Vandra Bros. Constr. Co., Inc. v. Commissioner

2000 T.C. Memo. 233, 80 T.C.M. 125, 2000 Tax Ct. Memo LEXIS 277
CourtUnited States Tax Court
DecidedAugust 2, 2000
DocketNo. 15483-96
StatusUnpublished

This text of 2000 T.C. Memo. 233 (Vandra Bros. Constr. Co., Inc. v. Commissioner) is published on Counsel Stack Legal Research, covering United States Tax Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vandra Bros. Constr. Co., Inc. v. Commissioner, 2000 T.C. Memo. 233, 80 T.C.M. 125, 2000 Tax Ct. Memo LEXIS 277 (tax 2000).

Opinion

VANDRA BROS. CONSTRUCTION CO., INC., Petitioner v. COMMISSIONER OF INTERNAL REVENUE, Respondent
Vandra Bros. Constr. Co., Inc. v. Commissioner
No. 15483-96
United States Tax Court
T.C. Memo 2000-233; 2000 Tax Ct. Memo LEXIS 277; 80 T.C.M. (CCH) 125; T.C.M. (RIA) 53975;
August 2, 2000, Filed

*277 Decision will be entered for petitioner.

Michael J. Occhionero, for petitioner.
Joseph P. Grant, for respondent.
Gale, Joseph H.

GALE

MEMORANDUM FINDINGS OF FACT AND OPINION

GALE, JUDGE: Respondent determined a deficiency of $ 405,017, and an accuracy-related penalty under section 6662(a) in the amount of $ 81,003.40, for petitioner's 1992 taxable year. Unless otherwise noted, all section references are to the Internal Revenue Code in effect for the year in issue.

After a concession by respondent, 1 we must decide whether respondent abused his discretion in determining that petitioner's use of the cash method of accounting did not clearly reflect income. We hold that he did.

FINDINGS OF FACT

Some of the facts have been stipulated and are so found. We incorporate by this reference the stipulation of facts and attached exhibits. At the time of filing the petition, petitioner was an Ohio corporation with*278 its principal place of business in Oakwood Village, Ohio.

Petitioner specialized in the construction of streets, sidewalks, curbs, and similar improvements for governmental entities. All of petitioner's customers were governmental and municipal agencies, including the State of Ohio and municipalities within the State. Petitioner's expertise was construction, in particular laying concrete, on public sites such as city streets and sidewalks that required the project to be completed with a minimal amount of disruption in traffic flow and in compliance with governmental regulations. Petitioner provided labor and equipment, 2 but petitioner did not maintain a supply of any of the materials that were used at a construction site, instead relying on suppliers to deliver needed materials to the construction site at the appropriate time. Petitioner only ordered the materials it needed for the job for the particular day. Petitioner had no plant or other facility to store materials and could not store materials at the construction site. (Petitioner left no material on site overnight except, occasionally, a negligible amount.) Concrete could not be stored on site for an additional reason: Within*279 a few hours of delivery, it would harden and become useless and worthless. Thus, petitioner tried to estimate as closely as possible the amount of materials needed so there would not be anything left over. Petitioner bore the cost of any wasted materials if they were the result of an over order, or, in the case of concrete, of it not being laid in time. If the materials were defective or, in the case of concrete, delivered too late, the supplier was responsible and bore the cost.

Virtually all of petitioner's projects required laying some concrete. Petitioner also engaged in related work, such as preparing a site by removing existing concrete or stone. Petitioner also installed items such as reinforcing steel, piping for sewers and drainage, and guardrails. During the year in issue, 67 percent of petitioner's total materials cost was due to concrete, 16 percent was due to stone, 6 percent was due to reinforcing material, and the remainder was due to*280 other materials. In general, petitioner subcontracted for certain parts of projects, such as electrical work, asphalt, or landscaping.

BIDS

Petitioner's work was generally obtained through competitive bids. Petitioner's bids comprised costs for labor, equipment, and materials. In computing its bid, petitioner estimated the cost of labor and equipment and added a markup to the cost of labor. Further, petitioner estimated the quantity of materials, which could include concrete, aggregate (stone and gravel), reinforcing steel, piping for sewer and drainage, guardrail, etc. However, petitioner did not add a markup to the cost of materials but rather included the cost of the materials, as quoted by the supplier, as an item in the bid. During the year in issue, 27 percent of petitioner's gross revenue came from the material cost of concrete. Petitioner would always solicit materials costs from at least two suppliers, and sometimes three or four, and would choose the lowest quoted cost for use in the bid. The cost of materials was subject to slight variations due, for example, to the distance between a supplier and the job site. However, petitioner got a discount for early payment to suppliers,*281 which was not passed along to customers. Occasionally a customer itself would supply materials (e.g., concrete), but this did not happen during the year in issue.

Bids were calculated by estimating the cost of each individual job that was necessary to complete the entire project. The bid price of most of the individual jobs was calculated on a per-unit basis. For instance, in arriving at a total bid for the reconstruction of a street in the City of South Euclid, petitioner bid $ 28 per square yard to install 9-inch reinforced concrete pavement, and $ 5 per linear foot to install 6-inch drainage conduit, and separate amounts for numerous other items. The bid price for some individual jobs was calculated on a per-item basis (for instance, $ 23 per each 9-foot guardrail post) or on a lump-sum basis (for instance, $ 60,000 for clearing and grubbing a certain area indicated in the project plan). The bid calculation also included the estimated number of units or items that the project required. However, petitioner would bill the customer on the basis of the number of units or items actually used on the project, not the number shown in the bid. In some cases, petitioner was required by the*282

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thor Power Tool Co. v. Commissioner
439 U.S. 522 (Supreme Court, 1979)
Ansley-Sheppard-Burgess Co. v. Commissioner
104 T.C. No. 17 (U.S. Tax Court, 1995)
RACMP Enters. v. Commissioner
114 T.C. No. 16 (U.S. Tax Court, 2000)
Hallmark Cards, Inc. v. Commissioner
90 T.C. No. 2 (U.S. Tax Court, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
2000 T.C. Memo. 233, 80 T.C.M. 125, 2000 Tax Ct. Memo LEXIS 277, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vandra-bros-constr-co-inc-v-commissioner-tax-2000.