2026 CO 52
Veolia Water Technologies, Inc., Petitioner
v.
Antero Treatment LLC, Antero Resources Corporation, Antero Midstream Partners LP, and Antero Midstream Corporation.
No. 25SC21
Supreme Court of Colorado, En Banc
June 23, 2026
2
Certiorari to the Colorado Court of Appeals Court of Appeals
Case No. 23CA897 Judgment Affirmed en banc
3
Attorneys for Petitioner: Fox Rothschild LLP Marsha M.
Piccone Risa B. Brown Denver, Colorado Mayer Brown LLP Nicole
A. Saharsky Minh Nguyen-Dang Washington, District of Columbia
Troutman Pepper Locke LLP Misha Tseytlin Chicago, Illinois
4
Troutman
Pepper Locke LLP Ralph A. Finizio Robert A. Gallagher
Pittsburgh, Pennsylvania
Attorneys for Respondents: Marie R. Yeates Houston, Texas
Vinson & Elkins, LLP James D. Thompson, III Stephanie L.
Noble Matthew C. Hoffman Garrett T. Meisman Houston, Texas
Vinson & Elkins, LLP Michael A. Heidler Austin, Texas
Womble Bond Dickinson (US) LLP Kendra N. Beckwith Kenneth F.
Rossman, IV Denver, Colorado Davis Graham &Stubbs LLP
James R. Henderson Denver, Colorado
Attorneys for Amicus Curiae Colorado Defense Lawyers
Association: Montgomery | Amatuzio Christopher R. Reeves
Denver, Colorado Attorneys for Amicus Curiae Gregory Klass:
Berg Hill Greenleaf Ruscitti LLP Geoffrey C. Klingsporn
Boulder, Colorado
5
JUSTICE GABRIEL delivered the Opinion of the Court, in which
CHIEF JUSTICE MARQUEZ, JUSTICE BOATRIGHT, JUSTICE HOOD,
JUSTICE SAMOUR, JUSTICE BERKENKOTTER, and JUSTICE BLANCO
joined.
6
OPINION
GABRIEL, JUSTICE.
¶1
This dispute arises from a series of agreements between and
among Antero Treatment LLC, Antero Midstream Partners LP,
Antero Midstream Corporation, and Antero Resources
Corporation (collectively "Antero"), on the one
hand, and Veolia Water Technologies, Inc.
("Veolia"), on the other, that led to the design
and construction of a facility to treat wastewater from
hydraulic fracturing ("fracking") operations.
Antero asserts claims against Veolia for, among other things,
breach of contract and fraud. We granted certiorari to
consider whether the economic loss rule bars Antero's
fraud claim when, according to Veolia, the parties were in a
contractual relationship, the fraud claim sought the same
relief as Antero's contract claim, and the fraud
concerned Veolia's performance under the contract.
¶2 We now conclude that because (1) the interrelated
contracts doctrine does not apply to a series of contracts
between two parties when each contract represents a
stand-alone transaction and (2) the fraud alleged here
occurred prior to the formation of the pertinent contract
and, on the facts presented, induced Antero to sign that
contract, the economic loss rule does not bar Antero's
fraud claim in this case.
¶3
We therefore affirm the court of appeals division's
decision below, albeit on other grounds, and we remand this
case with instructions to return the case to the trial court
for a determination of the reasonable attorney fees to be
awarded to
7
Antero as the prevailing party under the pertinent
contract's fee-shifting provision.
I.
Facts and Procedural History
¶4
Antero Treatment is an indirect, wholly owned subsidiary of
Antero Midstream Corporation, a company that owns, operates,
and develops midstream energy assets for Antero Resources, a
natural resources company engaged in oil and gas extraction
and production. In the summer of 2014, Antero began
investigating alternative disposal options for wastewater
produced from its fracking operations, which it had
previously discarded by trucking the wastewater to disposal
wells, a method that was economically and environmentally
problematic. Antero approached Veolia, a company that designs
and constructs water treatment facilities, to discuss options
for the disposal of Antero's wastewater. Veolia
subsequently presented Antero with a proposal to build a
facility that would use Veolia's technology to separate
and crystallize the solids within the wastewater, creating a
waste salt that could be landfilled and leaving behind water
that was clean enough to reuse or discharge into surface
waterways.
