Metropolitan Sanitary District v. Anthony Pontarelli & Sons, Inc.

288 N.E.2d 905, 7 Ill. App. 3d 829, 1972 Ill. App. LEXIS 2377
CourtAppellate Court of Illinois
DecidedSeptember 8, 1972
Docket55265
StatusPublished
Cited by40 cases

This text of 288 N.E.2d 905 (Metropolitan Sanitary District v. Anthony Pontarelli & Sons, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metropolitan Sanitary District v. Anthony Pontarelli & Sons, Inc., 288 N.E.2d 905, 7 Ill. App. 3d 829, 1972 Ill. App. LEXIS 2377 (Ill. Ct. App. 1972).

Opinion

PER CURIAM:

Plaintiff, in this appeal from an order granting defendants 1 summary judgment, contends that the motion was erroneously granted.

All counts of the amended complaint related to a contract between plaintiff and Anthony Pontarelli and Sons, Inc. (hereinafter referred to as Pontarelli) for the construction of a sewer. The substance of those counts is as follows: Count I aHeged that PontareHi and Burton Scheidt, plaintiff’s Chief Engineer, through fraud and deceit, induced plaintiff to pay PontareHi $2,965,042.89 to which PontareHi was not entitled; Count II aHeged that when PontareHi entered into the contract, it falsely and fraudulently represented that it would do all of the work required by the contract, but PontareHi never intended to abide by the contract terms; Count III alleged a combination and conspiracy on the part of PontareHi and Scheidt to defraud plaintiff; Count IV aHeged that Pontarelli wrongfully obtained $1,114,125.13 in payment for extra work which was not authorized by the Board of Trustees as required by the contract and that PontareHi refused to repay that amount as required by the contract; Count V alleged a cause of action for breach of express and implied warranties; Count VI aHeged a cause of action for breach of contract; Count VII aHeged a cause of action for negligence; Count VIII alleged a cause of action for unjust enrichment; and Count IX, as amended, aHeged a cause of action against Fidelity and Deposit Company of Maryland (hereinafter referred to as Fidelity) as surety on PontareHi’s performance bond.

No answers to this complaint were filed, but all defendants filed separate motions for summary judgment which were supported by affidavits and other documents. Plaintiff then filed counter-affidavits and documents.

Generally, Pontarelli contended that the complaint was conclusory. SpecificaUy, as to Count I, Pontarelli aHeged that the allegations were insufficient to state a cause of action against it; that because plaintiff had knowledge imputed to it through Scheidt of the actual facts, there could have been no reliance upon the representations of Pontarelli or Scheidt, and that plaintiff was estopped by its inspection of the construction to deny proper performance of the contract. As to Count II Pontarelli contended, inter alia, that because the charges did not relate to existing or past facts, no cause of action was alleged. As to Count III Pontarelli contended that the complaint did not allege an essential element of a cause of action for conspiracy i.e., damages, and again raised the defense of imputed knowledge. Witii reference to Count IV Pontarelli contended that the authorization of the final payment for extras ratified all extra payments and plaintiff was thereby estopped from denying performance; that Scheidt’s approval of the work was a complete defense under the contract, and the requirement of Board approval of extra work was obviated by the contract. With reference to Counts V, VI and VII, Pontarelli again raised the defense of imputed knowledge and estoppel and contended further that Scheidt’s approval of the work was binding upon plaintiff. Also, as to Count VIII Pontarelli raised the defense of imputed knowledge. With respect to Count IV Pontarelli contended that because no cause of action was properly pleaded against it, no cause of action was pleaded against Fidelity.

In Scheidt’s motion for summary judgment as to Count I he contended in substance that plaintiff had imputed knowledge and therefore could not have relied upon any false representations; that plaintiff was estopped from claiming damages; and that plaintiff did not plead a good cause of action. As to Count III, Scheidt contended that because of the knowledge imputed to it, plaintiff would not have been damaged as a result of Scheidt’s representations, that plaintiff was estopped from claiming damages, and plaintiff had not pleaded a good cause of action. Scheidt contended that both counts were conclusory and that no genuine issue of material fact existed. The motion did not expressly treat the remaining counts of the amended complaint as Scheidt merely stated that they did not seek relief against him.

Fidelity, in its motion for summary judgment on Count IV as amended, expressly relied upon Pontarelli’s motion. Fidelity went on to contend that plaintiff’s approval of the final payment constituted an acceptance of Pontarelli’s performance thereby releasing Fidelity of its obligation and liability.

