Debtor executed a change order recognizing some of these delays and assessing a delay charge of $4,155. The Debtor calculated the delay charge by multiplying $277 (the estimated daily cost of site supervision and overhead expenses) by 15 days. The Owner-Defendants refused to sign this change order. The architect was no longer associated with the Project, limiting the options available to the parties to settle the dispute for purposes of interim payments. Ultimately, the Debtor executed a substitute change order listing the additional days to be added to the completion time but omitting charges for those days (Debtor’s Composite Exhibit No. 4). Although the Debt- or verbally warned the Owner-Defendants that it would assess those charges at the end of the contract, it did not make a formal claim.

Thereafter, the Debtor excluded delay charges from its change orders and charged only for costs of materials and *365 labor. 2 Consistent with its promise to later add delay charges, the Debtor twice more executed change orders detailing additional days but assessing no charges. 3

Eventually, the Debtor completed the Project with the exception of the installation of the Chinese arch and walkway. The Debtor could not complete this part of the Project due to difficulties in obtaining permits and problems in delivery caused by the Owner-Defendants. By this time, the Debtor was under extraordinary financial pressures caused by an ambitious expansion of its business. The timely collection of its accounts receivables was critical to its financial health.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sharrard v. Ligon
892 So. 2d 1092 (District Court of Appeal of Florida, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
305 B.R. 361, 17 Fla. L. Weekly Fed. B 102, 2003 Bankr. LEXIS 1927, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mb-hayes-inc-v-tak-chin-choi-in-re-mb-hayes-inc-flmb-2003.