¶5
Antero and Veolia initially agreed on a "Bench Scale
Proposal" under which Veolia would conduct a study and
preliminary engineering for such a wastewater treatment
facility. Antero paid Veolia $355,000 to conduct this Bench
Scale Study, which culminated in Veolia's issuing two
"Bench Scale Reports." Throughout this
8
study period, Veolia represented to Antero that the
facility's waste salt would be solid and stable, with
"zero liquid waste," such that the salt would be
suitable for landfill disposal. In light of these
representations, and at Veolia's suggestion, Antero
retained a consultant to design and complete a landfill
permit application. This application was based on the
information and samples that Veolia had provided regarding
the waste salt's physical characteristics.
¶6
After the Bench Scale Proposal work, Antero provided Veolia
with two "Limited Notice to Proceed" agreements
("LNTPs"), under which Antero agreed to pay Veolia
$1.5 million to conduct additional design work. Following
these exploratory agreements, and throughout the summer of
2015, Antero and Veolia negotiated the terms of what would
become the parties' Design/Build Agreement
("DBA"), under which Veolia would design and build
a turnkey water treatment facility called
"Clearwater" for Antero.
¶7
As initially envisioned, the Clearwater facility would treat
Antero's wastewater in three stages. First, a
pretreatment stage would use chemicals to remove solids and
dissolved metals from the water. Second, a thermal stage
would crystallize and separate salt from the chemically
treated water. This stage would use four sequential chambers,
or "effects," in which wastewater would be heated
and crystallized waste salt would be separated. This stage
would also use "chillers," which would consume
significant power, for cooling purposes. Finally,
9
a post-treatment stage would remove any remaining volatile
organic compounds to produce water capable of reuse in oil
and gas operations or discharge into freshwater streams. This
process would satisfy Antero's objective of producing
waste salt that could be landfilled.
¶8
In addition, because the cost of power would be passed
through to Antero, Antero made clear to Veolia that any
agreement would need to satisfy certain specified power
consumption limits.
¶9
As the parties were negotiating the DBA, Veolia became
concerned about the potential power consumption required for
the chillers used in Clearwater's crystallization
process. Veolia specifically became concerned about its
ability to satisfy Antero's power consumption
requirements. Because of these concerns, and without
notifying Antero, Veolia began to redesign Clearwater to
split the fourth effect in the second stage of treatment from
one chamber to two, to reduce the need for the
power-demanding chillers.
¶10
Thereafter, and before the parties entered into the DBA,
Veolia further discovered that it had underestimated the
chillers' daily power requirements by a significant
margin, exacerbating its power consumption concerns. Despite
determining that the facility's power consumption would
likely exceed Antero's specified maximum consumption
requirements, Veolia did not share its calculations with
Antero. Instead, it moved forward with the DBA negotiations,
10
knowing full well that its most recent calculations exceeded
Antero's requirements.
¶11
Four days after Veolia discovered this significant but
undisclosed miscalculation, the parties signed the DBA, with
Antero ultimately agreeing to pay Veolia $255,765,253 once
the facility was completed.
¶12
The DBA contained a number of requirements and provisions
that are pertinent to this case.
¶13
First, the DBA included two key operating requirements for
the Clearwater facility: (1) the DBA's waste salt and
sludge specifications required "Free Liquids—Pass,
No free liquids" and "Total Solids—no limit,
must pass paint filter test," reflecting Antero's
requirement that the waste salt be suitable for landfilling;
and (2) the facility's power consumption could not exceed
505,500 kilowatt-hour ("kWh") per day with its
chillers on or 340,000 kWh per day with the chillers off.
¶14
Second, the DBA had an integration clause, which specifically
incorporated the prior Bench Scale Proposal and LNTPs into
the DBA. This integration clause provided, in pertinent part,
"This Agreement together with each LNTP, the Benchscale
Study (excluding the confidentiality provisions contained
therein) and the Existing Confidentiality Agreements, sets
forth the entire agreement between the Parties with regard to
the subject matter of this Agreement ...."
