Valley Forge, Inc. v. CK Construction, Inc.

Court of Appeals of Texas·Decided May 11, 2023·No. 08-22-00084-CV·Published

Opinion

COURT OF APPEALS

EIGHTH DISTRICT OF TEXAS

EL PASO, TEXAS

VALLEY FORGE, INC. § No. 08-22-00084-CV Appellant, § Appeal from the v. § County Court at Law No. 3

CK CONSTRUCTION, INC. § of El Paso County, Texas Appellee.

§ (TC# 2021DCV3705)

OPINION

Appellee CK Construction, Inc. (CK) filed a lawsuit claiming that Appellant Valley Forge, Inc. (Valley Forge) breached their construction contract by failing to pay all amounts promised after CK completed its contractual obligations to remodel a building owned by Valley Forge. Finding Valley Forge breached the contract, the trial court granted CK’s motion for summary judgment and entered a money judgment against Valley Forge, granted CK’s request for a judicial foreclosure of its lien on the subject property, and entered an award of attorney’s fees. Valley Forge contends the trial court erred in granting summary judgment, as questions of fact remain on whether it was in breach and on the amount of any debt owed to CK. Because we agree that factual questions remain on both issues, we reverse the trial court’s judgment and remand to the trial court for further proceedings.

I. FACTUAL AND PROCEDURAL BACKGROUND The parties agree on the following key issues: (1) in October 2020, CK and Valley Forge entered into a contract whereby CK agreed to renovate and remodel a building in El Paso, Texas (the Project); (2) Valley Forge made several payments to CK as required by the contract while the Project was ongoing; (3) in February 2021, CK fulfilled its contractual obligations on the Project; and (4) Valley Forge attempted to make a final payment to CK in the amount it believed was owed, but CK refused the payment contending it was inadequate to satisfy Valley Forge’s contractual obligations, which disagreement led to the present suit.

A. CK’s lawsuit

On October 19, 2021, CK filed suit against Valley Forge alleging Valley Forge breached the parties’ contract by failing to pay $69,166.15 CK claimed was due and owing together with $440 for “service calls and maintenance repairs” for a total of $69,606.15. 1 In its petition, CK alleged that the parties’ contract required Valley Forge to pay CK $492,577.62 for the Project work “plus 10% additional combined profit and overhead on additive change orders.” CK further argued that the parties agreed a “5% retainage was to be withheld on the Project subject to additions and deletions for agreed upon changes.” CK acknowledged that while the Project was ongoing, Valley Forge paid five invoices in accordance with the contract, but claims that after the Project was completed, it sent a sixth and final invoice to Valley Forge for the remaining amount of $69,606.15, which Valley Forge refused to pay. CK further alleged that it sent a demand letter to Valley Forge on August 10, 2021, seeking payment on the final invoice. According to CK, Valley Forge

1 In its petition, CK also brought a claim for tortious interference with contract, contending that after completion of the Project, Valley Forge wrongfully contacted CK’s subcontractors and sought to pay them directly. This claim, however, was not the subject of the summary judgment motion and was not addressed by the trial court in its order. We therefore do not address it in our analysis.

responded with a “nonsensical letter” contending the parties’ contract was “flawed,” that it was entitled to a credit, and suggesting that the parties should meet with the Project’s architect, go to mediation, or let the matter be handled “by the attorneys.”

CK then retained an attorney to pursue its lawsuit and filed a mechanic’s and materialman’s lien on the subject property in the amount it contended was owed under the contract. 2 In its lawsuit, CK sought damages in the amount of $69,606.15 for the alleged breach, a judicial order of foreclosure on the lien, a judicial sale of its interests in the subject property, and an award of attorney’s fees. Valley Forge filed a general denial to CK’s lawsuit.

B. CK’s Motion for Summary Judgment On March 8, 2022, CK filed its motion for summary judgment, contending there were no factual disputes regarding its claim that Valley Forge had breached the parties’ contract and it had conclusive evidence that it suffered damages in the amount of $69,606.15. As supporting evidence, CK attached an affidavit from its president, David Kessinger, in which he averred that the parties’ contract called for a “lump sum price of $429,577.62 plus 10% additional combined profit and overhead on additive change orders” and that it further called for a “[f]ive percent retainage” to be withheld on the Project. Kessinger further averred that CK had complied with all of its contractual obligations but that Valley Forge had failed to fulfill its obligation to pay the full amount due under the contract, which he calculated to be $69,166.15, plus $440 for service calls and maintenance repairs. Kessinger attached a copy of a ten-page “Pay Application,” which he asserted “sets out the amounts owing on the Project.” CK also attached a copy of the mechanic’s and materialman’s lien that it filed on the subject property together with its supporting affidavit of lien. And finally, CK attached an affidavit from its attorney stating that CK had hired her firm in this “collection

2 According to CK, the parties’ contract contained no dispute resolution procedures.

action” and that CK had thus far incurred attorney’s fees in the amount of $8,500 “in the attempt to collect the indebtedness of Valley Forge,” which she attested was “reasonable and necessary.”

