Valley Community Preservation Commission v. Mineta

246 F. Supp. 2d 1163, 2002 U.S. Dist. LEXIS 26275, 2002 WL 31994548
CourtDistrict Court, D. New Mexico
DecidedDecember 20, 2002
Docket02-1306 LH/WWD
StatusPublished
Cited by3 cases

This text of 246 F. Supp. 2d 1163 (Valley Community Preservation Commission v. Mineta) is published on Counsel Stack Legal Research, covering District Court, D. New Mexico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Valley Community Preservation Commission v. Mineta, 246 F. Supp. 2d 1163, 2002 U.S. Dist. LEXIS 26275, 2002 WL 31994548 (D.N.M. 2002).

Opinion

*1164 MEMORANDUM OPINION AND ORDER

HANSEN, District Judge.

THIS MATTER comes before the Court on Plaintiffs’ motion for preliminary injunction (Docket No. 6). Plaintiffs Valley Community Preservation Commission, Gerald Joe Ford, Royce Griggs and Troy Omness (“Plaintiffs”) filed suit, seeking to halt construction of a 37.5 mile federal-aid highway project to reconstruct U.S. 70 into a continuous four-lane highway through the Hondo River Valley in Lincoln County, New Mexico. The stretch of road at issue in this litigation is that between Ruidoso Downs and Riverside (“the Project”). This road is presently a rural two-lane highway. Plaintiffs contend that injunc-tive relief is needed to prevent irreparable injury to natural and historic resources, which are directly threatened as a result of imminent construction activities, because Defendants have failed to comply with the requirements of Section 4(f) of the Department of Transportation Act (“Section 4(f)”), 49 U.S.C. § 303, and the National Environmental Policy Act (“NEPA”), 42 U.S.C. § 4332(C). Plaintiffs seek judicial *1165 review of these decisions under the Administrative Procedure Act (“APA”), 5 U.S.C. § 551 et seq. Judicial review under the APA of informal agency adjudications is normally confined to the administrative record. See Florida Power & Light Co. v. Lorion, 470 U.S. 729, 744, 105 S.Ct. 1598, 84 L.Ed.2d 643 (1985).

The Court, having considered the original briefs, the supplemental briefs and arguments of counsel at a hearing on November 20, 2002, concludes that Plaintiffs’ motion for preliminary injunction (Docket No. 6) is not well-taken and will be denied.

I. Procedural Background

This matter was originally filed in the District Court for the District of Columbia on July 31, 2002. On September 26, 2002, that Court (the Honorable Reggie B. Walton) entered a Memorandum Opinion and Order, 2002 WL 31163094 (D.D.C. Sept.26, 2002), transferring this case to the District of New Mexico, denying Plaintiffs’ motion for temporary restraining order, and deferring ruling on Plaintiffs’ motion for preliminary injunction to this Court. Having assessed the arguments advanced by both parties in briefing and a hearing, Judge Walton found that Plaintiffs were not likely to succeed on the merits of any of their claims. Weighing the interests of environmental and cultural resource protection against the interest of protecting human lives, that Court further found that Plaintiffs had failed to establish that the public interest favored the grant of emergency injunctive relief.

This matter was transferred and actually docketed in this Court on October 15, 2002. The Court requested supplemental briefs and scheduled a hearing on this matter for November 13, 2002. - At the behest of both parties, the hearing was postponed until November 20, 2002. 1

At the November 20 hearing, without contradiction from defense counsel, Plaintiffs’ Counsel, Ms. Forster, clarified that only two issues have been raised in the context of this injunctive relief proceeding: a claim raised under § 4(f) of the Department of Transportation Act and a claim under the National Environmental Protection Act 2 , involving a potential conflict of interest of the contractor, Parsons Brinek-erhoff. The Court will accordingly limit its analysis to these two issues.

II. Legal Standards

A. Injunctive Relief

New Mexico, like the District of Columbia, employs the four-part standard for injunctive relief. The variations in this standard, as employed by these two districts, are not material The substantive requirements for a preliminary injunction *1166 and temporary restraining order are identical. Bieros v. Nicola, 857 F.Supp. 445, 446 (E.D.Pa.1994). Under that test, Plaintiffs must show: (1) a substantial likelihood of prevailing on the merits; (2) irreparable harm absent an injunction; (3) the threatened injury outweighs the harm that the preliminary injunction may cause the opposing party; and, (4) issuance of the injunction is in the public interest. Fed. Lands Legal Consortium ex rel. Robarb Estate v. United States, 195 F.3d 1190, 1194 (10th Cir.1999).

B. Review of Agency Action under The Administrative Procedure Act

Neither NEPA nor the Department of Transportation Act provide an independent cause of action and therefore this case falls under the aegis of the Administrative Procedure Act. Under the APA, the Tenth Circuit (as well as the D.C. Circuit 3 ) directs that a court may set aside the Federal Highway Administration’s (“FHWA’s”) decision to implement a highway project only if the Court finds the agency has abused its discretion, or has acted arbitrarily, capriciously, or contrary to the law. See Davis v. Mineta, 302 F.3d 1104, 1111 (10th Cir.2002)(citations omitted).

The Court’s role in reviewing the agency’s decision is not to determine whether it was correct; rather the Court is limited to determining whether the agency’s decision was in compliance with the law. See Associations Working for Aurora’s Residential Environment (“AWARE”) v. Colorado Dept. of Transp., 153 F.3d 1122, 1127 (10th Cir.1998).

C. Review /Analysis of NEPA Claims

NEPA requires that agencies such as FHWA evaluate the impacts of projects they propose prior to deciding to follow any specific course of action. Citizens’ Committee to Save Our Canyons v. U.S. Forest Service, 297 F.3d 1012, 1022 (10th Cir.2002). In discharging its duties under NEPA, the agency must take a “hard look” at environmental consequences of proposed actions. This “hard look” at potential environmental impacts is accomplished through the environmental impact statement process. Id. NEPA does not mandate substantive results or permit the Court to substitute its judgment for that of the agency. Id. Rather, the Court must apply a deferential stand when reviewing the Agency’s actions, reversing only if its actions are “arbitrary, capricious, otherwise not in accordance with the law, or not supported by substantial evidence.” Hoyl v. Babbitt,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
246 F. Supp. 2d 1163, 2002 U.S. Dist. LEXIS 26275, 2002 WL 31994548, Counsel Stack Legal Research, https://law.counselstack.com/opinion/valley-community-preservation-commission-v-mineta-nmd-2002.