11
¶15
Finally, the DBA included a damages cap clause that limited
Veolia's liability to sixty percent of the contract sum
for most claims but explicitly provided that this limitation
did not apply in the case of, among other things, either
party's "gross negligence, fraud or willful
misconduct." (Emphasis added.)
¶16
After the parties signed the DBA, Veolia's senior
management began developing a "plan" to
"sell" its proposed design change (i.e., splitting
the fourth effect into two separate chambers) as "a
WIN/WIN Scenario and benefit for the project." In the
course of its internal conversations, however, Veolia had
identified a significant risk that splitting the fourth
effect might compromise the waste salt's quality and
render the waste salt too unstable for Antero's landfill
plans. Veolia did not disclose this risk to Antero.
¶17
Then, just eight days after the DBA was signed, Veolia
proposed to Antero Change Order 1 to modify the original
design of Clearwater by splitting the fourth effect.
Consistent with its plan to sell this design change as a win,
Veolia presented it to Antero as "design
optimizations" and listed the proposed change's
alleged benefits. Again, however, Veolia never communicated
the potential risk that this design change posed to the waste
salt's quality. To the contrary, Veolia repeatedly
assured Antero that the salt quality would be of suitable
stability for Antero's envisioned landfill strategy.
Ultimately, having not been advised of (or having
12
been misled as to) the material facts, Antero agreed to
Change Order 1, and Veolia began constructing Clearwater.
¶18
Two years after the DBA was signed, Clearwater began treating
wastewater and producing waste salt. Consistent with the
risks that Veolia had identified internally (but did not
disclose to Antero) before Change Order 1 was signed,
Clearwater produced a "soupy salt" as a result of
the splitting of the fourth effect. This salt quality caused
a number of problems for Antero. Among other things, the salt
leaked out of transport trucks and storage buildings. In
addition, the "soupy salt" could not be landfilled
using the standard landfilling techniques and equipment that
Antero had envisioned. Rather, the salt could be landfilled
only after difficult and expensive solidification efforts
that had never been part of Antero's landfill strategy.
¶19
As a result of the issues arising from the waste salt's
quality, as well as from other mechanical, design, and
process-based failures that arose at the facility, Clearwater
never satisfied a number of the critical terms of the DBA.
Subsequently, Veolia informed Antero that the salt quality
would not improve and that it was Antero's problem.
Antero terminated the DBA the next day and eventually
"mothballed" Clearwater.
13
¶20
Antero and Veolia thereafter filed suit against one another,
and the cases were consolidated. As pertinent here, Antero
brought claims against Veolia for both breach of contract
under the DBA and for fraud.
¶21
The case proceeded to a bench trial, after which the trial
court found that, prior to the execution of the DBA, Veolia
knew that Clearwater would not meet Antero's required
power consumption guarantee, had fraudulently concealed that
fact from and intentionally failed to disclose that fact to
Antero, and had failed to disclose to Antero its plan to
split the fourth effect, all to induce Antero to execute the
DBA. The court further determined that the economic loss rule
did not bar Antero's claim for this fraudulent
inducement. In its analysis, the court noted that Colorado
case law excepts from the economic loss rule "a
defendant's pre-contractual conduct because, at that
time, there was no contract that could have subsumed
identical tort duties."
¶22
In reaching this conclusion, the trial court rejected
Veolia's assertion that under Colorado case law, the DBA
was part of a "network of contracts" between the
parties extending back to the Bench Scale Proposal and LNTPs,
such that any misrepresentations occurred during the course
of contract performance. The court distinguished the case law
on which Veolia had relied, finding that the DBA was not a
part of a network of interrelated contracts. Rather, it was
the governing
14
contract, and it was not entered into until after the
pertinent misrepresentations were made.
¶23
In light of the foregoing findings, the trial court
ultimately ordered Veolia to pay Antero $215.2 million in
damages. The court also awarded Antero attorney fees under
the DBA's fee-shifting clause, which provided, among
other things, that the prevailing party in a lawsuit arising
out of or in connection with the DBA was entitled to recover
its reasonable attorney fees.