The gist of the affidavits filed by plaintiff is set out below.

The sewer was not constructed in accordance with the terms of the contract. Hie sewer was improper, faulty and unworkmanlike in the following respects: it is out of alignment; it has a rough grade (in some places the grade varied 20 to 30 inches within a very short distance) and sharp breaks, its concrete bed is unstable, and, in part, the sewer settled more than eight feet. One affidavit stated that, instead of concrete as called for in the contract, a twelve inch stone bed was laid under the sewer. The contract required 330,000 pounds of reinforcement steel; only 113,097 pounds were delivered to the jobsite, but plaintiff was bffled for 412,758 pounds, the difference in value amounting to $33,000. Plaintiff was also bffled for 8146 cubic yards of encasement concrete but only 7465 cubic yards were installed, a difference in value of $10,400. The location and distribution of reinforcement steel and concrete covering for the sewer pipe was not as required by the contract. An insufficient quahty of material was used in the sewer’s construction, the concrete top to the sewer was improperly placed. Extremely poor construction procedures resulted in a deficiency of the encasement concrete in the invert and the arch. The joints in the sewer opened causing it to leak, allowing foreign matter to infiltrate the sewer and be carried to a treatment plant. The leaks also caused stalactites to form on the inside top of the pipes. The flowage capacity of the sewer was reduced below contract requirements. This was partially caused by the use of steel bands on the joints. The “sandbox” procedure used in the construction proved to be unsatisfactory. Better “dewatering” of the site was possible at the time of repairs and possibly during the construction itself. Approximately ten percent of the sewer line needed replacement or repair. Where repairs have been made, a good grade has been maintained and there are no apparent leales. A portion of the sewer wiU be abandoned. In both May and June of 1966 the sewer coUapsed. The Pittsburgh Testing Laboratory was retained to review the work on the sewer and reported that there was a shortage of concrete around the pipe and the amount of reinforcement steel “probably” was less than that called for in the design drawings. It was through the report of the Pittsburgh Testing Laboratory, filed on September 30, 1966, that plaintiff first learned of the deficiency in the materials. It was Scheldt’s duty to inspect the work and the materials used. Scheldt appointed Edward Lopatowski as resident engineer and he was to report all matters to Scheldt. Although there were gross irregularities in the work, Lopatowski and Scheldt certified that the work was properly performed in compliance with the plans and specifications. Lopatowski knew that the sewer afignment was poor, the grade was not being maintained and the joints were open.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Heartland Women's Healthcare, Ltd. v. Simonton- Smith
2021 IL App (5th) 200135-U (Appellate Court of Illinois, 2021)
Garlick v. Naperville Township
2017 IL App (2d) 170025 (Appellate Court of Illinois, 2017)
Gold Realty Group Corp. v. Kismet Café, Inc.
832 N.E.2d 403 (Appellate Court of Illinois, 2005)
Gold Realty Group Corp. v. Kismet Cafe
Appellate Court of Illinois, 2005
Resolution Trust Corp. v. Franz
909 F. Supp. 1128 (N.D. Illinois, 1995)
American National Bank & Trust Co. v. Edgeworth
618 N.E.2d 899 (Appellate Court of Illinois, 1993)
Home Insurance v. Dunn
963 F.2d 1023 (Seventh Circuit, 1992)
Home Insurance Company v. Dunn
963 F.2d 1023 (Seventh Circuit, 1992)
Fister/Warren v. Basins, Inc.
578 N.E.2d 37 (Appellate Court of Illinois, 1991)
Turner v. Cosmopolitan National Bank
536 N.E.2d 806 (Appellate Court of Illinois, 1989)
First National Bank v. Jones
523 N.E.2d 377 (Appellate Court of Illinois, 1988)
Bank of Waukegan v. Epilepsy Foundation of America
516 N.E.2d 1337 (Appellate Court of Illinois, 1987)
Commonwealth Eastern Mortgage Co. v. Williams
516 N.E.2d 515 (Appellate Court of Illinois, 1987)
Gold v. Vasileff
513 N.E.2d 446 (Appellate Court of Illinois, 1987)
Olivieri v. Coronet Insurance
528 N.E.2d 986 (Appellate Court of Illinois, 1987)
McGinnis v. A. R. Abrams, Inc.
490 N.E.2d 115 (Appellate Court of Illinois, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
288 N.E.2d 905, 7 Ill. App. 3d 829, 1972 Ill. App. LEXIS 2377, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metropolitan-sanitary-district-v-anthony-pontarelli-sons-inc-illappct-1972.