Viliski v. City of Minneapolis

3 L.R.A. 831, 41 N.W. 1050, 40 Minn. 304, 1889 Minn. LEXIS 83
CourtSupreme Court of Minnesota
DecidedMarch 22, 1889
StatusPublished
Cited by14 cases

This text of 3 L.R.A. 831 (Viliski v. City of Minneapolis) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Viliski v. City of Minneapolis, 3 L.R.A. 831, 41 N.W. 1050, 40 Minn. 304, 1889 Minn. LEXIS 83 (Mich. 1889).

Opinion

Dickinson, J.

This action is for the recovery of the value of a large quantity of stone, quarried by one Patterson from Thirteenth [305]*305avenue, between Third and Fifth streets, in the city of Minneapolis, and appropriated by Patterson to his own use. The fee of the land where the stone in question was quarried was, with the fee of the adjacent lots, in the plaintiff and in certain other persons, who have assigned to him their causes of action for the acts complained of. The acts of Patterson here in question were done pursuant to a contract between him and the city, the body of which is set forth in the complaint, and the making of which is admitted. The time for the performance of this contract by Patterson appears by the complaint to have been subsequently extended, by the mutual consent and agreement of the contracting parties, to November, 1887. This is also, as we construe the answer, admitted. The acts complained of were done prior to that date. The written contract of the city with Patterson in -terms permitted the latter to excavate, have, and carry away all the rock in Thirteenth avenue between the other streets above named; in consideration of which permit Patterson agreed to excavate and carry away all the rock, as before designated, and, after the rock had been excavated, and as the work should progress, to construct with such rock a covered stone drain through the avenue, within the same limits, and also to refill the avenue to the original grade of the same. The agreement further stated that the same was made on the part of the city for the purpose of grading this avenue, and of causing the removal, at the least expense to the city, of the material necessary to be removed in such grading; and that Patterson should have no compensation, except the right to use and dispose of as he might see fit any surplus rock so excavated and not needed for the drain.

It appeared upon the trial of the cause that the grade of this avenue had never been established by the city council, there having been established only what is termed a “preliminary grade” by the city engineer, for the purpose of carrying on public improvements; that the rock which is the subject of this action had been taken from below this temporary grade; that the ledge thus excavated and removed was, in depth, from the surface of the soil, some nine or ten feet; that (as appears from the testimony of Patterson that he fulfilled the contract) all the rock in the street to that depth, and to the whole [306]*306width of the street, was taken out, and so much of it as was not required for the sewer was used by Patterson for his own purposes; and that the excavation was then refilled to within about two feet of the original surface of the ground, as directed by the city engineer.

We think that it appears conclusively from the case that the removal of this stone was not for the purpose of grading this street; for the contract provided for refilling by the contractor after all the stone should be removed, as was in fact done, although the excavation was not refilled quite to the original level. It view of what was by the terms of the contract to be done, the statement embodied in it as to the reasons or purposes in view cannot be here accepted as showing that the grading of this street was one of the purposes for which the stone was to be removed. We consider, also, that the conclusion is to be drawn from the case that the rock was excavated the whole width of the street, not because that was necessary in order to construct the sewer at the proper level, but because the city could thus secure the construetien of the sewer without expense, the contractor being compensated for doing the work by the large quantity of stone thus secured for his own use. The right of the city to dispose of the stone in the manner above indicated and the measure of the plaintiff’s damages 'are the principal questions involved in this case. We have not-hitherto been required to determine such questions, under the circumstances here presented.

In considering the principles to be applied in the determination of the case, a distinction is to be observed, depending upon the fact as to whether the excavation and removal of the material in question is reasonably necessary on the part of the city for purposes properly connected with the public easement, or, not being of that character, is to be deemed an unjustifiable invasion of the rights of the owner of the soil. Accordingly we separate the subject of this action into two parts, and will first consider the case with regard to so much of the stone in question as was not reasonably necessary to be quarried for the purposes of the construction of the sewer.