¶24
Veolia appealed, arguing, among other things, that the trial
court had erred in finding that the economic loss rule did
not bar Antero's fraud claims. A division of the court of
appeals affirmed the trial court's judgment, but on
different grounds. Veolia Water Techs., Inc. v. Antero
Treatment LLC, 2024 COA 126, ¶¶ 2, 95, 157,
564 P.3d 1089, 1095, 1108, 1117.
¶25
In its analysis, the division determined, contrary to the
trial court, that the Bench Scale Proposal, LNTPs, and DBA
functioned as an interrelated network of contracts, such that
Veolia's misrepresentations were made after the contracts
were executed. Id. at ¶ 95, 564 P.3d at 1108.
The division further determined, however, that the economic
loss rule did not bar Antero's fraud claims because the
DBA excepted such claims in its damages cap provision and the
tort duties that Veolia had violated were independent of its
contractual duties. Id. at ¶ 107, 564 P.3d at
1110.
15
¶26
On this latter point, the division concluded that
Veolia's duty to refrain from fraudulently concealing or
misrepresenting material facts was independent of
Veolia's implied duty of good faith and fair dealing in
the allegedly interrelated contracts. Id. at ¶
98, 564 P.3d at 1109. The division reasoned that the implied
duty applies only to a party's discretionary authority to
determine certain terms of a contract. Id. at ¶
99, 564 P.3d at 1109. Here, however, Veolia had no discretion
to modify the DBA's salt quality or power consumption
guarantees. Id. at ¶¶ 100-01, 564 P.3d at
1109. Accordingly, there was no overlap in Veolia's
common law tort duty and its implied contractual duty.
Id. at ¶ 101, 564 P.3d at 1109. The division
thus affirmed, albeit on other grounds, the trial court's
determination that Antero's fraud claims were not barred
by the economic loss rule. Id. at ¶¶ 104,
107, 564 P.3d at 1110.
¶27
Veolia then petitioned this court for certiorari, and we
granted its petition.
II.
Analysis
¶28
We begin by setting forth the applicable standard of review.
We then discuss the pertinent principles of the economic loss
rule. Finally, we apply these principles to the facts before
us, ultimately concluding that Antero's fraudulent
inducement claim is not barred by the economic loss rule.
16
A.
Standard of Review
¶29
The application of the economic loss rule presents a question
of law that we review de novo. Mid-Century Ins. Co. v.
HIVE Constr., Inc., 2025 CO 17, ¶ 21, 567 P.3d 153,
158. We, however, defer to the trial court's factual
findings unless they are clearly erroneous, and we will not
overturn such factual findings unless they are unsupported by
the record. Ralph L. Wadsworth Constr. Co. v. Reg'l
Rail Partners, 2026 CO 19, ¶ 21, 587 P.3d 658, 663.
B.
The Economic Loss Rule
¶30
The economic loss rule developed to maintain the boundary
between contract and tort law. Town of Alma v. AZCO
Constr., Inc., 10 P.3d 1256, 1259 (Colo. 2000). Under
the rule, a party that suffers only economic loss from the
breach of an express or implied contractual duty may not
assert a tort claim for that breach absent an independent
duty of care under tort law. Id. at 1264. The rule
thus serves to enforce the expectancy interests created by
the parties' contractual promises so that the parties may
allocate risks and costs during bargaining, and it ensures
predictability in commercial transactions. Id. at
1262.
¶31
To determine whether the economic loss rule applies, courts
look not to the nature of the damages but to the source of
the duty allegedly breached, i.e., the contract or some other
source. Mid-Century Ins., ¶ 24, 567 P.3d at
158. To do so, courts consider whether (1) the relief sought
in tort is the same as the contractual
17
relief; (2) there exists a recognized common law duty of care
in tort; and (3) the tort and contractual duties differ in
any way. Id. at ¶ 25, 567 P.3d at 158. "If
the parties have memorialized the applicable duty of care in
their contract (i.e., if the duty is contained within or
imposed under the contract), then no duty exists independent
of the contract, and the economic loss rule will apply to bar
a tort claim." Id. If, however, a recognized
common law tort duty exists independent of any contractual
obligations, then the economic loss rule does not apply and
does not bar a tort claim asserting a violation of that
independent duty of care. See Town of Alma, 10 P.3d
at 1263.
¶32
Applying these principles, we concluded in Van Rees v.
