Minnesota Towers, Inc. v. City of Duluth

474 F.3d 1052, 40 Communications Reg. (P&F) 210, 2007 U.S. App. LEXIS 432, 2007 WL 57581
CourtCourt of Appeals for the Eighth Circuit
DecidedJanuary 10, 2007
Docket06-1118
StatusPublished
Cited by3 cases

This text of 474 F.3d 1052 (Minnesota Towers, Inc. v. City of Duluth) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Minnesota Towers, Inc. v. City of Duluth, 474 F.3d 1052, 40 Communications Reg. (P&F) 210, 2007 U.S. App. LEXIS 432, 2007 WL 57581 (8th Cir. 2007).

Opinions

LOKEN, Chief Judge.

Duluth property owner James Bechthold leased a commercial site to Minnesota Towers, Inc., for the construction of a 195-foot telecommunications tower. American Cellular Corporation and other wireless cell phone service providers planned to use the tower to better serve the Piedmont Heights area of Duluth. Minnesota Towers and Bechthold (hereafter collectively referred to as Minnesota Towers) applied to the City of Duluth for a special use permit to construct the tower, as required by the City’s zoning laws. The Duluth Planning Commission recommended approval, but the Duluth City Council, the City’s final decision-maker, rejected the Commission’s approval resolution. Minne[1053]*1053sota Towers then filed this action challenging the City’s adverse action under federal and state law. The district court denied Minnesota Towers summary judgment on its federal claims but granted summary judgment on the ground that the City’s denial was untimely and therefore the application must be deemed approved as a matter of state law. The City appeals. We reverse.

I. The Governing Minnesota Statute

In 1995, the Minnesota Legislature passed a statute providing that a city must approve or deny a request for a zoning permit within sixty days unless the applicant is given written notice that the period has been extended an additional sixty days. 1995 Minn. Laws ch. 248, art. 18, § 1, codified at Minn.Stat. § 15.99, subd. 2, 3(f) (1996). Subdivision 2 further provided that failure to deny a request within sixty days “is approval of the request.” In addition, if a city denies a request, “it must state in writing the reasons for the denial at the time that it denies the request.” Minnesota courts have rigorously enforced these requirements against non-complying cities in cases such as Demolition Landfill Servs., LLC v. City of Duluth, 609 N.W.2d 278 (Minn.App.2000).

In Demolition Landfill, the City voted down a resolution approving a permit application. Though the vote in Demolition Landfill was taken within the statutory deadline, the court held that the application was approved by operation of § 15.99, as initially enacted, because (i) voting down a resolution approving an application was not a denial for purposes of subdivision 2, and (ii) in any event the City did not provide contemporaneous written reasons for its action, as subdivision 2 required. 609 N.W.2d at 281. The Legislature responded by amending subdivision 2, making the original provision subdivision 2(a) and adding subdivisions 2(b) and 2(c), which provide in relevant part:

(b) When a vote on a 'resolution or properly made motion to approve a request fails for any reason, the failure shall constitute a denial of the request provided that those voting against the motion state on the record the reasons why they oppose the request....
(c) Except as provided in paragraph • (b), if an agency, other -than a multi-member governing body, denies the request, it must state in’writing the reasons for the denial at the time that it denies the request. If a multimember governing body denies a request, it must state the reasons for denial on the record and provide the applicant in writing a statement of the reasons for the denial. If the written statement is not adopted at the same time as the denial, it must be adopted at the next meeting following the denial ... but before the expiration of the time allowed for making a decision under this section. The written statement must be consistent with the reasons stated in the record at the time of the denial.

2003 Minn. Laws ch. 41, § 1, codified at MinmStat. § 15.99, subd. 2(b), (c).

After the statute was amended, a multi-member governing body voted in favor of a proposed denial resolution on the last day of the sixty-day period but failed to provide the applicant with the timely written statement of reasons that subdivision 2(c) requires. The Minnesota Court of Appeals held that the application was deemed approved as a matter of -law because new subdivision 2(c) did not overrule the Demolition Landfill holding that a timely written statement of reasons is mandatory. Veit Co. v. Lake County, 707 N.W.2d 725, 729-30 (Minn.App.2006).

[1054]*1054II. Background

In this case, Minnesota Towers applied for the special use permit on September 29, 2004. The Planning Commission voted to approve the application on November 9 and forwarded a proposed approval resolution to the City Council. The City Council voted 8-0 to reject the approval resolution on November 22, fifty-four days after Minnesota Towers filed the application. Six Council members stated on the record their reasons for denying the special use permit. On November 23, the Duluth City Attorney sent a letter notifying Minnesota Towers of the Council’s action and setting forth numerous reasons why the application was denied. The City Council passed a resolution adopting the City Attorney’s statement of reasons on December 6, sixty-eight days after the application was initially filed.

The summary judgment record reflects that it is Planning Commission practice to extend the statutory sixty-day period to 120 days for every application by mailing the extension notice § 15.99, subd. 3(f), requires. However, in this case, the Senior Planner’s secretary drafted an extension letter, but no copy of a signed letter can be found in the pertinent files of the City, of either applicant, or of Minnesota Towers’s engineer and land surveyor, who would normally have been sent courtesy copies.

Minnesota Towers argued, and the district court agreed, that the City Attorney’s November 23 letter to Minnesota Towers was not a written statement of reasons by the City Council, as subdivision 2(c) requires, and the City Council’s December 6 resolution did not adopt this statement of reasons within the statutory sixty-day period. Accordingly, the City failed to take proper action denying the application within sixty days because it did not comply with subdivision 2(c) as construed in Veit. Turning to the subdivision 3(f) extension issue, the court concluded, after discovery on the issue, that an extension letter was never sent. Accordingly, the court ruled that the application was approved by operation of law because the sixty-day deadline in § 15.99 was neither met nor extended. On appeal, the City argues that the district court erred in applying subdivision 2(c) of § 15.99 and also overlooked genuine issues of material fact precluding summary judgment on the extension issue. Given our resolution of the first issue, we need not reach the second.

III. Discussion

In this case, as in Demolition Landfill, the City Council took action by voting down a proposed resolution approving the Minnesota Towers application, rather than by voting in favor of a resolution denying the requested permit. The City argues that its actions were therefore taken under and are governed by subdivision 2(b) of § 15.99, not subdivision 2(c). Subdivision 2(b) does not expressly require a written statement of reasons within the sixty-day period, only that Council members “state on the record the reasons why they oppose the request.” Therefore, the City contends, its denial was timely under § 15.99.

Neither

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hans Hagen Homes, Inc. v. City of Minnetrista
728 N.W.2d 536 (Supreme Court of Minnesota, 2007)
Minnesota Towers, Inc. v. City of Duluth
474 F.3d 1052 (Eighth Circuit, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
474 F.3d 1052, 40 Communications Reg. (P&F) 210, 2007 U.S. App. LEXIS 432, 2007 WL 57581, Counsel Stack Legal Research, https://law.counselstack.com/opinion/minnesota-towers-inc-v-city-of-duluth-ca8-2007.