As has already been intimated, the case does hot show a justification for the quarrying of the .stone through the whole width of the street, and far below the surface. It was not necessary for the grad[307]*307ing of the street, for no grade had been established different from the natural surface of the ground, nor is it claimed to be even probable that any other grade will ever be required. The case does not call for a consideration of the question as to whether the city might not excavate to a greater width than was necessary for present purposes, in anticipation of future improvements rendering that necessary. The ease discloses no other purpose, either present or prospective, than the construction of this sewer. The claim that this was the most economical way for the city to secure the construction of the sewer ignores the rights of the owner of the soil. The acquisition of the easement does not include a right on the part of the public to use or dispose of the material found within the lateral limits of the street, except so far as may be reasonably necessary for the full enjoyment of the easement, or properly incident thereto. The quarrying and disposal of stone from below the street grade, the same not being necessary for purposes connected with the use or improvement of the street, is not included within the rights acquired by the city when a street is established over the land of an individual, and he has a right of action therefor. Rich v. City of Minneapolis, 37 Minn. 423, (35 N. W. Rep. 2;) Althen v. Kelly, 32 Minn. 280, (20 N. W. Rep. 188.) It may be that if the city had not thus appropriated the stone in question to compensate the contractor for constructing the sewer, and if only so much stone had been removed as was reasonably necessary for putting in the sewer, a considerable expense would have been incurred, which might have been chargeable upon the adjacent property by special assessment. This probably would have been authorized by provisions of the charter prescribed for such purposes. Eut the fact that the necessity for a legally-authorized assessment has been avoided by the course pursued by the city is no justification. It had no power to summarily, and without statutory authority or legal proceedings, seize the property of the owner of the soil, whether upon his private premises or within the limits of the street, and appropriate it to the payment of the expense of constructing the sewer, nor could it authorize such an appropriation by another. Hence, as to so much of the stone in controversy as it was not reasonably necessary to disturb for the purposes of the improvement [308]*308undertaken, — the construction of the sewer, — the plaintiff had a right of action, unless it had been voluntarily relinquished.

The proper measure of damages should be distinctly settled, so far as seems necessary for the purposes of this case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yuba County Water Agency v. Ingersoll
45 Cal. App. 3d 452 (California Court of Appeal, 1975)
Campbell v. Monaco Coal Mining Co.
85 N.E.2d 138 (Belmont County Court of Common Pleas, 1948)
Carter Oil Co. v. Myers
105 F.2d 259 (Seventh Circuit, 1939)
City of St. Paul v. Bielenberg
204 N.W. 544 (Supreme Court of Minnesota, 1925)
Pearson v. Twohy Bros.
231 P. 129 (Oregon Supreme Court, 1924)
Town of Rost v. O'Connor
176 N.W. 166 (Supreme Court of Minnesota, 1920)
Ashurst v. Lohoefner
156 S.W. 805 (Missouri Court of Appeals, 1913)
Lawler v. Brennan
134 N.W. 154 (Wisconsin Supreme Court, 1912)
Town of Glencoe v. Reed
67 L.R.A. 901 (Supreme Court of Minnesota, 1904)
District of Columbia v. Robinson
14 App. D.C. 512 (D.C. Circuit, 1899)
Haas v. City of Evansville
50 N.E. 46 (Indiana Court of Appeals, 1898)
Anderson v. Bement
41 N.E. 547 (Indiana Court of Appeals, 1895)
Andrews v. Youmans
47 N.W. 304 (Wisconsin Supreme Court, 1890)

Cite This Page — Counsel Stack

Bluebook (online)
3 L.R.A. 831, 41 N.W. 1050, 40 Minn. 304, 1889 Minn. LEXIS 83, Counsel Stack Legal Research, https://law.counselstack.com/opinion/viliski-v-city-of-minneapolis-minn-1889.