Northern States Power Co. v. City of Mendota Heights

646 N.W.2d 919, 2002 Minn. App. LEXIS 829, 2002 WL 1547923
CourtCourt of Appeals of Minnesota
DecidedJuly 16, 2002
DocketC3-02-65
StatusPublished
Cited by9 cases

This text of 646 N.W.2d 919 (Northern States Power Co. v. City of Mendota Heights) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northern States Power Co. v. City of Mendota Heights, 646 N.W.2d 919, 2002 Minn. App. LEXIS 829, 2002 WL 1547923 (Mich. Ct. App. 2002).

Opinion

OPINION

KLAPHAKE, Judge.

Appellant Northern States Power Co., d/b/a Xcel Energy (Xcel) brought this mandamus petition and declaratory judgment complaint against respondent City of Mendota Heights to compel the city to approve its application for a conditional use permit (CUP) under the automatic approval provisions of Minn.Stat. § 15.99 (2000). Xcel applied for the CUP to upgrade an existing transmission line running through the city. Power Line Task Force, Inc. (PLTF), a group of private citizens who live near the existing line, was allowed to intervene in support of the city’s position.

On cross motions for summary judgment, the district court concluded that Xcel was equitably estopped from asserting its right to automatic approval of the CUP under section 15.99. The court did not reach the other issues raised by the parties, including whether section 15.99 “unconstitutionally violates due process” or whether a later enacted franchise ordinance applies to Xcel’s pending CUP application.

Because, under the undisputed facts of this case, Xcel did not approve an extension of the deadline for acting on its CUP application beyond September 8, 2000, and because the city did not act prior to that date, Xcel is entitled to issuance of the CUP under section 15.99. We therefore reverse.

FACTS

On March 2, 1999, Xcel filed an application with the city for a conditional use permit to allow Xcel to upgrade an existing single-circuit transmission line to a double-circuit transmission line. The line runs through several other cities in the southeast metropolitan area, including South St. Paul and Sunfish Lake. The project would replace the existing poles with new, single-steel pole structures approximately 25 feet higher than the existing ones.

*922 By statute, the city had 60 days from Xeel’s filing of the permit application to act. Minn.Stat. § 15.99 (2000). This time deadline was suspended pending completion of proceedings before the Minnesota Environmental Quality Board (MEQB). 1 See Minn.Stat. 116D.04, subd. 2a(c) (1998) (allowing any group of 25 or more individuals to petition MEQB to consider whether proposed construction project has “potential for significant environmental effects”). In November 1999, the MEQB determined that the project did not have the potential for significant adverse environmental effects. With the conclusion of the MEQB proceedings, the parties agreed that the city’s 60-day statutory review period would resume. 2 See Minn.Stat. § 15.99, subd. 3(e). On December 3, the city sent Xcel a letter in which it set out the parties’ agreement that the review period under section 15.99 would resume on January 25, 2000, when the next planning commission meeting was scheduled to be held, and expire on February 9, 2000, “unless further extended by the [c]ity.” 3

On January 25, the city’s planning commission met and reviewed the CUP application. Xcel representative Pat Cline verbally agreed “to continue the hearing to next month” due to the amount of materials the commission had recently received and the fact that not all neighbors had received notice of the meeting. Cline indicated that “[Xcel] had no dispute with the [c]ity regarding the starting and ending dates for the 60-day review period and that [Xcel] was more than happy to come back to the February * ⅜ ⅜ meeting.” The commission passed a motion to continue the public hearing on the CUP application until its February 22 meeting and “to extend the 60-day review period for an additional sixty days.” On February 11, two days after the February 9 deadline passed, the city sent Xcel a letter confirming that the planning commission had extended the review period for an additional 60 days, to April 9.

At its February 22 meeting, the planning commission recommended denial of the CUP. The commission cited concerns regarding potential health and safety risks associated with the project, possible detrimental impacts on nearby property values, and the need for a review of the project on a regional basis because of its impact on several cities and jurisdictions.

*923 On March 6, the city council met to consider the recommendations of the planning commission. The city proposed that Xcel hire an independent consultant and that a “Regional Steering Committee” be created to involve the other cities along the power line. Xcel agreed to the proposal and agreed that the statutory period of review would be extended as long as the work of the committee was done in good faith and within a set time limit.

On April 4, the city council adopted a resolution authorizing the creation of the steering committee. The resolution further provided that the steering committee would retain an independent consultant to review the project and advise the committee. The city passed a second resolution denying Xcel’s permit application unless “[Xcel] submits a letter formally extending the review period for a period of five months from April 9.” On April 5, Xcel agreed in writing to an extension of the review period to September 8, 2000.

As planned, Xcel recommended several consultants and one was chosen by the regional steering committee. The committee met several times over the next few months. As agreed, Xcel paid the fees and monitored the progress of the consultant’s study.

The September 8, 2000 deadline, however, passed without any communication between Xcel and the city. The issue was not discussed until mid-March 2001, when an Xcel representative raised the issue with the city regarding the lack of “any documentation or exchange between us extending” the September 8 deadline and the possibility of a “de facto approval.”

In March 2001, the consultant issued a final report to the committee. The consultant agreed that the project was necessary and that it would eliminate the concern of electrical outage of the existing circuit and other associated lines. After evaluating five alternatives to the project, the consultant concluded that Xcel’s “proposed plan comes closest to meeting the electrical supply requirements, taking into account the economic cost of the improvements.” The consultant further concluded: “Double-circuiting the existing line on the existing right-of-way will reduce the electric and magnetic fields.”

On April 10, Xcel met with the city’s mayor. The mayor informed Xcel that its permit application was on the agenda for the next planning commission meeting, scheduled for April 24. Xcel responded that it “declined to again appear before the Planning Commission, having appeared before that body at the beginning of the process.” The mayor agreed that the record was complete, but now “believed that the [c]ity should require [Xcel] to offer to buy houses affected by EMF levels above a certain threshold as a permit condition.”

On May 8, 2001, Xcel sent a letter to the city demanding that the city issue the permit by June 5, 2001. Xcel stated that it had not approved any further extension of the September 8, 2000 deadline and that it “has not waived and does not waive its entitlement to issuance of a permit under [section 15.99].”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harstad v. City of Woodbury
902 N.W.2d 64 (Court of Appeals of Minnesota, 2017)
Hans Hagen Homes, Inc. v. City of Minnetrista
713 N.W.2d 916 (Court of Appeals of Minnesota, 2006)
Pollard v. Southdale Gardens of Edina Condominium Ass'n
698 N.W.2d 449 (Court of Appeals of Minnesota, 2005)
Concept Properties, LLP v. City of Minnetrista
694 N.W.2d 804 (Court of Appeals of Minnesota, 2005)
Allen v. City of Mendota Heights
694 N.W.2d 799 (Court of Appeals of Minnesota, 2005)
Moreno v. City of Minneapolis
676 N.W.2d 1 (Court of Appeals of Minnesota, 2004)
Tollefson Development, Inc. v. City of Elk River
665 N.W.2d 554 (Court of Appeals of Minnesota, 2003)
Advantage Capital Management v. City of Northfield
664 N.W.2d 421 (Court of Appeals of Minnesota, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
646 N.W.2d 919, 2002 Minn. App. LEXIS 829, 2002 WL 1547923, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northern-states-power-co-v-city-of-mendota-heights-minnctapp-2002.