Unleaded Software, Inc., 2016 CO 51, ¶ 15, 373 P.3d
603, 607, that tort claims based on misrepresentations made
prior to the formation of a contract and that allegedly
induced the plaintiff to enter into that contract violated an
independent duty in tort and, thus, such claims were not
barred by the economic loss rule. In so concluding, we
observed that an important distinction exists between
"failure to perform the contract itself, and promises
that induce a party to enter into a contract in the first
place." Id. at ¶ 13, 373 P.3d at 607.
¶33
Although questions regarding the application of the economic
loss rule frequently arise in disputes involving one-to-one
contractual relationships, "[c]ontractual duties arise
just as surely from networks of interrelated contracts as
18
from two-party agreements." BRW, Inc. v. Dufficy
&Sons, Inc., 99 P.3d 66, 72 (Colo. 2004).
¶34
With these principles in mind, we turn to the facts before
us.
C.
Application
¶35
Veolia contends that the economic loss rule bars Antero's
fraud claims because (1) Veolia and Antero were parties to a
network of interrelated contracts that established a broad
and ongoing contractual relationship; and (2) any
misrepresentations were made in the course of that
relationship and were therefore governed by the parties'
contractual duties, particularly the implied covenant of good
faith and fair dealing. We disagree with each premise of
Veolia's argument, and thus we disagree with Veolia's
conclusion.
¶36
As an initial matter, we disagree with Veolia's assertion
that Veolia and Antero were parties to a network of
interrelated contracts for purposes of the economic loss
rule. As noted above, the parties entered into a series of
distinct and stand-alone contracts, none of which obligated
either party to proceed to a subsequent contract.
Specifically, under the Bench Scale Proposal, Veolia agreed
to conduct a study and preliminary engineering for Clearwater
to validate the process design and confirm Veolia's
proposed treatment approach. Nothing obligated either party
to proceed thereafter. Similarly, the LNTPs obligated Veolia
to conduct additional design work. Again, however, nothing in
those LNTPs
19
obligated the parties to proceed further. The DBA then
followed as a stand-alone agreement.
¶37
BRW, 99 P.3d at 72-74, on which Veolia principally
relies in arguing that the contracts at issue comprised a
network of interrelated contracts, is distinguishable. In
BRW, we addressed whether the economic loss rule
applied in a tort suit for claims of negligent breach of a
duty and negligent misrepresentation brought by a
subcontractor against a design engineer and its agent when no
contract existed between the subcontractor and those parties.
Id. at 67 &n.1. We began by noting that multiple
parties are frequently involved in large construction
projects and that "[t]hese parties typically rely on a
network of contracts to allocate their risks, duties, and
remedies." Id. at 72. We further observed that
in this context, the parties have the opportunity to define
their rights and remedies in a contractual relationship.
Id. Thus, even though a subcontractor might not have
the opportunity to negotiate directly with the engineer or
architect, it has the chance to allocate the risks of
following specified plans when it contracts with a party
involved in the network of contracts. Id. In this
way, the "application of the economic loss rule
encourages a subcontractor to protect itself from risks,
holds the parties to the terms of their bargain, enforces
their expectancy interests, and maintains the boundary
between contract and tort law." Id.
20
¶38
Applying these principles to the facts in that case, we
observed that the interrelated contracts at issue contained
the duties of care owed by the engineer and its agent and
that the subcontractor's remedies therefore existed in
contract. Id. at 74. Accordingly, we concluded that
the economic loss rule barred the subcontractor's
negligence claims against the engineer and its agent.
Id.; see also S K Peightal Eng'rs, LTD v.
Mid Valley Real Est. Sols. V, LLC, 2015 CO 7, ¶ 10,
342 P.3d 868, 872-73 (concluding, in a case in which a
later-created entity that acquired title to a spec home sued
two soil engineers that had subcontracts with the home's
developer but not with the entity, that the economic loss
rule could apply to an entity that did not exist at the time
the contracts containing the duties at issue were formed if
that entity was a party to or a third-party beneficiary of
the contract or an interrelated contract).
