Edmonston v. Holder

1948 OK 254, 218 P.2d 905, 203 Okla. 189, 1948 Okla. LEXIS 436
CourtSupreme Court of Oklahoma
DecidedNovember 23, 1948
DocketNos. 33055, 33056
StatusPublished
Cited by10 cases

This text of 1948 OK 254 (Edmonston v. Holder) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Edmonston v. Holder, 1948 OK 254, 218 P.2d 905, 203 Okla. 189, 1948 Okla. LEXIS 436 (Okla. 1948).

Opinion

GIBSON, J.

Though separately filed and briefed the above entitled causes were consolidated for the purpose of the oral argument and same are consolidated for the purpose of review.

Incidental to the construction by the United States of the pipe line from Texas to the eastern seaboard, known as the “Big Inch”, there was created the War Emergency Pipelines, Inc., hereinafter referred to as W. E. P., which, as an agency of the Federal Government, was authorized to make contracts for the construction thereof. The W. E. P. requested bids for the construction of the pipe line on a “cost plus fixed fee” basis. Plaintiff in error Herbert A. Edmonston, then doing business as Oil States Construction Company, desiring to obtain a contract for construction of a section thereof, but realizing that he had neither sufficient [190]*190equipment, skilled personnel nor working capital to fulfill such a contract, entered into contracts with others to supply such deficiency, and it is the construction of such contracts that is involved herein.

Previous to bidding on the project Edmonston, on February 15, 1943, approached defendant in error Clyde H. Brown, who was experienced as a pipe line construction superintendent, but then retired, and by oral contract engaged his services, first, to make surveys and reports preliminary to bidding on the project and thereafter to act as superintendent of the construction in event contract was awarded and, as consideration for such service, agreed to pay said Brown a salary of $600 per month and expenses, beginning forthwith, and to pay the further sum of 1/10 of the fixed fee that would be provided in the contract with W. E. P. During the latter part of March, 1943, Edmonston was advised by W. E. P. that he had been awarded a contract to construct approximately 62 miles of the pipe line and that the usual form of contract would follow for his execution. On April 1, 1943, Edmonston entered into a written contract with defendant in error A. C. Holder, who was then actively engaged in the business of pipe line construction and had in his employ experienced personnel and welding and ditching equipment, under the terms of which the use of the entire perspnnel and equipment was acquired by Edmonston. Though not declared in the contract it was understood and agreed that Edmonston was to employ and pay the personnel for the services rendered and pay to Holder such rental for use of the equipment as was provided by the W. E. P. contract. The provision in the contract relating to the further consideration to which Holder became entitled is as follows:

“In consideration of such services, Second Party agrees to pay to First Party a sum equal to twenty per cent (20%) of any and all amount or amounts received by Second Party from the War Emergency Pipelines, Inc. as his fixed fee under the contract above referred to, said payments to be made to First Party as, if and when the same are received by Second Party from the War Emergency Pipelines, Inc.”

On April 5, 1943, Edmonston entered into written contract with plaintiff in error Frates. Thereunder Frates, who was given control and supervision of the fiscal affairs involved in the execution of the contract, obligated himself to render such assistance as necessary to raise funds up to $75,000, if need be, to finance the project, and more if necessary. And, pertinent here, is the following provisions therein:

“It is understood and agreed that nothing in this contract or in the association of the parties hereto shall be construed to create or establish a partnership between the parties hereto, but this undertaking is expressly and solely limited to the purposes herein set forth.
“First party agrees to pay to second party as consideration for services rendered by second party in accordance herewith, one-half of the net profits accruing under said contract as and when said profits accrue. It is further understood and agreed that there will be an amount of money specified in said contract which is on cost plus a fixed fee basis, from which shall be deducted twenty per cent (20%) to be paid to the welding contractor and ten per cent (10%) to be paid to the superintendent of construction, and the balance of said agreed amount in the contract as a profit item divided equally between the parties.”

Thereafter, performance of the contract with W. E. P. was begun and prosecuted to completion and the work was accepted in the fall of 1943, and the fact of performance by said Brown and said Holder of their respective contractual obligations with Edmonston is not in question. Brown was paid in full his salary and personal expenses according to contract, but was paid no part of the fixed fee which Edmonston was entitled to receive under the W. E. P. contract. Holder was paid in full for rental of his equipment and the [191]*191sum of $2,800 as credit upon the amount of the fixed fee he was entitled to under his contract.

Such was the situation when, on April 16, 1945, these actions were instituted. Each action was tried upon issues made upon a second amended petition, but since the original and first amended petitions were introduced in evidence we state the material substance thereof.

In each of the original petitions it is alleged that the relationship between Edmonston and Frates, doing business as Oil States Construction Company, is that of a partnership, and that the relationship between the plaintiff and the partnership is one of joint adventure. The first amended petition makes the First National Bank & Trust Company additional defendant, avers that Edmonston and Frates had assigned to the bank the entire fixed fee provided in the W. E. P. contract, and prays judgment against the bank as well as the other defendants for plaintiff’s portion thereof.

The second amended petitions filed in said actions, on March 5 and 6, 1946, respectively, plead the facts herein-before outlined and allege that said Edmonston and Frates, doing business as Oil States Construction Company, were partners at the time of execution of plaintiff’s contract, and that, if not partners then, they became such thereafter and succeeded to the rights and obligations of Edmonston under the contract; that soon after April 1, 1943, Edmonston and Frates assigned to said bank all moneys and credits accrued and to accrue under the W. E. P. contract including the interest in the fixed fee owing to plaintiff under his contract; that plaintiff has superior right in the funds received or to be received to extent of the amount owing; and, in addition to intermediate equitable relief, judgment is sought against the defendants and each of them for that portion of the fixed fee owing to plaintiff under his contract. There is no allegation in either second amended petition that there existed between plaintiff and defendants a joint adventure nor is there alleged therein a state of facts from which the existence of such relation could properly be inferred, and none of the allegations of the original or first amended petition are made a part thereof.

For answer the defendant bank denied generally, except to extent allegations were admitted. It admitted the contract between W. E. P. and Oil States Construction Company and that the latter assigned to the bank the funds, moneys and credits due it under the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Products Co. v. Mangless
387 F. Supp. 744 (E.D. Oklahoma, 1974)
Ford Motor Company v. Arguello
382 P.2d 886 (Wyoming Supreme Court, 1963)
Albina Engine & Machine Works, Inc. v. Abel
305 F.2d 77 (Tenth Circuit, 1962)
Seaton v. Tucker
1958 OK 108 (Supreme Court of Oklahoma, 1958)
Finance Corporation v. Modern Materials Company
1957 OK 36 (Supreme Court of Oklahoma, 1957)
Mead v. Mead
1956 OK 249 (Supreme Court of Oklahoma, 1956)
Wat Henry Pontiac, Inc. v. Pitcock
1956 OK 230 (Supreme Court of Oklahoma, 1956)
Mercury Oil Refining Company v. Richardson
1956 OK 44 (Supreme Court of Oklahoma, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
1948 OK 254, 218 P.2d 905, 203 Okla. 189, 1948 Okla. LEXIS 436, Counsel Stack Legal Research, https://law.counselstack.com/opinion/edmonston-v-holder-okla-1948.