Sanitary District v. United States Fidelity & Guaranty Co.

61 N.E.2d 286, 326 Ill. App. 163, 1945 Ill. App. LEXIS 332
CourtAppellate Court of Illinois
DecidedMay 18, 1945
DocketGen. No. 43,021
StatusPublished

This text of 61 N.E.2d 286 (Sanitary District v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sanitary District v. United States Fidelity & Guaranty Co., 61 N.E.2d 286, 326 Ill. App. 163, 1945 Ill. App. LEXIS 332 (Ill. Ct. App. 1945).

Opinion

Mr. Justice Kiley

delivered the opinion of the court.

This is an action against the surety on a contractor’s bond wherein plaintiff recovered the amounts of judgments against it based on suits for damages arising out of a sewer improvement. Defendant has appealed.

February 20, 1936, McKay Engineering and Construction Company entered into a contract with plaintiff under which the Company agreed to build a sewer in Berwyn, Illinois. The contract required a surety bond which defendant executed on the day of the contract. The City of Berwyn authorized the improvement and plaintiff completed the work according to contract, with some modification, June 1, 1937. November 19,1937 suit was commenced by several owners of property in Berwyn for damages to their property, resulting from the construction work and judgments totaling $16,496.77 were entered against the Sanitary District. These judgments were paid by the District and after demand upon defendant for reimbursement was refused, this suit was started.

Defendant contends it is not bound on its bond except for judgments based on the Company’s negligence. Plaintiff answers that by its bond defendant agreed to pay all judgments in “consequence of the awarding of the construction contract,” and to be concluded by judgments in any suits for damages to property arising out of the improvement. There is no dispute on evidence and a question of law is involved whether the defendant surety is obliged by the bond to reimburse the District. The trial court denied defendant’s motion, at the close of plaintiff’s case and at the close of the entire case, for a finding in its favor on the question of law. In deciding the case the trial court said that there was a finding in the property damage judgment that the Company was negligent, and that that judgment was conclusive against defendant under the terms of its bond.

Plaintiff had the burden of showing that the judgment came within the terms of the bond and it relies upon the language of the instruments involved. Determination of the question requires construction of the bond. Plaintiff contends the bond must be construed in its favor and relies for support upon Gunsul v. American Surety Co., 308 Ill. 312, which points out the distinction between individual and corporate sureties, but cannot be said to support plaintiff’s contention. Allowing for the rule of construction that ambiguities are resolved against the one who drafts an instrument, we believe the language of the instruments here should not be strained to enlarge or restrict the fair meaning of the language used. Turk v. United States Fidelity Co., 361 Ill. 206; Galesburg Sanitary District v. American Surety Co., 308 Ill. App. 457. The contract between plaintiff and McKay, etc. required, pursuant to Chap. 29, Par. 15, Ill. Rev. Stats. [Jones Ill. Stats. Ann. 126.320], a bond for half the amount of the contract guaranteeing the faithful performance of all the terms and conditions of the contract, and a separate bond guaranteeing the prompt payment for labor and services. The performance bond in the amount of $557,985.00 provided that .any obligations thereunder should be void if the Company performed the contract according to its terms, specifications and plans; if it protected and indemnified the Sanitary District against all judgments in consequence of the awarding of the contract or arising out of the negligence of the Company; and if it performed other conditions not pertinent here. The first condition recited, clearly refers to the actual construction work and was fulfilled according to the District’s approval of its chief engineer’s communication that the work was completed satisfactorily June 1,1937. The second condition is vital. The final paragraph of the bond provides that it is expressly understood that any judgment against the Sanitary District in any suits for damages for injury to real or personal property or to persons arising out of any act or doing of the Company or its employees, should be conclusive against each and all of the parties to the obligation as to liability, amount, etc. In that paragraph also defendant agreed to be concluded as to amount of liability, etc., by any judgment “as aforesaid in any suits for damages for injury to real . . . property . . . growing out of any act or doing” of the Company or its employees. We agree with defendant that the last paragraph of the bond does not purport to recite the extent of defendant’s liability, but simply to preclude defendant from attacking judgments against the District coming within the terms of the bond. The words, “as aforesaid” are words of limitation of the judgments -by which defendant was to be concluded, and refer to judgments expressed in the vital condition above mentioned, those in consequence of the awarding of the contract and those resulting from the carelessness or negligence of the Company. A further description of the judgments in the final paragraph of the bond is that they shall be entered in suits for damages for injury to real property, etc. growing out of any act or doing of the Company. This further description is helpful for it enables us .to better understand which class of judgments mentioned, in the vital condition, the term “as aforesaid” refers to.

If a judgment of the kind entered against the District and the basis of this proceeding can be said to be in consequence of the awarding “of the contract,” it can only be so because the words “in consequence of” are used to describe not only liabilities arising out of the contract transaction, but also arising out of everything that follows the awarding of the contract and winding up of the improvement. If the words are so used then the words describing the alternative liability arising from the carelessness or neglect of the Company are surplusage. We should, however, give effect to all the words if that can be reasonably done. We believe that the limitation, in the last paragraph of the bond, of the judgments to those in “suits for damages for injury to real . . . property growing . . . out of,” etc., refers to the second class of liabilities described in the bond proper arising from the negligence of the Company. Furthermore, we believe that that class of liabilities includes and is coextensive with the agreement in the contract to pay all damages “for injury to real . . . property . . . growing out of any act or doing of the contractor . . . that is in¿> the nature of a legal liability.” We believe that this construction is consistent with precedent in this court. In Maezes v. City oChicago, 316 Ill. App. 464, construing a similar provision of a contract to determine the liability of the contractor thereunder, we held that where the contractor exercised due care and skill in doing the work he was not liable to pay the damages and that the construction work was not its “act or deed,” but that of the District. In Euwema Co. v. McKay Eng. & Const. Co., 316 Ill. App. 650, we also held that the liability of the contractor was limited to injuries caused by its negligence.

The plaintiff argues here that the judgment in favor of Berwyn property owners against the District is conclusive on the defendant because a finding in it attributed the damages to the acts of the Company, and moreover, that defendant was requested to defend that action in behalf of the District. It is true that the defendant was requested to make the defense and refused to do so. Its refusal was based upon its position that the action was not one covered by its bond and it took the risk of the consequences of its refusal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Turk v. United States Fidelity & Guaranty Co.
197 N.E. 765 (Illinois Supreme Court, 1935)
Nelson v. McKenzie-hague Co.
256 N.W. 96 (Supreme Court of Minnesota, 1934)
De Baker v. Southern California Railway
39 P. 610 (California Supreme Court, 1895)
City of Joliet v. Harwood
86 Ill. 110 (Illinois Supreme Court, 1877)
City of Chicago v. Murdock
212 Ill. 9 (Illinois Supreme Court, 1904)
Gunsul v. American Surety Co.
139 N.E. 620 (Illinois Supreme Court, 1923)
Galesburg Sanitary District v. American Surety Co. of New York
32 N.E.2d 407 (Appellate Court of Illinois, 1941)
Maezes v. City of Chicago
45 N.E.2d 521 (Appellate Court of Illinois, 1942)
Euwema Co. v. McKay Engineering & Construction Co.
45 N.E.2d 555 (Appellate Court of Illinois, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
61 N.E.2d 286, 326 Ill. App. 163, 1945 Ill. App. LEXIS 332, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sanitary-district-v-united-states-fidelity-guaranty-co-illappct-1945.