¶39
Unlike BRW, this case does not involve multiple
parties entering into a network of interlocking contracts to
perform a large transaction or project and in which certain
of the parties contracted directly with some but not all of
the other parties. Rather, this case involves two parties
that entered into a series of contracts with each other.
Moreover, the parties' contracts were not interlocking
agreements forming parts of a larger transaction or project.
To the contrary, although the Bench Scale Proposal and LNTPs
were related to the DBA, the DBA was a stand-alone,
fully integrated agreement governing the construction of
21
Clearwater, and, thus, it constituted its own distinct and
separate transaction. Our case law on the interrelated
contracts doctrine is therefore inapposite here.
¶40
Notwithstanding Veolia's assertion to the contrary, the
DBA's integration clause does not establish otherwise. As
noted above, that clause merely restated as duties under the
DBA duties that the parties had undertaken in their prior
agreements. The parties, however, were not required to
incorporate those duties into the DBA. They did so after
separately negotiating the latter agreement.
¶41
Nor are we persuaded by Veolia's reliance on Dream
Finders Homes LLC v. Weyerhaeuser NR Co., 2021 COA 143,
506 P.3d 108. In that case, a division of our court of
appeals expanded the interrelated contracts doctrine beyond
the context of a complex, multi-party, interrelated
transaction in which no contract existed between certain of
the parties to the transaction. Id. at ¶¶
45-48, 506 P.3d at 119-20. We have not explicitly endorsed
such an approach. Even if we did, however, Dream
Finders, too, is distinguishable.
¶42
Dream Finders involved a scenario in which none of a
series of documents between and among a joist manufacturer,
its distributor, and joist purchasers set forth all of the
terms and conditions of the parties' purchase agreement.
Id. at ¶¶ 46-47, 506 P.3d at 119. In these
circumstances, the division agreed with the joist
manufacturer that the documents constituted a single
agreement governing the sales of the joists. Id. at
¶ 48, 506 P.3d at 120. Having thus concluded, the
22
division further determined that any misrepresentations
alleged by the purchasers were post-contractual (because the
misrepresentations occurred after the earliest of the
documents on which the parties had agreed). Id. at
¶¶ 50-52, 506 P.3d at 120. And because the tort
duties alleged by the purchasers to have been breached
mirrored the duties set forth in the parties' contract,
the economic loss rule barred the purchasers'
misrepresentation and fraudulent concealment claims.
Id. at ¶¶ 53-83, 506 P.3d at 120-26.
¶43
Here, unlike in Dream Finders, Veolia does not
allege that the DBA failed to include all of the terms of the
parties' agreement. Indeed, it appears undisputed that
the DBA represented a complete recitation of the parties'
agreement for Clearwater's construction. Accordingly,
even if the Dream Finders division's
understanding of the interrelated contracts doctrine were
correct—an issue that we need not address
here—that case does not assist Veolia.
¶44
Lastly, we note that were we to accept Veolia's argument
that the contracts in this case were interrelated such that
they constitute a broad and ongoing contractual relationship,
the economic loss rule would essentially bar fraud claims
whenever parties happen to have had a preexisting contractual
relationship relating to a particular project or undertaking.
Such a rule would require contracting parties to bargain
preemptively to allocate risks and costs for
23
unknown future contracts. We have never extended the economic
loss rule or the interrelated contracts doctrine that far,
and we decline to do so now.
¶45
For these reasons, we conclude that Veolia and Antero were
not parties to a network of interrelated contracts
establishing an ongoing contractual relationship that
subsumed the violation of a duty to refrain from fraudulent
misrepresentations. (To the extent that the division below
concluded that Veolia and Antero were parties to a network of
interrelated contracts under BRW, we respectfully
disagree with that conclusion.) Rather, the parties signed a
series of independent agreements, and the pertinent
misrepresentations occurred prior to, and, on the facts
presented, induced Antero to enter into, the DBA.
Specifically, Veolia failed to disclose its inability to meet
Antero's power consumption requirements prior to the
execution of the DBA. And as the trial court found, with
ample record support, the power consumption guarantee was
critical to Antero and without that guarantee, Antero would
not have signed the DBA.
