Vilbig Const. Co. v. Whitham

1948 OK 272, 201 P.2d 922, 201 Okla. 86, 1948 Okla. LEXIS 539
CourtSupreme Court of Oklahoma
DecidedDecember 14, 1948
DocketNo. 32055
StatusPublished
Cited by18 cases

This text of 1948 OK 272 (Vilbig Const. Co. v. Whitham) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vilbig Const. Co. v. Whitham, 1948 OK 272, 201 P.2d 922, 201 Okla. 86, 1948 Okla. LEXIS 539 (Okla. 1948).

Opinions

PER CURIAM.

This action was brought by L. E. Whitham against Vil-big Construction Company, a corporation, and J. Lee & E. A. Vilbig, Inc., a corporation, for an accounting and the appointment of a receiver in connection with and arising out of the paving of Tillman Air Field near Frederick, Okla. At the beginning of the action the trial court appointed a receiver, and its action was by the defendants appealed to this court, which, in an opinion reported in 194 Okla. 460, 152 P. 2d 916, sustained the action of the trial court. The essential facts are stated in that opinion, and will not be restated here.

After the appointment of the receiver had been sustained by this court, defendants filed their answer and cross-petition, and when the case came on for trial demanded a jury trial. The trial court denied a trial by jury, holding that the case was an accounting in equity; took an account between the parties; made very complete findings of fact, and rendered judgment for plaintiff. The trial court decreed that to the sum of $154,948.90, claimed by defendants to be the net profits arising from the paving operation aforesaid, there should be added the additional amount of $67,929.73, making a total profit of $222,878.63; that under the contract between the parties defendants were entitled to the sum of $93,-467.35, and that the remainder, in the sum of $129,411.28 belonged to plaintiff, and decreed the payment of such amount to him. From this judgment defendants appeal, and plaintiff cross-appeals as to certain items. These contentions will be disposed of together.

Defendants make three contentions going to the entire controversy, which may properly be disposed of before [88]*88taking up the accounting feature of the case. The first of these general propositions is that the action is an action at law for damages, and that the trial court erred in refusing the defendants a jury trial and in treating the case as an accounting in equity. In connection with this contention they assert that the arrangement between the parties was not a joint venture, but that plaintiff was a superintendent for the defendants.

In Vilbig Construction Co. v. Whitham, supra, we held that under the contract between plaintiff and defendants the relationship between them was that of joint adventurers; that the relation was fiduciary in character and required the utmost good faith on the part of both parties, and that the rights and liabilities as between them were similar to those of partners. The defendants admittedly were dirt grading contractors, having little or no experience in the laying of concrete pavement, and as such had a contract with the government for doing the dirt grading at the Tillman Air Field, which was preliminary to the laying of the pavement. The action by plaintiff was predicated upon the theory that after his discharge by defendants, the defendants charged against the paving operation numerous expenses which should have been borne by them under the grading contract, and that in constructing the pavement they incurred a great amount of unnecessary expense. He further charged that the action of defendants in discharging plaintiff was for the fraudulent purpose of reducing the net profit to be derived from the paving operation so as to prevent a reduction of their profits if the contract was renegotiated by the government, in which event, under the contract between the plaintiff and defendants, defendants would have borne a portion of any resulting loss. The complexity of the accounts and the number of items involved in the contentions of the parties, coupled with the fiduciary relationship which existed between them, was, in our judgment, sufficient to justify the holding of the trial court that the action was equitable and that it would be impracticable if not impossible to try the cause to a jury. Also, it appears that a considerable part of the evidence required by plaintiff to establish his contentions was in the hands of defendants.

In 1 C. J. 613 and in 1 C. J. S. 645, the essentials of equitable jurisdiction in an action on account are said to be the need of a discovery, the complicated character of the accounts, and the existence of a fiduciary or trust relation. All three of these essentials inhered in the instant case. The trial court did not err in treating the matter as equitable and refusing the defendants’ request for a jury trial. Templeman v. Walker, 175 Okla. 366, 52 P. 2d 737.

Defendants next contend that the trial court erred in overruling their demurrer and in not dismissing plaintiffs complaint for the reason that it did not allege a previous demand for an accounting and a refusal thereof by defendants, citing in support of this contention Wiegardt v. Becken, 10 Wash. 2d 182, 118 P. 2d 182, 143 A. L. R. 1208.

It appears that the action was brought pending a renegotiation of the contract between defendants and the United States Government, so that at the time of the bringing of the action a demand, if made, could not have been complied with. It further appears that the accounts were very complicated and that the items thereof were bitterly disputed by the parties, and that if a demand had been made by plaintiff there could have been no satisfactory adjustment of the accounts between them. Under these circumstances we think the trial court correctly held that the express allegation of a demand and refusal in the petition was not necessary. 1 C. J. 627; 1 C. J. S. 660, §28.

Defendants next contend that the trial court erred in refusing to cancel the contract between them and plaintiff, which relief they sought in their answer [89]*89and cross-petition, and assert that the evidence adduced clearly shows that such relief should have been granted to them.

In this connection they point out that under their contract plaintiff agreed to> furnish all the equipment and. experienced personnel necessary for the completion of the joint venture, and to give the project proper supervision. They assert that he wholly failed to do these things, and that they had the right, under said contract, to take active charge of the supervision and control of the work and the men, materials, tools and equipment furnished by plaintiff, in the event plaintiff should for any reason refuse, neglect or fail to efficiently prosecute the work to completion.

The evidence shows that immediately upon the execution by plaintiff of the contract between plaintiff and defendants, plaintiff went to Frederick and began the preparatory work necessary to the performance of the contract before the actual laying of the pavement could be commenced; that before he signed the contract he had discussed with J. Lee Vilbig, vice president of the Vilbig Construction Company, and president of J. Lee & E. A. Vilbig, Inc., the amount of equipment necessary, including that owned by him which he could place upon the job, and that which could be obtained by renting the same from the government or procuring it from dealers by purchase agreements; that they had also discussed the question of where gravel, sand and stone could be procured, and had agreed that plaintiff and one Theo. Montgomery, with whom plaintiff was associated, should establish a plant for the production of sand and gravel at a point near the Air Field, and that plaintiff should erect a crusher to prepare such gravel for use; that they had also agreed that a railroad spur should be constructed for the unloading of stone and other material and equipment which might be shipped to the job and had, in fact, agreed upon all the preliminary work to be done in order to be ready to do the actual laying of the pavement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Margaret Blair Trust v. Blair
2016 OK CIV APP 47 (Court of Civil Appeals of Oklahoma, 2016)
Thielenhaus v. Thielenhaus
890 P.2d 925 (Supreme Court of Oklahoma, 1995)
Bd. of Public Works City of Hammond v. L. Cosby Bernard, Co.
528 N.E.2d 93 (Indiana Court of Appeals, 1988)
Chandler-Frates & Reitz v. Kostich
1981 OK 74 (Supreme Court of Oklahoma, 1981)
Mills v. Mills
1973 OK 74 (Supreme Court of Oklahoma, 1973)
Missouri-Kansas-Texas Railroad Co. v. Edwards
1961 OK 192 (Supreme Court of Oklahoma, 1961)
Daisy D. Blankenship v. Maxwell Rowntree
238 F.2d 500 (Tenth Circuit, 1956)
Ottinger v. United States
230 F.2d 405 (Tenth Circuit, 1956)
M. E. Trapp Associated v. Tankersley
1951 OK 221 (Supreme Court of Oklahoma, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
1948 OK 272, 201 P.2d 922, 201 Okla. 86, 1948 Okla. LEXIS 539, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vilbig-const-co-v-whitham-okla-1948.