Turk v. United States Fidelity & Guaranty Co.

197 N.E. 765, 361 Ill. 206
CourtIllinois Supreme Court
DecidedJune 14, 1935
DocketNo. 22896. Reversed and remanded.
StatusPublished
Cited by3 cases

This text of 197 N.E. 765 (Turk v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Turk v. United States Fidelity & Guaranty Co., 197 N.E. 765, 361 Ill. 206 (Ill. 1935).

Opinion

Mr. Justice Shaw

delivered the opinion of the court:

On July 11, 1930, the plaintiff below, Louis Turk, entered into a contract with A. E. Bjork whereby the latter undertook to furnish all labor and materials necessary to move back and re-set a certain building on Western avenue, in Chicago, in connection with the widening of that street and to comply with the provisions of a condemnation judgment. The contract price was $6700, $1000 of which was to be paid when the new location was excavated, $3000 to be paid when the building was moved, $1000 to be paid when sewer, water and plumbing had been installed, and the remaining $1700 to be paid within ten days after the completion of the contract. It was also set forth in the agreement that in case the contractor should be guilty of any substantial breach, the owner would have the right to terminate the agreement and engage another contractor to complete the job, in which circumstances the original contractor was to be liable for any and all damages, the wording being, “such damages to be deducted from part of the contract price that should remain due to the contractor.” There was also a provision for a date of completion and liquidated damages in the event of delay beyond that date. To secure the performance of this contract a bond was executed by the contractor with the defendant, the United States Fidelity and Guaranty Company, as surety, the principal sum of the bond being the full contract price of $6700. It was the condition of the bond that it should be void only in the event the contractor should “perform and fulfill all and every the covenants, conditions, stipulations and agreements in said contract mentioned to be performed and fulfilled, and shall keep the said obligee harmless and indemnified from and against all and every claim, demand, judgment, lien, cost and fee of every description, incurred in suits or otherwise against the said obligee, growing out of or incurred in, the prosecution of said work according to the terms of the said contract, and shall re-pay the said obligee all sums of money which the said obligee may pay to other persons on account of work and labor done or materials furnished on or for said contract, and if the said principal shall pay to the said obligee all damages or forfeitures which may be sustained by the non-performance or mal-performance on the part of the said principal of any of the covenants, conditions, stipulations and agreements of said contract,” etc.

The contract contained within itself certain specifications but there were no plans, it being provided as to plans that the contractor should furnish such as might be necessary. Neither were there any provisions for an architect nor for architect’s certificates upon which to make payments. The full contract and specifications are set forth in the declaration and are of a very simple nature. There is no provision as to any umpire, arbitrator or agent for the purpose of determining when the payments were to be made except as above indicated, and the whole agreement indicates little more than that the building shall be moved back upon a new foundation, with its necessary implication that it be done in a workmanlike manner.

The amended declaration in the case sets forth the bond and the contract, with its included specifications, in hcec verba, and alleges various breaches of the contract. It is set forth that about September 1, 1930, the plaintiff was informed by the contractor that the rear of the building had been excavated as required, the necessary new footings built in preparatory to moving and the necessary holes cut for loading of the building, and that he thereupon paid the contractor $1000. It is further alleged that about the 20th of September the contractor informed the plaintiff that the building had been moved to its new location, and that he thereupon made the payment of $3000 required; that on October 8, 1930, he was informed by the contractor that the water and plumbing had been taken care of as provided in the contract, and that he thereupon paid the further sum of $1000 to the contractor. It is further alleged that after the plaintiff had made these payments, totaling $5000 in all, he discovered for the first time that the preceding work had not been done according to the specifications, and that he thereupon prohibited the contractor from doing any further work and engaged another to complete it. It is alleged that it cost him $3666.22 to pay the second contractor to complete the work, and that it was not completed until sixty-seven days beyond the time when the first contractor agreed to finish it, whereby certain liquidated damages had accrued, making the total amount sought to be recovered $4871.22. Numerous specific breaches of the contract are set forth in the amended declaration, a detailed statement of which is not necessary to an understanding of the case nor to the present opinion.

A demurrer was interposed by the defendant, the United States Fidelity and Guaranty Company, which was sustained in the superior court. The plaintiff elected to stand by his amended declaration and appealed to the Appellate Court for the First District, where the judgment of the superior court was affirmed. The cause is brought before this court for review upon writ of certiorari.

The contentions of the defendant which were allowed to prevail in the trial and Appellate Courts were based upon a theory that no damages could be recovered by the plaintiff except such as might be deducted from any unpaid portion of the contract price and upon certain language used by this court in Finney v. Condon, 86 Ill. 78. It was there stated, in connection with the facts in that particular case, that the reserved per cent on a building contract is provided as much for the indemnity of the surety as for the owner’s protection; that equitably the surety is entitled to have the sum retained for his benefit, and that if the principal releases it without the consent of the surety the surety will be discharged. In that case, however, there was a finding that the payments had been properly made upon architect’s certificates, and that although relatively they were in excess of what they ought to have been in relation to the full contract price, they were not necessarily in excess of eighty-five per cent of the work and materials actually performed and furnished, it being apparent that the contract had been taken too low. It thus appears that, notwithstanding any language used in that opinion, the case is not in point on the facts now before us and not necessarily controlling in this one. It remains for us to inquire whether the judgments arrived at are in consonance with the rules laid down by us in other cases which appear not to have been considered by the trial and Appellate Courts.

It is first contended by the defendant that a surety is a favorite of the law and is not to be held liable beyond his express engagement. Such cases as Ryan v. Trustees of Shawneetown, 14 Ill. 20, and others to the same effect, are cited, and with this general statement of an old rule we find no fault, except for the necessity of pointing out a certain exception to it. Since the advent of corporate sureties for hire it has been necessary to make a distinction between the gratuitous and paid surety, and this distinction has been recognized in this court. (Gunsul v. American Surety Co. 308 Ill.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fisher v. Fidelity & Deposit Co.
466 N.E.2d 332 (Appellate Court of Illinois, 1984)
Metropolitan Sanitary District v. Anthony Pontarelli & Sons, Inc.
288 N.E.2d 905 (Appellate Court of Illinois, 1972)
Sanitary District v. United States Fidelity & Guaranty Co.
61 N.E.2d 286 (Appellate Court of Illinois, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
197 N.E. 765, 361 Ill. 206, Counsel Stack Legal Research, https://law.counselstack.com/opinion/turk-v-united-states-fidelity-guaranty-co-ill-1935.