Vermont Electric Power Co. v. Hartford Steam Boiler Inspection & Insurance

72 F. Supp. 2d 441, 53 Fed. R. Serv. 483, 1999 U.S. Dist. LEXIS 17475, 1999 WL 1021872
CourtDistrict Court, D. Vermont
DecidedOctober 22, 1999
Docket2:98-cv-00356
StatusPublished
Cited by14 cases

This text of 72 F. Supp. 2d 441 (Vermont Electric Power Co. v. Hartford Steam Boiler Inspection & Insurance) is published on Counsel Stack Legal Research, covering District Court, D. Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vermont Electric Power Co. v. Hartford Steam Boiler Inspection & Insurance, 72 F. Supp. 2d 441, 53 Fed. R. Serv. 483, 1999 U.S. Dist. LEXIS 17475, 1999 WL 1021872 (D. Vt. 1999).

Opinion

OPINION AND ORDER

SESSIONS, District Judge.

This is a lawsuit brought by Plaintiff Vermont Electric and Power Company (“VELCO”) against The Hartford Steam Boiler Inspection and Insurance Company (“Hartford”) and Continental Insurance Company (“Continental”) for breach of insurance contract. VELCO argues that the breach occurred when Defendants failed to reimburse VELCO for the cost of repair of three damaged transformers. Both Defendants moved for Summary Judgment. Plaintiff VELCO filed a cross-motion for partial Summary Judgment on liability. For the reasons that follow, Continental’s motion for summary judgment is GRANTED, Hartford’s motion for Summary Judgment is DENIED, and VELCO’s cross-motion for Partial Summary Judgment on liability is DENIED.

Factual Background

For purposes of these motions, the following facts are assumed to be true. VELCO uses a Highgate Converter Station which has three transformers of identical design. Two of these transformers operate together and one serves as a back up. The transformers were installed in August of 1985. The first transformer stopped working on August 15, 1996, due to a short circuit problem caused by overheating. In April 1997, after the return of the first transformer, VELCO sent the second transformer for inspection and repair, and it was found to have identical problems to the first. The same was done with the third (spare) transformer in October of 1997. These problems were found to have been progressively caused by continuous damage, which were allegedly the consequence of defective design.

*444 VELCO was covered by Allendale Mutual Insurance Company (“Allendale”) under an all-risk policy when the losses were discovered in 1996 and 1997. Although the total loss suffered was $8,367,371, VELCO settled with Allendale for $2,384,769. VELCO seeks to recover the difference from previous carriers Hartford and Continental. Hartford insured VELCO from August 1990 through October 1993, and Continental supplied coverage from August 1988 through August 1990.

VELCO’s asserts that its experts have concluded that the damage began at the time of installation in 1985 and was progressive and continuous throughout the periods of coverage by Hartford and Continental. Hartford and Continental refute this assertion, and, if their Summary Judgment motions are denied, seek additional discovery to pursue questions of cause and timing of the damage.

Discussion

Summary Judgment is appropriate when there is no genuine issue as to any material fact, and the moving party is entitled to a judgment as a matter of law. Fed. R.Civ.P. 56(c); Alexander & Alexander Services, Inc. v. These Certain Underwriters at Lloyd’s, London, England, 136 F.3d 82, 86 (2d Cir.1998) (citing Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986)). The movant bears the burden of showing that no genuine issue of material fact exists. Gallo v. Prudential Residential Servs., 22 F.3d 1219, 1223 (2d.Cir.1994) (citing Heyman v. Commerce & Indus. Ins. Co., 524 F.2d 1317, 1320 (2d Cir.1975)). All ambiguities must be resolved and all inferences from the facts drawn in favor of the non-moving party. Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986). In sum, “[t]he court must draw all reasonable inference in favor of the non-moving party and only grant summary judgment for the moving party if no reasonable trier of fact could find in favor of the non-moving party.” Vermont Gas Systems, Inc. v. United States Fid. & Guar. Co., 805 F.Supp. 227, 231 (D.Vt.1992) citing Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247-52, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986).

Although the complaint has not specified the grounds for jurisdiction, the Court assumes that jurisdiction of this matter is based on diversity, 28 U.S.C. § 1332(a)(1). The Court applies Vermont law to the substantive issues. See Erie R. Co. v. Tompkins, 304 U.S. 64, 78, 58 S.Ct. 817, 82 L.Ed. 1188 (1938).

I. Continental’s Motion for Summary Judgment

Continental contends that it is immune from liability on three separate grounds. First, they claim that during the time of coverage, VELCO did not suffer a “loss.” Second, they claim that Plaintiffs failed to bring suit within the two year limitation period. Third, Continental argues that even if the loss had occurred during the policy period, the type of loss Plaintiffs allege was specifically excluded from coverage in the policy language. In light of exclusionary language of the policy, the Court need not address the first two issues.

“The cardinal principle for the construction and interpretation of insurance contracts — as with all contracts — is that the intentions of the parties should control.” Newmont Mines Ltd. and Esso Resources Canada Ltd. v. Hanover Ins. Co., 784 F.2d 127, 135 (2d Cir.1986). However, ambiguous policy language often makes this a difficult task. The determination of whether language is ambiguous is a question of law resolved “by reference to the contract alone.” See O’Neil v. Retirement Plan for Salaried Employees of RKO Gen., Inc., 37 F.3d 55, 59 (2d Cir.1994), citing Burger King Corp. v. Horn & Hardart Co., 893 F.2d 525, 527 (2d Cir.1990). Language is ambiguous when “it is ‘capable of more than one meaning when viewed objectively by a reasonably intelligent person who has examined the context *445 of the entire integrated agreement.’ ” O’Neil at 59, citing Care Travel Co. v. Pan Am. World Airways, 944 F.2d 983, 988 (2d Cir.1991). When it is impossible to determine the exact meaning of an ambiguous provision, the Court should employ the rule of contra proferentmn, which construes the ambiguity against the drafter of the insurance policy. “It is a general rule of construction in Vermont that a doubtful provision in a written instrument is construed against the party responsible for drafting it.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aspen Specialty Ins. Co. v. Nucor Corp.
2025 NCBC 67 (North Carolina Business Court, 2025)
People's Trust Ins. Co. v. Garcia
263 So. 3d 231 (District Court of Appeal of Florida, 2019)
Michelle Russell & a. v. NGM Insurance Company
176 A.3d 196 (Supreme Court of New Hampshire, 2017)
Kesling v. American Family Mutual Insurance
861 F. Supp. 2d 1274 (D. Colorado, 2012)
Seed Company Limited v. Westerman
840 F. Supp. 2d 116 (District of Columbia, 2012)
Fiess v. State Farm Lloyds
202 S.W.3d 744 (Texas Supreme Court, 2006)
Swire Pacific Holdings, Inc. v. Zurich Ins. Co.
845 So. 2d 161 (Supreme Court of Florida, 2003)
Yale University v. Cigna Insurance
224 F. Supp. 2d 402 (D. Connecticut, 2002)
Port of Seattle v. Lexington Ins. Co.
48 P.3d 334 (Court of Appeals of Washington, 2002)
Port of Seattle v. Lexington Insurance
111 Wash. App. 901 (Court of Appeals of Washington, 2002)
Fonda Group, Inc. v. Lewison
162 F. Supp. 2d 292 (D. Vermont, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
72 F. Supp. 2d 441, 53 Fed. R. Serv. 483, 1999 U.S. Dist. LEXIS 17475, 1999 WL 1021872, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vermont-electric-power-co-v-hartford-steam-boiler-inspection-insurance-vtd-1999.