Scott v. Rolling Hills Place Inc.

688 So. 2d 937, 1996 WL 714018
CourtDistrict Court of Appeal of Florida
DecidedFebruary 21, 1997
Docket96-1159
StatusPublished

This text of 688 So. 2d 937 (Scott v. Rolling Hills Place Inc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Scott v. Rolling Hills Place Inc., 688 So. 2d 937, 1996 WL 714018 (Fla. Ct. App. 1997).

Opinion

688 So.2d 937 (1996)

William SCOTT, P.E., etc., Appellant,
v.
ROLLING HILLS PLACE INC., etc., Appellee.

No. 96-1159.

District Court of Appeal of Florida, Fifth District.

December 13, 1996.
Order Denying Rehearing, but Granting Clarification February 21, 1997.

*938 Ronald W. Brown and Geoffrey B. Dobson of Dobson & Brown, P.A., St. Augustine, for Appellant.

Allen C.D. Scott, II and Holly E. Scott of Scott & Scott, P.A., St. Augustine, for Appellee.

W. SHARP, Judge.

Scott appeals from a final judgment entered against him for breach of contract, which included compensatory as well as punitive damages based on his provision of engineering services for Rolling Hills Place, Inc. (Rolling Hills). We reverse.

Rolling Hills hired Scott, a professional engineer, to work on a 57 acre, single family planned unit development. At the time Rolling Hills engaged Scott's services, he held a position as a full time utility manager for the City of St. Augustine, with a part-time engineering practice. Rolling Hills was aware of this situation. Scott prepared two proposals for his services. The first proposal was rejected. The second proposal was orally accepted, and Scott memorialized it in a letter agreement which Rolling Hills executed, but did not return to Scott. It was silent as to the method of payment. It included seven tasks which Scott was to complete, as well as specific payment amounts and a target date for each specified task. All application, connection and filing fees were assigned as the responsibility of Rolling Hills.

Scott commenced work on the project based upon the oral agreement between the parties. He submitted invoices on June 30, 1993, September 27, 1993 and January 12, 1994, which Rolling Hills paid in full. However, when Scott submitted the fourth invoice on April 15, 1994, Rolling Hills paid only one-half. Two more invoices, on July 28, 1994 and September 8, 1994, went unpaid. At that time, Scott claimed Rolling Hills owed him in excess of $15,000. The plans were completed, and all that had to be done was for Scott to sign and seal the plans. He failed to do this because Rolling Hills refused to pay him. He also filed a mechanics lien[1] against the property to protect his interests.

Rolling Hills filed this action against Scott in November of 1994, alleging Scott had breached the contract, and that the lien was a fraudulent one. It requested damages for breach of contract, and punitive damages as well as attorneys' fees. Subsequently, in January of 1995, Rolling Hills hired Christopher Hurst, a civil engineer, to complete the project. Hurst freely admitted copying Scott's plans on which he affixed his own "surveyor—engineer's block.". On January 27, 1995, Hurst submitted the plans to St. John's County. Later minor adjustments were made to the plans. These plans were approved.

After a nonjury trial, the judge found that Scott breached the contract due to his failure to sign and seal the plans. He also found the contract to be nonspecific as to when payments were due, and that Rolling Hills offered to escrow the remainder due under the *939 agreement if Scott would finish the job.[2] The lower court acknowledged that Scott produced much of the work for the project, but found Rolling Hills received no benefit from these endeavors. This finding was in direct contrast to Hurst's unrebutted testimony that he copied Scott's plans and that these plans were approved.

Based upon its findings that Scott breached the contract, the court found that Rolling Hills suffered damages of $10,630 for engineering services to complete the plans and obtain approvals, $6,096 for survey work, compensatory damages of $5 and punitive damages of $5,000. Prejudgment interest from October 14, 1994 in the sum of $2,901.37 was also awarded, for a total sum of $24,632.90.

The key issue in this case is which party breached the contract first. The unrebutted facts compel us to conclude that Rolling Hills was the party who first breached the contract by its failure to pay Scott monies due him under it. Although the contract was silent as to the method of payment, the actions of the parties in making interim payments on the submission of invoices became a term of the contract. Lalow v. Codomo, 101 So.2d 390, 393 (Fla.1958); Bay Management, Inc. v. Beau Monde, Inc., 366 So.2d 788 (Fla. 2d DCA 1978). Parties' interpretations of their own contract will be followed unless contrary to law. Welsh v. Carroll, 378 So.2d 1255, 1257 (Fla. 3d DCA 1979), cert. denied, 386 So.2d 643 (Fla.1980). See also, M.G.M. Inc. v. Scheider, 40 N.Y.2d 1069, 392 N.Y.S.2d 252, 253, 360 N.E.2d 930 (1976)(courts imply term from external sources, including course of dealing, where contract silent).

