Village Commons, LLC v. Marion County Prosecutor's Office

882 N.E.2d 210, 2008 Ind. App. LEXIS 374, 2008 WL 565311
CourtIndiana Court of Appeals
DecidedMarch 4, 2008
Docket49A05-0704-CV-195
StatusPublished
Cited by12 cases

This text of 882 N.E.2d 210 (Village Commons, LLC v. Marion County Prosecutor's Office) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Village Commons, LLC v. Marion County Prosecutor's Office, 882 N.E.2d 210, 2008 Ind. App. LEXIS 374, 2008 WL 565311 (Ind. Ct. App. 2008).

Opinion

*212 OPINION

RILEY, Judge.

STATEMENT OF THE CASE

Appellants-Plaintiffs, Village Commons, LLC and Rynalco, Inc. (collectively, Landlord), appeals the trial court’s judgment in favor of the Appellees-Defendants, Marion County Prosecutor’s Office and Carl Briz-zi, in his official capacity as Marion County Prosecutor (collectively, MCPO).

We affirm.

ISSUES

Landlord raises three issues for our review, which we restate as:

(1) Whether the exclusive-remedy provision of the lease between Landlord and the MCPO barred the MCPO from asserting that it was evicted by acts or omissions of the Landlord;
(2) Whether the trial court’s findings that the MCPO was both actually evicted and constructively evicted were clearly erroneous; and
(3) Whether a provision limiting the MCPO’s time to sue barred the MCPO’s defenses and counterclaims.

FACTS AND PROCEDURAL HISTORY

On June 2, 1999, then Marion County Prosecutor Scott C. Newman, executed a lease on behalf of the MCPO with Lombard Associate Limited Partnership (Lombard) to lease the basement of the Victoria Centre in Indianapolis, Indiana (the Lease). Sometime thereafter, Lombard sold the Victoria Centre to Landlord and assigned the Lease to Landlord. The MCPO’s Grand Jury Division used the leased premises as its office and evidence storage space.

Pursuant to the provisions of the Lease, the MCPO was to rent 9,356 square feet of lower level space in the Victoria Centre for a period of seven years and five months, commencing on August 1, 1999. The payment obligations increased over time, beginning with zero dollars owed per month for the first five months, increasing to $8,576.33 per month for months seventy-eight through eighty-nine of the lease term.

Under the Lease provisions, Landlord was required to maintain all equipment used in common with other tenants — such as elevators, plumbing, heating and similar equipment — and to maintain the premises in good order, condition and repair. In the event of breach by Landlord, the lease provided that the MCPO could “sue for injunctive relief or to recover damages for any loss resulting from the breach, but [it] shall not be entitled to terminate this Lease or withhold, setoff or abate any rent due thereunder.” (Appellant’s Addendum to Brief, tab 1).

Beginning in 2001, there was a series of water intrusions from the outside and leaks from building equipment, which damaged property secured by the MCPO and affected the areas that the MCPO occupied or used. On March 11, 2001, there was a leak in the restroom area. On June 25, 2001, there was a leak in the MCPO’s evidence room. On August 2, 2001, there was leak in what the MCPO refers to as its war room, a room that extends out from the building underneath a sidewalk adjacent to the building. On August 16, 2001, there was leak in the electrical conduit. On August 24 and 28, 2001, Landlord took an inventory of water spots on ceiling tiles and other water damage throughout the MCPO’s leased area and noted several spots and other damage that had been caused by sweating pipes or leaks. On August 28 and September 10, 2001, leaks were again noted in the war room, which were either caused by cracks in the side *213 walk or steam from Indianapolis Power and Light’s underground pipes.

As a result of repeated water intrusions in the war room, Landlord hired Indoor Air Management (IAM) to conduct microbiological sampling and visual inspections. IAM reported visual signs of water damage in the war room and along dry wall. Landlord caulked and sprayed sealant on the sidewalk above the ;war room on several occasions, but these actions did not stop the leaking. The drywall was scheduled to be repaired, but another leak delayed the work. Landlord sought an estimate to remove and re-pour the concrete sidewalk above the war room on October 11, 2001. However, Landlord elected not to perform this work due to the estimated costs.