¶46
In short, the facts before us demonstrate that Antero's
fraud claim amounts to a straightforward fraudulent
inducement claim. Accordingly, we conclude that Van
Rees, ¶¶ 13-15, 373 P.3d at 607, controls and,
therefore, the economic loss rule does not bar that claim.
¶47
In light of this determination, we need not address whether
Veolia also fraudulently induced Antero to sign Change Order
1. But for the fraudulent
24
inducement of the DBA, the parties would not have been in a
position to agree to Change Order 1.
¶48
Finally, we note that even if Veolia's misrepresentations
and fraudulent concealment could be said to have been
post-contractual, we would reach the same result because, as
the division below opined, the covenant of good faith and
fair dealing, on which Veolia relies, does not apply to
nondiscretionary contract terms like those at issue here.
See Veolia Water Techs., ¶¶ 99-101, 564
P.3d at 1109. Thus, Antero would not have a viable claim for
breach of that implied covenant. See id.
¶49
Specifically, as noted above, Veolia contends that if its
misrepresentations were post-contractual, then any tort duty
to refrain from such misrepresentations would be subsumed by
either its express or implied contractual duties and barred
by the economic loss rule. Here, however, the parties'
agreements did not contain any express duties to refrain from
making misrepresentations. In fact, the DBA explicitly
contemplated the parties' ability to bring separate
claims for fraud, given the damages cap exception for
"gross negligence, fraud or willful misconduct."
Accordingly, if Veolia had a contractual duty to refrain from
making misrepresentations, then that duty had to arise, if at
all, from the contract's implied covenant of good faith
and fair dealing. See Former TCHR, LLC v. First Hand
Mgmt. LLC, 2012 COA 129, ¶ 29, 317 P.3d 1226, 1232
(concluding that the disclosure duties that the plaintiff
claimed to have been breached arose from and were
25
expressly described by the parties' preexisting agreement
or were subsumed within that agreement's implied covenant
of good faith and fair dealing); Hamon Contractors, Inc.
v. Carter &Burgess, Inc., 229 P.3d 282, 289
(Colo.App. 2009) (noting that the implied covenant of good
faith and fair dealing prohibits fraud in the performance of
contractual obligations as to which a party has discretionary
authority and, thus, the covenant may preclude fraud claims
arising out of the party's contractual performance).
¶50
As we have previously recognized, however, "[t]he duty
of good faith and fair dealing applies when one party has
discretionary authority to determine certain terms
of the contract, such as quantity, price, or time."
Amoco Oil Co. v. Ervin, 908 P.2d 493, 498 (Colo.
1995) (emphasis added). In this context, "discretionary
authority" refers to a party's ability after
contract formation to set or control the terms of
performance, and discretion occurs when, at contract
formation, the parties defer a decision regarding performance
terms of the contract. Id.
¶51
Here, as the division below observed, Veolia had no
discretion to modify Clearwater's core requirements under
the DBA (e.g., the salt quality requirements or power
guarantees) without Antero's written consent. Veolia
Water Techs., ¶¶ 100-01, 564 P.3d at 1109. As
a result, under the settled law described above, Veolia did
not owe Antero an implied contractual duty to refrain from
making misrepresentations regarding these matters.
Consequently, even if Veolia's
26
misrepresentations were post-contractual, no contractual duty
would have subsumed Veolia's common law tort duty to
refrain from making misrepresentations, and the economic loss
rule still would not bar Antero's fraud claim. See
Town of Alma, 10 P.3d at 1263 (noting that the economic
loss rule does not apply when the court has recognized the
existence of a duty independent of any contractual
obligations).
III.
Conclusion
¶52
For the foregoing reasons, we conclude that (1) the
interrelated contracts doctrine does not apply to a series of
contracts between two parties when each contract represents a
stand-alone transaction and (2) the fraud alleged here
occurred prior to the formation of the DBA and, on the facts
presented, induced Antero to sign that contract. Accordingly,
under Van Rees, ¶¶ 13-15, 373 P.3d at 607,
the economic loss rule does not bar Antero's fraud claim
in this case.
¶53
We therefore affirm the division's judgment below, albeit
on other grounds, and we remand this case with instructions
that the case be returned to the trial court for a
determination of the reasonable attorney fees to be awarded
to Antero pursuant to the DBA's fee-shifting provision.