Village of Downers Grove v. American Surety Co. of New York

218 Ill. App. 608, 1920 Ill. App. LEXIS 327
Appellate Court of Illinois·Decided June 29, 1920·No. Gen. No. 6,798·Published·Cited by 5 cases

Opinion

Mr. Presiding Justice Dibell

delivered the opinion of the court.

In the spring and summer of 1915 the Village of Downers G-rove, under ordinance No. 49, laid sidewalks on certain streets, to be paid for by special assessment. The contract was duly let to Kent R. Wyllie, who by the contract was required to give a bond for the performance of the contract, and he did give such a bond, executed by himself as principal and by the American Surety Company of New York as surety. The work was completed and accepted by the Board of Local Improvements of said village, and in October, 1915, the county court entered an order finding that the work had been constructed substantially in compliance with the ordinance. During the same time the village also provided for the construction of a sidewalk on another street, under ordinance No. 50, and the contract was let. to the same contractor and he gave a like bond for the performance of that contract, with the same surety, and the work was done and certified in like manner by the Board of Local Improvements, and on the same day in October, 1915, a like order was entered by the county court, finding the work done in substantial compliance with the ordinance. In the following spring it was found,that portions of each of said sidewalks were disintegrating, and this was obviously due to a failure by the contractor to build those portions in conformity to the plans and specifications, for the proof is undisputed that a sidewalk constructed in compliance with the plans and specifications would last from 30 to 50 years. Wyllie seems to have ’ disappeared, and the surety was notified of the condition and called upon to repair the work, and there were interviews and correspondence between the village officers and representatives of the surety company which covered a considerable period of time and ended in a refusal by the surety company to take any action. The village thereupon let several contracts for the repair of various parts of the sidewalk, and brought two actions against the contractor, one upon each bond. There was much special pleading in each case which requires no discussion, as it was stipulated at the trial that defendant could put in any defense which it could properly put in under any plea well pleaded. The two suits were tried together before a jury under an agreement that they should be so tried and that there should be separate verdicts. There was a jury trial and there was a separate verdict in each case for plaintiff for the amount of the debt and assessing the damages. A motion by defendant for a new trial was denied. Two judgments were entered in proper form. A single appeal was prayed and prosecuted by defendant, and this appeal has been treated by appellee as properly prosecuted in that way.

Section 84 of the Local Improvement Act (J. & A. |f 1477) enacts that after the work has been done, it shall be the duty of the Board of Local Improvements to certify to the county court whether the improvement conforms to the requirements of the ordinance and to make application to the county court to determine whether the facts stated in said certificate are true, and thereupon, after public notice, the county court shall hear the application and determine the same in a summary manner, and enter an order according to the facts, which order shall be conclusive upon all the parties, and the statute denies any appeal or writ of error. The chief defense interposed by appellant is that the order of the county court in these two special assessment cases is conclusive that these improvements were completed in compliance with the ordinance, and that that judgment is res judicata in this case, and that the circuit court has no jurisdiction to again try that question. Various cases' are cited where it has been said that such order of the county court is conclusive and that that question cannot again be litigated in the circuit court. Some of these are cases where owners were objecting to the payment of instalments of the assessment because of defective workmanship, and others are cases where the contractor was endeavoring to enforce payment by a suit against the city, where the work had not been formally accepted and the question of its completion had not been submitted to the county court as said statute requires. The statute does not intend that such order of the county court shall be in every respect conclusive upon everybody, for section 83 of the same Act (J. & A. jf 1476) provides that if any property owner shall be injured by any failure to construct such improvement in substantial compliance with the ordinance, he may recover the amount of his injury or pecuniary loss because thereof in an action on the case against the municipality.

Free access — add to your briefcase to read the full text and ask questions with AI

Village of Downers Grove v. American Surety Co. of New York, 218 Ill. App. 608, 1920 Ill. App. LEXIS 327 (Ill. Ct. App. 1920).

218 Ill. App. 608 (Village of Downers Grove v. American Surety Co. of New York) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Metropolitan Sanitary District v. Anthony Pontarelli & Sons, Inc.
288 N.E.2d 905 (Appellate Court of Illinois, 1972)
Govekar v. Kweder
16 N.E.2d 249 (Appellate Court of Illinois, 1938)
Missoula County Free High School v. Smith
8 P.2d 800 (Montana Supreme Court, 1932)
City of Aurora v. Lakin
222 Ill. App. 480 (Appellate Court of Illinois, 1921)
Baker v. Ayers
223 Ill. App. 460 (Appellate Court of Illinois, 1921)