Veit Co. v. Lake County

707 N.W.2d 725, 2006 Minn. App. LEXIS 14, 2006 WL 91301
CourtCourt of Appeals of Minnesota
DecidedJanuary 17, 2006
DocketA04-1958
StatusPublished
Cited by6 cases

This text of 707 N.W.2d 725 (Veit Co. v. Lake County) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Veit Co. v. Lake County, 707 N.W.2d 725, 2006 Minn. App. LEXIS 14, 2006 WL 91301 (Mich. Ct. App. 2006).

Opinion

OPINION

PETERSON, Judge.

On appeal from .the denial of relator applicants’ application to amend their conditional-use permit, relators argue that their application was approved by operation of law because respondent county did not (1) provide relators a written statement of the reasons for denying the permit within the required statutory period; and (2) provide relators a written statement of the reasons for the denial that was consistent with the reasons stated on the record. We reverse.

FACTS

In July 2000, respondent Lake County Planning Commission granted relator B & B Aggregates a conditional-use permit (CUP) for a commercial gravel operation. In the published conditional-use order, the planning commission found that B & B’s CUP request did not include crushing or washing operations and that the CUP allowed only gravel mining and screening. After B & B submitted to the planning commission a separate application for a crushing permit and sought a writ of mandamus in the district court to compel the planning commission to approve B & B’s permit request, the planning commission issued an amended order granting B & B’s *727 request for a crushing permit, but it did not allow blasting or quarrying. B & B amended its petition for a writ of mandamus to compel the planning commission to include blasting and quarrying in the permit, arguing that blasting and quarrying are inherent to a commercial gravel operation. The district court granted summary judgment for respondent Lake County and its planning commission, and this court affirmed. B & B Aggregates v. Lake County, 2002 WL 453231 (Minn.App. Mar.26, 2002).

In June 2003, B & B applied to Lake County to “add blasting and quarrying to previously approved ‘CUP.’ ” On August 18, 2003, the planning commission denied B & B’s application. B & B did not challenge the August 18, 2003 decision.

On June 15, 2004, B & B, this time joined by relator Veit Company, submitted another application to add blasting and quarrying to its previously approved CUP. The planning commission conducted a hearing on relators’ application on August 16, 2004. At the close of the hearing, a commission member moved to deny the CUP application based on relators’ failure to show that the proposed use would not create potential health and safety, environmental, lighting, noise, signing, or visual problems and would not be detrimental to the rightful use and enjoyment of other property in the immediate vicinity nor substantially diminish or impair property values within the vicinity. The motion carried. At the meeting, a written notice of denial was given to John Pippert, a vice president of Veit. The notice does not list any reasons for the denial. In October 2004, relators received from the planning commission a written order that states that relators’ application is denied and includes as an attachment a planning-commission resolution that states reasons for the denial.

By writ of certiorari, relators sought this court’s review of the planning commission’s denial of their CUP application.

ISSUE

Was relators’ CUP application approved by operation of law because the planning commission failed to comply with the requirements in Minn.Stat. § 15.99, subd. 2(c) (Supp.2003)?

ANALYSIS

Because the planning commission determined facts about the nature and effects of relators’ proposed land use and then exercised its discretion in determining whether to allow the use, the denial of relators’ application was a quasi-judicial decision. Neitzel v. County of Redwood, 521 N.W.2d 73, 75 (Minn.App.1994), revieiv denied (Minn. Oct. 27, 1994). The supreme court has explained

that in the absence of an adequate method of review or legal remedy, judicial review of the quasi-judicial decisions of administrative bodies, if available, must be invoked by writ of certiorari. Review by certiorari is limited to an inspection of the record of the inferior tribunal in which the court is necessarily confined to questions affecting the jurisdiction of the board, the regularity of its proceedings, and, as to merits of the controversy, whether the order or determination in a particular case was arbitrary, oppressive, unreasonable, fraudulent, under an erroneous theory of law, or without any evidence to support it.

Dietz v. Dodge County, 487 N.W.2d 237, 239 (Minn.1992) (quoting State ex rel. Ging v. Bd. of Educ. of Duluth, 213 Minn. 550, 571, 7 N.W.2d 544, 556 (1942) (overruled on other grounds)).

Relators argue that when denying their CUP application, the planning commission *728 failed to comply with the requirements in Minn.Stat. § 15.99, subd. 2(c) (Supp.2003), that the commission state reasons for the denial in writing. Relators contend that because the planning commission failed to comply with these statutory requirements, they are entitled to have their application granted. Respondents contend that the written denial that relators received’ on August 16, 2004, and the verbatim transcript of the August 16 hearing conform to the requirements of section 15.99.

Statutory interpretation is a question of law subject to de novo review. Am. Tower, L.P. v. City of Grant, 636 N.W.2d 309, 312 (Minn.2001).

Minn.Stat. § 15.99, subd. 2 (Supp.2003), states:

(a) Except as otherwise provided in this section, section 462.358, subdivision 3b, or chapter 505, and notwithstanding any other law to the contrary, an agency must approve or deny within 60 days a written request relating to zoning, septic systems, or expansion of the metropolitan urban service area for a permit, license, or other governmental approval of an action. Failure of an agency to deny a request within 60 days is approval of the request. If an agency denies the request, it must state in uniting the reasons for the denial at the time that it denies the request.
(b) When a vote on a resolution or properly made motion to approve a request fails for any reason, the failure shall constitute a denial of the request provided that those voting against the motion state on the record the reasons why they oppose the request. A denial of a request because of a failure to approve a resolution or motion does not preclude an immediate submission of a same or similar request.
(c)Except as provided in paragraph (b), if an agency, other than a multi-member governing body, denies the request, it must state in writing the reasons for the denial at the time that it denies the request. If a multimember governing body denies a request, it must state the reasons for denial on the record and provide the applicant in writing a statement of the reasons for the denial.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Minnesota Towers, Inc. v. City of Duluth
474 F.3d 1052 (Eighth Circuit, 2007)
Hans Hagen Homes, Inc. v. City of Minnetrista
713 N.W.2d 916 (Court of Appeals of Minnesota, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
707 N.W.2d 725, 2006 Minn. App. LEXIS 14, 2006 WL 91301, Counsel Stack Legal Research, https://law.counselstack.com/opinion/veit-co-v-lake-county-minnctapp-2006.