Scott's failure to sign and seal the plans arose as a result of Rolling Hills' refusal to pay him for his services, and after Rolling Hills verbalized to third parties its intention not to make full payment under the contract. Moreover, it occurred some five months after Rolling Hills breached the contract by not paying the April invoice in full, and it was Scott's attempt to secure payment for which he was entitled under the contract.

We are also unpersuaded by Rolling Hills' argument that Scott filed a fraudulent lien. We find no evidence in the record which would support this finding. Rather, Scott's filing of the lien was to ensure that he received payment for his work, a purpose for which the mechanic's lien law was framed. Prosperi v. Code, Inc., 626 So.2d 1360, 1362 (Fla.1993). As the court noted in Prosperi, the purpose of the mechanic's lien law is "to afford the laborer or materialman adequate assurance of being fully compensated for his labor or services." Id. at 1362. Section 713.31(2)(a) requires a willful exaggeration of the lien before a lien may be deemed fraudulent.[3] Scott's claim of lien only indicated the amount he believed remained unpaid for the work performed, and we are unable to find this estimate to be a willful exaggeration of what was due him, in light of the facts in this case. A dispute as to the amount of money owed, or a dispute as to the method of payment, does not convert a good faith dispute into a fraudulent lien. Vinci Development Co. v. Connell, 509 So.2d 1128, 1132 (Fla. 2d DCA), rev. denied, 518 So.2d 1274 (Fla.1987). Therefore, the punitive damage award must be stricken,[4] and Scott is entitled to have his lien enforced.

*940 Upon remand to the trial court, a judgment in favor of Scott shall be entered in Rolling Hills' breach of the contract suit, and a hearing should be held on the question of damages. Scott is entitled to recover for the loss of his anticipated profits, which is the difference between the contract price and what it would have cost to perform the contract. Brevard County v. Interstate Engineering Co., 224 So.2d 786 (Fla. 4th DCA 1969). See also Physicians Reference Laboratory, Inc. v. Daniel Seckinger, M.D. & Associates, 501 So.2d 107 (Fla. 3d DCA 1987) (measure of damages for breach of contract to furnish services is the profit nonbreaching party would have earned during the remainder of the term if the contract had not been breached). He is further entitled to attorneys fees, as requested in his counterclaim. § 713.29, Fla. Stat. (1995).

REVERSED AND REMANDED.

GOSHORN and THOMPSON, JJ., concur.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Globe Refining Co. v. Landa Cotton Oil Co.
190 U.S. 540 (Supreme Court, 1903)
Fla. E. Coast Railway Co. v. Beaver St Fisheries, Inc.
537 So. 2d 1065 (District Court of Appeal of Florida, 1989)
Jackson v. US AVIATION
466 So. 2d 1119 (District Court of Appeal of Florida, 1985)
Physicians Reference Laboratory, Inc. v. DANIEL SECKINGER, MD AND ASSOCIATES, PA
501 So. 2d 107 (District Court of Appeal of Florida, 1987)
Bay Management, Inc. v. Beau Monde, Inc.
366 So. 2d 788 (District Court of Appeal of Florida, 1978)
County of Brevard v. Interstate Engineering Co.
224 So. 2d 786 (District Court of Appeal of Florida, 1969)
Bird Lakes Dev. v. Meruelo
626 So. 2d 234 (District Court of Appeal of Florida, 1993)
Prosperi v. Code, Inc.
626 So. 2d 1360 (Supreme Court of Florida, 1993)
Lalow v. Codomo
101 So. 2d 390 (Supreme Court of Florida, 1958)
Vinci Development Co. v. Connell
509 So. 2d 1128 (District Court of Appeal of Florida, 1987)
Jacobs v. Wainwright
450 So. 2d 200 (Supreme Court of Florida, 1984)
Tillman v. Howell
634 So. 2d 268 (District Court of Appeal of Florida, 1994)
Welsh v. Carroll
378 So. 2d 1255 (District Court of Appeal of Florida, 1979)
Poinsettia Dairy Products, Inc. v. the Wessel Co.
166 So. 306 (Supreme Court of Florida, 1936)
Metro-Goldwyn-Mayer, Inc. v. Scheider
360 N.E.2d 930 (New York Court of Appeals, 1976)
Hollis v. State
688 So. 2d 937 (District Court of Appeal of Florida, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
688 So. 2d 937, 1996 WL 714018, Counsel Stack Legal Research, https://law.counselstack.com/opinion/scott-v-rolling-hills-place-inc-fladistctapp-1997.