Another leak was discovered outside of an office on January 22, 2002, and was noticeably worse on January 29, 2002. On Memorial Day 2002, the main water supply pipe in the building’s air conditioning system broke causing a leak in the evidence room. Approximately seventy boxes of evidence were damaged. The MCPO had to dedicate .several person-hours to attend to the damaged evidence. On June 10, 2002, Mold Remediation Services (MRS) inspected the damaged evidence room and detected mold spores. MRS provided Landlord a quoted price for recommended work to address the microbial contamination. However, due to the estimated cost of the remediation services, Landlord did not hire MRS, but rather permitted its maintenance man to perform demolition and replace drywall. Landlord’s maintenance man did not perform several of the tasks recommended by MRS.

On July 17, 2002, nearly one year after the original leak in the war room, Landlord’s maintenance man again replaced ceiling tiles that showed signs of water damage. On July 19, 2002, IAM performed microbiological testing in the main evidence room, hallway, conference room and office of the Chief Deputy Prosecutor of the Grand Jury Division, Mark Holl-ingsworth (Hollingsworth). IAM informed the MCPO that additional demolition was necessary and that the boxes that were damaged should be discarded because of microbiological contamination.

On July 81, 2002, a new leak caused by the HVAC system was discovered in the break room. On- August 2, 2002, IAM reported that moisture readings collected from drywall in the closet area were elevated. A wall in the war room had visible signs of water damage. Also, different types of mold spores were present inside the premises than those found outdoors. Surface testing reported excessive fungal growth. IAM recommended several actions to deal with the moisture and microbiological problems, many of which were previously recommended by MRS.

Landlord spoke with IAM and was advised regarding'the possibility of allergic reactions for certain people to mold contamination. However, after this meeting Landlord advised the MCPO there were no health risks presented by the building conditions. At least one of the MCPO employees complained of suffering from unusual coughing and sneezing for a prolonged period of time. Another of the MCPO employees experienced headaches while working at the leased premises. The employee reported his symptoms to a physician, was reassigned outside of the leased premises,.and the symptoms subsided. On August 13, 2002, Landlord and the MCPO met with an IAM employee to discuss IAM’s report. IAM’s employee explained to the MCPO there was an elevated mold count, but not the type of mold that requires a building to be quarantined.

On October 10, 2002, Hollingsworth instructed an employee to make daily inspections. The employee reported to *214 Hollingsworth that there were moisture problems in three of the four rooms the MCPO Grand Jury Division used to store evidence. Landlord sent a letter to the MCPO on October 14, 2002, suggesting the MCPO move evidence that it was storing and other materials away from parts of the premises that were vulnerable to water damage.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

James R. Sapp v. Flagstar Bank, FSB
12 N.E.3d 913 (Indiana Court of Appeals, 2014)
Roche Diagnostics Operations, Inc. v. Marsh Supermarkets, LLC
987 N.E.2d 72 (Indiana Court of Appeals, 2013)
MNW, LLC v. Mega Auto Group, Inc.
884 F. Supp. 2d 740 (N.D. Indiana, 2012)
Sengul v. CMS Franklin, Inc.
265 P.3d 320 (Alaska Supreme Court, 2011)
Murat Temple Ass'n v. Live Nation Worldwide, Inc.
953 N.E.2d 1125 (Indiana Court of Appeals, 2011)
Chiprean v. Brody & Lacy Stock
925 N.E.2d 489 (Indiana Court of Appeals, 2010)
Sunburst Chemical, LLC v. Acorn Distributors, Inc.
922 N.E.2d 652 (Indiana Court of Appeals, 2010)
Stewart v. TT COMMERCIAL ONE, LLC
911 N.E.2d 51 (Indiana Court of Appeals, 2009)
Balvich v. Spicer
894 N.E.2d 235 (Indiana Court of Appeals, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
882 N.E.2d 210, 2008 Ind. App. LEXIS 374, 2008 WL 565311, Counsel Stack Legal Research, https://law.counselstack.com/opinion/village-commons-llc-v-marion-county-prosecutors-office-indctapp-2008.