Gun Lake Ass'n v. County of Aitkin

612 N.W.2d 177, 2000 Minn. App. LEXIS 629, 2000 WL 821498
CourtCourt of Appeals of Minnesota
DecidedJune 20, 2000
DocketC7-99-1630
StatusPublished
Cited by8 cases

This text of 612 N.W.2d 177 (Gun Lake Ass'n v. County of Aitkin) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gun Lake Ass'n v. County of Aitkin, 612 N.W.2d 177, 2000 Minn. App. LEXIS 629, 2000 WL 821498 (Mich. Ct. App. 2000).

Opinion

*179 OPINION

PETERSON, Judge

Respondents applied to Aitkin County for a conditional use permit (CUP) to operate a hot-mix, asphalt plant on property in Fleming Township. When the county planning commission initially considered the CUP application, it stated it was conditionally granting the application and that specific conditions for the operation of the hot-mix plant would be imposed later. The planning commission later approved certain conditions and relators appealed the planning commission’s decision to the Aitkin County Board of Commissioners, which denied the appeal. On appeal to this court from the county board’s denial of the appeal from the planning commission, relators challenge the grant of the CUP and the process used to create the later-imposed conditions. Because the county board’s decision to deny the portion of the appeal challenging the grant of the CUP is consistent with Minn.Stat. § 15.99, subd. 2 (1998), and because relators have not shown that the process used to create the conditions was defective, we affirm.

FACTS

Respondent George Shetka owns property in Fleming Township in Aitkin County. Respondent Charles Hawkinson manages that property. In May 1998, Hawkinson applied to Aitkin County for a CUP allowing part of the Shetka property to be used as a “permanent/ongoing site for the use of temporary/portable hot mix plants.”

The Gun Lake Resident’s Association and Robert Carlson, among others, opposed the application. The Fleming Township Board of Supervisors sent the county planning commission a letter expressing the board’s opposition to allowing a hot-mix facility on Shetka’s land. In July 1998, the township board sent the planning commission another letter stating that the township wanted to present its case for adopting a list of conditions for any CUP the county might grant.

At some point in July 1998, the township board, residents’ associations, Hawkinson, Shetka, and a representative of an environmental group met. They discussed, and at least tentatively agreed upon, conditions for the operation of the proposed hot-mix plant. On July 20, 1998, the county planning commission met to address the CUP application. At that meeting: (a) the proposed conditions were presented to the planning commission; (b) a township representative stated that the township board believed the proposed conditions were “solid,” would protect the surrounding environment, and that the township board was in favor of granting the CUP with those conditions; (c) the planning commission noted that two other sets of proposed conditions had been introduced; (d) Shetka’s attorney argued that if the legal requirements for a CUP were satisfied, the commission lacked discretion to deny the application; (e) questions were raised about whether there were other possible sites for a hot-mix plant in the county; and (f) the planning commission stated that it was conditionally approving the CUP application but that the question of conditions for the CUP would be referred to an ad hoc environmental responsibility team made up of two members of the planning commission, the county attorney, and staff from the zoning office.

On July 20,1998, the county zoning ordinance required that an appeal of a planning commission decision be taken to the county board within 30 days. No appeal of the planning commission’s July 20 decision was taken. On July 29, 1998, the environmental responsibility team met to create a list of proposed conditions for the CUP. A representative from the township and counsel for Carlson were allowed to be “non-verbal observers” at the meeting.

An August 14, 1998, letter from the Minnesota Environmental Quality Board to the planning commission stated that an Environmental Assessment Worksheet *180 (EAW) had been requested for the proposed hot-mix plant and that the county was the proper authority to ask the CUP applicant to complete the worksheet. Effective August 25, 1998, the county zoning ordinance was amended to require that an appeal of a planning commission decision be by writ of certiorari to the Minnesota Court of Appeals. An EAW was filed in February 1999. Comments on the EAW were filed through early March. Comments from the Minnesota Pollution Control Agency stated that while the odor associated with the hot-mix plant would not be easy to address, the other aspects of the EAW were not a major concern.

A March 22, 1999, memorandum from the county planning commission to the county board stated that the environmental responsibility team did not recommend continuing the environmental review process by requiring an Environmental Impact Statement (EIS) for the proposed facility. The next day, the county issued its decision against requiring a full EIS, stating that the identified environmental impacts were minor and/or temporary, the plan did not include environmental effects that could not be addressed, and the project lacks a potential for significant environmental effects.

On April 19, 1999, the full planning commission met to consider the list of proposed CUP conditions that had been developed by the environmental responsibility team. Relators’ counsel argued that the process for developing the conditions had been flawed because his attempt to put information in the record (apparently at the July 29 meeting that started the process for drafting the conditions) had been ignored. The chair of the commission replied that the only thing at issue at the meeting was the propriety of the eondi-tions for the CUP. After some alterations, the commission approved the proposed conditions. Counsel for Carlson asked how to appeal the planning commission’s decision and the county attorney told him to appeal to the county board.

On May 15, Carlson’s counsel sent the county board a letter stating that Carlson was appealing the “April 19, 1999 granting of a [CUP.]” 1 On August 10, the county board heard the appeal. On August 31, the board voted 3-2 to deny the appeal. This appeal followed. During the pen-dency of the appeal, Fleming Township was dismissed as a party to the appeal.

ISSUES

1. Did the county board act arbitrarily, or otherwise improperly, in denying the portion of relators’ appeal challenging the grant of the CUP application?

2. Did relators show defects in the process used to create the conditions imposed on the conditional use permit?

ANALYSIS

I.

“[A]n agency must approve or deny within 60 days a written request relating to zoning” and “[fjailure of an agency to deny a request within 60 days is approval of the request.” Minn.Stat. § 15.99, subd. 2 (1998). “Agency” includes a county. Minn.Stat. § 15.99, subd. 1 (1998). Rela-tors allege that the CUP application was made on May 20, 1998. Shetka alleges that the application was made on May 18, 1998. Although some of the documents supporting the CUP application are dated May 18, the application is dated May 20. For purposes of this appeal, we assume *181 that the application was made on May 20, 1998.

Sixty days from May 20, 1998, was Sunday, July 19,1998. Therefore, the last day for the county to approve or deny the application was Monday, July 20, 1998. See Minn.Stat.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Breza v. City of Minnetrista
725 N.W.2d 106 (Supreme Court of Minnesota, 2006)
Veit Co. v. Lake County
707 N.W.2d 725 (Court of Appeals of Minnesota, 2006)
Breza v. City of Minnetrista
706 N.W.2d 512 (Court of Appeals of Minnesota, 2005)
Moreno v. City of Minneapolis
676 N.W.2d 1 (Court of Appeals of Minnesota, 2004)
Tollefson Development, Inc. v. City of Elk River
665 N.W.2d 554 (Court of Appeals of Minnesota, 2003)
Jorgensen v. Knutson
662 N.W.2d 893 (Supreme Court of Minnesota, 2003)
Northern States Power Co. v. City of Mendota Heights
646 N.W.2d 919 (Court of Appeals of Minnesota, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
612 N.W.2d 177, 2000 Minn. App. LEXIS 629, 2000 WL 821498, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gun-lake-assn-v-county-of-aitkin-minnctapp-2000.