CK referred to but did not provide a copy of the parties’ contract, any change orders that Valley Forge authorized, any invoices that it sent to Valley Forge, or any of the correspondence between the parties.

C. Valley Forge’s response to the Motion for Summary Judgment Valley Forge filed a timely response to CK’s summary judgment on March 28, 2022, contending that disputed issues of material fact that made summary judgment improper. In particular, Valley Forge argued that it was not in breach of the contract, as it tendered a check for $40,165.38 to CK upon completion of the Project, which it believed was the total amount owed to CK at that time but that CK refused to accept the check. In addition, Valley Forge argued that foreclosure of CK’s lien was improper given the parties’ dispute over the amount of debt—if any— that Valley Forge owed CK.

Valley Forge attached an affidavit to its response from its president, Lee Urias, contending that CK was “incorrect” in stating the terms of the original contract, averring that the original contract was not for $492,577.62 and that it neither contained provisions for a “10% combined profit” nor for a “5% retainage.” Urias further averred that Valley Forge never signed any of the “alleged changes on the project.” As well, Urias contended that it did not owe CK $440 for the service call and repair fees, alleging there was a “warranty” that covered this cost. In addition, Urias attested that Valley Forge had tendered a check to CK for “final payment” in the amount of $40,165.38 after the Project was completed but that Kessenger refused to accept the check, claiming that Valley Forge owed it $51,000 at the time. According to Urias, he attempted to explain to Kessinger that there were “deductions” owed to Valley Forge that had “not been credited

correctly,” but Kessinger “simply refused payment.” Urias also contended that Valley Forge never received an itemized invoice from CK in the amount it is now demanding and that it never refused to pay any such invoice.

Free access — add to your briefcase to read the full text and ask questions with AI

Valley Forge, Inc. v. CK Construction, Inc., (Tex. Ct. App. 2023).

Valley Forge, Inc. v. CK Construction, Inc. (Valley Forge, Inc. v. CK Construction, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Mann Frankfort Stein & Lipp Advisors, Inc. v. Fielding
289 S.W.3d 844 (Texas Supreme Court, 2009)
Frost National Bank v. Fernandez
315 S.W.3d 494 (Texas Supreme Court, 2010)
Rich v. McMullan
506 S.W.2d 745 (Court of Appeals of Texas, 1974)
Llopa, Inc. v. Nagel
956 S.W.2d 82 (Court of Appeals of Texas, 1997)
Mays v. Pierce
203 S.W.3d 564 (Court of Appeals of Texas, 2006)
Hayek v. Western Steel Company
478 S.W.2d 786 (Texas Supreme Court, 1972)
McCulley Fine Arts Gallery, Inc. v. "X" Partners
860 S.W.2d 473 (Court of Appeals of Texas, 1993)
B & W SUPPLY, INC. v. Beckman
305 S.W.3d 10 (Court of Appeals of Texas, 2009)
Deutsch v. Hoover, Bax & Slovacek, L.L.P.
97 S.W.3d 179 (Court of Appeals of Texas, 2003)
SLT Dealer Group, Ltd. v. AmeriCredit Financial Services, Inc.
336 S.W.3d 822 (Court of Appeals of Texas, 2011)
CVN Group, Inc. v. Delgado
95 S.W.3d 234 (Texas Supreme Court, 2002)
II Deerfield Ltd. Partnership v. Henry Building, Inc.
41 S.W.3d 259 (Court of Appeals of Texas, 2001)
Green International, Inc. v. Solis
951 S.W.2d 384 (Texas Supreme Court, 1997)
Harris County Appraisal District v. Reynolds/Texas, J.V.
884 S.W.2d 526 (Court of Appeals of Texas, 1994)
DeLuca v. Munzel
673 S.W.2d 373 (Court of Appeals of Texas, 1984)
Crawford Services, Inc. v. Skillman International Firm, L.L.C.
444 S.W.3d 265 (Court of Appeals of Texas, 2014)
Mark Davis v. Norma Chaparro
431 S.W.3d 717 (Court of Appeals of Texas, 2014)
Usaa Texas Lloyds Company v. Gail Menchaca
545 S.W.3d 479 (Texas Supreme Court, 2018)