Vilbig Const. Co. v. Whitham

1944 OK 259, 152 P.2d 916, 194 Okla. 460, 1944 Okla. LEXIS 499
CourtSupreme Court of Oklahoma
DecidedSeptember 26, 1944
DocketNo. 31398.
StatusPublished
Cited by13 cases

This text of 1944 OK 259 (Vilbig Const. Co. v. Whitham) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vilbig Const. Co. v. Whitham, 1944 OK 259, 152 P.2d 916, 194 Okla. 460, 1944 Okla. LEXIS 499 (Okla. 1944).

Opinion

HURST, J.

The plaintiffs in error, defendants below, Vilbig Construction Company, a corporation, and J. Lee and E. A. Vilbig, Inc., a corporation, appeal from an order denying a motion to vacate the appointment of a receiver pen-dente lite for certain jointly owned properties in possession of said defendants and acquired in connection with a construction project in which the plaintiff and defendants were jointly interested.

The defendants are affiliated corporations, having their offices at Dallas, Tex., and are engaged in the construction business, their principal business being grading and paving highways and streets. The plaintiff,. L. E. Whitham, who resides at Wichita Falls, Tex., is also engaged in the construction business, his principal business being paving highways and streets.

In'July, 1942, the United States Government was contemplating building Tillman Air Field near Frederick, Okla., and the plaintiff and the defendants .entered into negotiations with reference to bidding on the contract for laying approximately 704,000 square yards of paving at Tillman Air Field. It was agreed between the plaintiff and the defendants that the defendants should file a bid for the work and the plaintiff would participate in the contract and would assemble the equipment and personnel necessary to perform the work and superintend the carrying out of the contract. Accordingly, the defendants filed a bid which was accepted by the government at a contract price of $1,561,524.

The defendants entered into a contract with Theo Montgomery & Company, a sand and gravel contractor of San Angelo, Tex., to furnish the washed sand and gravel necessary for the project at a contract price of $2 per ton for the gravel and $1.80 per ton for the sand. The aggregate bill for the sand and gravel purchased and used was about $350,000 or $360,000. The plaintiff was interested with Theo Montgomery & Company in furnishing the sand and gravel and was to receive 50 per cent of the profits and stand 50 per cent of the losses incident to furnishing the sand and gravel. There is testimony, not disputed, that the defendants knew of the plaintiff’s .interest in said contract. And there is testimony that no profit was made on that contract, and the only profit which Theo Montgomery & Company may realize will be its part of the 12c per cubic yard profit on the concrete laid under the principal contract.

The profits on the paving project were to be divided as follows: The first 13c per cubic yard was to go to the defendants; the next 12c per cubic yard was to go to Theo Montgomery &' Company under the contract for furnishing the sand and gravel; and the balance of the profit, if any, was to go to the plaintiff. The plaintiff was also to receive a weekly salary of $150 as part compensation for his services in superintending the construction.

The plaintiff testified that during *462 August and September, 1942, he made all arrangements necessary to start laying the pavement; that he transported some of his own machinery to Frederick and bought and rented other necessary machinery and equipment, arranged for water and the sand and gravel, and assembled the machinery, equipment, personnel and laborers, and was prepared to start laying pavement prior to October 7, 1942.

The defendants had other construction contracts in the vicinity of Tillman Air Field, one at Chattanooga, Okla., near Frederick, a second to do the grading work preparatory to laying the pavement for Tillman Air Field, and a third for paving between barracks near the Air Field and around the gasoline storage tanks. It appears that, due' to the delay of defendants in doing the grading work, the plaintiff was unable to start laying concrete until October 7, 1942. He laid concrete a few hours each day from October 7 until October 14, 1942, when rains set in, and due to the rains and conditions of the ground he was unable to lay concrete until October 21st.

The contract between the plaintiff (second party) and the defendants (first parties) contains this clause:

“Second party agrees to oversee and supervise the performance of work governed by this contract, and to furnish all equipment and experienced personnel necessary for its completion, giving the project efficient supervision and attention, the same as if the work had been bid in his own name. It is distinctly understood, however, that first parties retain all the authority and privilege that they would have if first parties were themselves carrying out the construction, furnishing equipment, their own supervision and personnel. Should second party for any' reason refuse, neglect, or fail to efficiently prosecute the said work in accordance with the terms of this agreement, first parties in such event may take active charge of the supervision and control of said work, men, materials, tools, equipment, and supplies furnished by second party and complete the work under their own direct control, supervision, and management.”

Under the right given by this provision, the defendants, on October 21, 1942, discharged plaintiff as superintendent of the enterprise and assumed the responsibility of carrying out the contract. The plaintiff claims that said action was arbitrary and without just cause or excuse. The letter of discharge reads as follows:

“Since we do not feel that you are prosecuting the work of paving at Frederick in an efficient manner and with the speed which is required to complete the job fast enough, we wish to replace you and make changes we deem necessary. We will retain the personnel organization who wish to remain under the new supervision.
“We are appointing a superintendent of construction as of this date and are writing letters to that effect to Allied Engineering Company and the Army Captain in charge of construction.”

Some time during the month of February, 1943, the contract for laying the concrete was practically completed. On February 26, 1943, the plaintiff filed this action asking for relief in three respects, (a) for an accounting in connection with carrying out the paving contract, (b) a restraining order to prevent the removal of the property acquired by and for the joint enterprise, and, (c) the appointment of a receiver pendente lite to take charge of the jointly acquired property.

The plaintiff alleged, and introduced evidence tending to prove, that the defendants had been guilty of bad faith in several respects in an attempt to reduce plaintiff’s profit and to prevent the United States Government from re-negotiating the contract and capturing part of the profit; that they had run up the cost of the work by charging to the cost of the project large sums of money that should have been charged against defendants in connection with other and separate contracts of the defendants, in which the plaintiff was *463

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DEPT. OF SECURITIES EX REL. FAUGHT v. Blair
2010 OK 16 (Supreme Court of Oklahoma, 2010)
Oklahoma Department of Securities ex rel. Faught v. Blair
2010 OK 16 (Supreme Court of Oklahoma, 2010)
Britton v. Green
325 F.2d 377 (Tenth Circuit, 1963)
Rockett v. Ford
1958 OK 142 (Supreme Court of Oklahoma, 1958)
Vilbig Const. Co. v. Whitham
1948 OK 272 (Supreme Court of Oklahoma, 1948)
Edmonston v. Holder
1948 OK 254 (Supreme Court of Oklahoma, 1948)
United States Fidelity & Guaranty Co. v. Dawson Produce Co.
1948 OK 74 (Supreme Court of Oklahoma, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
1944 OK 259, 152 P.2d 916, 194 Okla. 460, 1944 Okla. LEXIS 499, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vilbig-const-co-v-whitham-okla-1944.